Section 890
Section 890.1150 Water
Service Pipe Installation
a) Underground Water Service. Water service pipe shall be
installed outside the foundation wall in accordance with either subsection
(a)(1) or (2) and shall comply with both subsections (a)(3) and (4).
1) Water service and building drain or building sewer may be
installed in separate trenches with a minimum of 10 feet horizontal
separation. Material listed in Appendix A.Table A (Approved Materials for
Building Sewer and Approved Materials for Water Service Pipe) shall be used,
provided that the material is specific for this type of installation. (See
Appendix I.Illustration E.)
2) The water service and the building drain or building sewer may
be installed in the same trench provided that the water service is placed on a
solid shelf a minimum of 18 inches above the building drain or building sewer.
The building sewer shall be of material listed in Appendix A.Table A (Approved
Building Drainage/Vent Pipe) for a building drain. (See Appendix I.Illustration
F for the proper installation of water service, building drain and building
sewer.)
3) The minimum depth for any water service pipe shall be at least
36 inches or the maximum frost penetration of the local area, whichever is of
greater depth.
4) No water service pipe shall be installed or permitted outside
of a building or in an exterior wall unless the pipe is protected from
freezing, in accordance with Section 890.1210(a).
b) Potable Water Piping and Sanitary Sewer Crossing Installation
Requirements
1) Potable water piping that passes above or below a sanitary sewer
shall be installed with a minimum vertical separation of 18 inches for a distance
of 10 feet on either side from the center of the sanitary sewer
wall unless the pipe is protected from
freezing, in accordance with Section 890.1210(a).
b) Potable Water Piping and Sanitary Sewer Crossing Installation
Requirements
1) Potable water piping that passes above or below a sanitary sewer
shall be installed with a minimum vertical separation of 18 inches for a distance
of 10 feet on either side from the center of the sanitary sewer.
2) If potable water piping passes beneath a sanitary sewer or
drain, the sanitary sewer or drain shall be constructed of materials as
specified in Appendix A.Table A (Approved Building Drainage/Vent Pipe) for
building drains and shall extend on each side of the crossing to a distance of
at least 10 feet as measured at right angles to the water line. The potable
water piping shall comply with Appendix A.Table A as specified for a water
service pipe (Approved Materials for Water Service Pipe). (See Appendix I.Illustration
G.)
3) When compliance with subsection (b)(1) or (2) is not possible,
a pressure rated pipe, approved for building drain material listed in Appendix
A.Table A, shall encase the water service pipe. The casing pipe shall be
sealed with a casing seal and extend 10 feet on either side of the center of
the sanitary sewer pipe. The sleeve or case shall be at least two times the
size of the water service.
c) When compliance with subsection (a) or (b) is not possible,
the Department shall be contacted for consideration of alternative methods.
d) Stop-and-Waste Valve. Combination stop-and-waste valves and
cocks shall not be installed in an underground potable water pipe. Frost-free
hydrants and fire hydrants shall not be considered stop-and-waste valves. (See
Section 890.1140(e).)
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.