Section 3702

Section 3702.70  Application

for Permit to Remove Dams – Contents

Application for a permit to

remove a dam shall be made on forms provided by OWR.  Separate applications are

required for each dam.  The application shall include, as a minimum:

a)         Plans and documents, sealed, signed and dated by an engineer,

stating that the design documents have been prepared under the engineer's

personal supervision and are in conformance with this Part.

b)         Computations for design of the method and timing for

dewatering the reservoir.

c)         Design plans and computations to effect the breach, including

size of breach, shape of breach and disposal of spoil material.

d)         Plans and computations for controlling erosion at the site of

the breach during and after the breach.

e)         Computations detailing the effects of the breach on the

channel downstream of the breach.

f)         Plans and computations for restoring the channel upstream of

the breach.

g)         Plans and computations for control of sediment deposits in the

reservoir.

h)         Plans for the restoration of the bed of the reservoir.

i)          Plans for maintenance of the breach, downstream and upstream

channels, and reservoir bed.

j)          A time schedule for initiation and completion of all phases

of the removal of the dam operation.

k)         Agreement of the applicant to provide as-built plans upon

completion of removal.  These plans shall be signed by the engineer or other

qualified personnel who was responsible for inspection during the removal.

l)          Right of access authorization for the OWR to inspect the

breach site and vicinity before, during and after breaching operations and

until restoration of the stream and impacted area is complete.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.