Section 3702
Section 3702.30
Applicability
a) Classification
1) Dams will be categorized in one of three classes, according to
the degree of threat to life and property in the event of a dam failure. The
three classes of dams are:
A) Class I − Dams located where failure has a high
probability for causing loss of life or substantial economic loss in excess of
that which would naturally occur downstream of the dam if the dam had not
failed. A dam has a high probability for causing loss of life or substantial
economic loss if it is located where its failure may cause additional damage to
such structures as a home, a hospital, a nursing home, a highly traveled
roadway, a shopping center, or similar type facilities where people are
normally present downstream of the dam. This is similar to U.S. Army Corps of
Engineers HIGH HAZARD POTENTIAL category as defined in the Corps Guidelines,
and the U.S. Soil Conservation Service Class (c) dams as defined in Soil
Conservation Service Technical Release No. 60.
B) Class II – Dams located where failure has a moderate
probability for causing loss of life or may cause substantial economic loss in
excess of that which would naturally occur downstream of the dam if the dam had
not failed. A dam has a moderate probability for causing loss of life or
substantial economic loss if it is located where its failure may cause
additional damage to such structures as a water treatment facility, a sewage
treatment facility, a power substation, a city park, a U.S. Route or Illinois
Route highway, a railroad or similar type facilities where people are
downstream of the dam for only a portion of the day or on a more sporadic
basis. This is similar to U.S. Army Corps of Engineers SIGNIFICANT HAZARD
POTENTIAL category and the U.S. Soil Conservation Service Class (b) dams
atment facility, a sewage
treatment facility, a power substation, a city park, a U.S. Route or Illinois
Route highway, a railroad or similar type facilities where people are
downstream of the dam for only a portion of the day or on a more sporadic
basis. This is similar to U.S. Army Corps of Engineers SIGNIFICANT HAZARD
POTENTIAL category and the U.S. Soil Conservation Service Class (b) dams.
C) Class III – Dams located where failure has low probability for
causing loss of life, where there are no permanent structures for human
habitation, or minimal economic loss in excess of that which would naturally
occur downstream of the dam if the dam had not failed. A dam has a low
probability for causing loss of life or minimal economic loss if it is located
where its failure may cause additional damage to agricultural fields, timber
areas, township roads or similar type areas where people seldom are present and
where there are few structures. This corresponds to U.S. Army Corps of
Engineers LOW HAZARD POTENTIAL category and U.S. Soil Conservation Service
Class (a) dams.
2) Dams will be categorized in one of three size
classifications. The size classifications shall be based on dam height and
impounding capacity. If either the height or impounding capacity meets the
minimum requirement for the larger size, the dam will be classified in the
larger size category.
CLASSIFICATION
IMPOUNDING
CAPACITY
ACRE-FEET
DAM HEIGHT FEET
Small
< 1,000
< 40
Intermediate
> 1,000
to
<
50,000
> 40 to
< 100
Large
>
50,000
> 100
b) New
Dams
1) Class I and II Dams
The owner of a
proposed Class I or II dam shall obtain an OWR permit prior to the start of
construction. The owner must do all construction and maintenance of the dam in
accordance with this Part, as it applies to Class I or II dams
FEET
DAM HEIGHT FEET
Small
< 1,000
< 40
Intermediate
> 1,000
to
<
50,000
> 40 to
< 100
Large
>
50,000
> 100
b) New
Dams
1) Class I and II Dams
The owner of a
proposed Class I or II dam shall obtain an OWR permit prior to the start of
construction. The owner must do all construction and maintenance of the dam in
accordance with this Part, as it applies to Class I or II dams.
2) Class III Dams
A) The owner of a proposed Class III dam shall obtain an OWR
permit prior to the start of construction if the dam meets any of the following
criteria:
i) the drainage area of the proposed dam is 6400 acres or more
in a rural area or 640 acres or more in an urban area; or
ii) the dam is 25 feet or more in height, provided that the
impounding capacity is greater than 15 acre-feet; or
iii) the dam has an impounding capacity of 50 acre-feet or more,
provided that the dam height is greater than 6 feet.
B) If a permit is required for the Class III dam under any of
these criteria, then the owner must do all construction and maintenance of the
dam in accordance with this Part, as it applies to Class III dams.
c) Existing Dams
The owner of a
dam that was permitted and built in compliance with an OWR permit before
September 2, 1980 and that is currently in good repair shall not be required,
except in compliance with Section 3702.150 or 3702.190, to make changes in the
design, structure or construction of the dam. The owner of a dam that was
permitted and built before September 2, 1980, but is not in accordance with the
OWR permit or is not in good repair, shall be required to meet all current
standards for existing dams. The owner of a dam built after September 2, 1980
shall be required to meet all standards for proposed dams existing at the time
of its construction. Operation, maintenance, inspection and financial responsibility
standards must be complied with at all dams
ut is not in accordance with the
OWR permit or is not in good repair, shall be required to meet all current
standards for existing dams. The owner of a dam built after September 2, 1980
shall be required to meet all standards for proposed dams existing at the time
of its construction. Operation, maintenance, inspection and financial responsibility
standards must be complied with at all dams.
1) Class I and II Dams
A) OWR has developed an inventory of dams in Illinois. OWR and
federal agencies have conducted and are conducting inspections of existing dams
having a potential for loss of life or property damage in case of a dam
failure. As inspection reports are completed, OWR will furnish in writing to
the owner of the dam a detailed and specific list of defects discovered in the
course of the inspection of the dam, including the specific nature of any
inadequacies of the capacity of the spillway system and any indications of
seepage, erosion or other evidence of structural deficiency in the dam or
spillway, together with a statement of the applicable standards of this Part
that, if complied with by the owner of the dam, will put the dam into
compliance with this Part.
B) If an inspection by OWR, or in which OWR concurs, finds that a
dam is in an unsafe condition, OWR will notify the appropriate officials of the
affected city or county, the State's Attorney of the county in which the dam is
located, and the Illinois Emergency Management Agency (IEMA), and will assist
IEMA in any emergency actions deemed necessary by IEMA.
C) OWR will notify the owner of an inspected dam if the owner must
obtain a permit or amendment to an existing permit for the dam. Separate
permit applications are required for each dam
ty or county, the State's Attorney of the county in which the dam is
located, and the Illinois Emergency Management Agency (IEMA), and will assist
IEMA in any emergency actions deemed necessary by IEMA.
C) OWR will notify the owner of an inspected dam if the owner must
obtain a permit or amendment to an existing permit for the dam. Separate
permit applications are required for each dam.
D) If an existing Class I or II dam has been inspected and found
to have serious deficiencies requiring major modifications, within 90 days
after receipt of notice from OWR that a permit or amendment to an existing
permit is required under this Part, the owner of the dam must provide written
assurance to OWR of the following: the owner's intention to rectify the
deficiencies noted, the date the owner will submit a completed permit
application, the time frame for initiating and completing the appropriate remedial
measures, and the methods and designs to be used for the remedial measures.
E) If an existing Class I or II dam has been inspected and found
to have no serious deficiencies requiring major modifications, OWR will notify
the owner of the dam that it must submit, within 90 days, a permit application
including the following, if the following has not been previously provided to
OWR:
i) an Operating Plan (Section 3702.40(b)(4));
ii) a Maintenance Plan (Section 3702.40(b)(5));
iii) a Financial Responsibility Statement (Section 3702.40(b)(6));
and
iv) a Right of Access Statement (Section 3702.40(b)(7)(A)).
F) An owner initiating major modifications to an existing Class I
or Class II dam must obtain a new permit or amendment to an existing permit prior
to the initiation of the modifications
;
ii) a Maintenance Plan (Section 3702.40(b)(5));
iii) a Financial Responsibility Statement (Section 3702.40(b)(6));
and
iv) a Right of Access Statement (Section 3702.40(b)(7)(A)).
F) An owner initiating major modifications to an existing Class I
or Class II dam must obtain a new permit or amendment to an existing permit prior
to the initiation of the modifications.
2) Class III Dams
A) Using the inventory of dams or other similar information, OWR,
over a period of time, upon receipt of a complaint or upon its own
investigation, may contact owners of those existing Class III dams that:
i) have a drainage area of 6400 acres or more in a rural area or
640 acres or more in an urban area; or
ii) are 25 feet or more in height, provided that the impounding
capacity is greater than 15 acre-feet; or
iii) have an impounding capacity of 50 acre-feet or more, provided
that the dam height is greater than 6 feet.
B) OWR will inform the owners of the dams that they must submit to
OWR a maintenance program and a statement indicating actions to be taken to
remedy the noted deficiencies.
C) If an inspection by OWR, or in which OWR concurs, finds that a
dam is in an unsafe condition, OWR will notify the appropriate officials of the
affected city or county, the State's Attorney of the county in which the dam is
located, and IEMA.
D) Owners of existing Class III dams in locations where there is
potential for downstream urban development, which could cause a change in dam
classification in the foreseeable future, when so notified by OWR, shall be
required to report annually the existing land uses downstream of the dam.
Extent of downstream land use to be reported is dependent upon factors such as
slope and width of flood plain and density and intensity of downstream
development. Extent downstream will not exceed 2 miles unless otherwise
indicated by OWR
dam
classification in the foreseeable future, when so notified by OWR, shall be
required to report annually the existing land uses downstream of the dam.
Extent of downstream land use to be reported is dependent upon factors such as
slope and width of flood plain and density and intensity of downstream
development. Extent downstream will not exceed 2 miles unless otherwise
indicated by OWR. The owner may provide information indicating that an extent
downstream shorter than 2 miles is appropriate. The width of flood plain shall
be the width of the area inundated by the 100-year flood.
E) Owners of Class III dams desiring to make major modifications
to their dams shall obtain an OWR permit or an amendment to an existing OWR
permit for the work prior to the initiation of the modifications.
d) Designation by OWR of Dam Classification
Before
assigning or changing the dam classification for a new or existing dam, OWR
shall give notice and opportunity for hearing pursuant to Section 3702.170 to
the applicant or existing dam owner and other interested persons of that
action.
1) Initial Assignment of Dam Classification
A) New Dams
The
classification of new dams will be based upon information available to OWR. This
information includes, but is not limited to, USGS quadrangle maps of the
downstream area, the preliminary report and support data from the owner's
engineer, known elevations of structures downstream of the proposed dam,
information from the public, and previous study data. This information is
available from OWR data and data supplied by the owner's engineer, the public
and federal or State agencies. The owner of the proposed dam shall submit
information to establish the degree of threat to life and property damage in
the event of a dam failure.
B) Existing Dams
i) The classification of existing dams that have been inspected
by the U.S
udy data. This information is
available from OWR data and data supplied by the owner's engineer, the public
and federal or State agencies. The owner of the proposed dam shall submit
information to establish the degree of threat to life and property damage in
the event of a dam failure.
B) Existing Dams
i) The classification of existing dams that have been inspected
by the U.S. Army Corps of Engineers, other federal agencies, or OWR will be
based upon that agency's inspection report.
ii) The classification of existing dams that have not been
inspected by a federal agency or OWR but that have had major modifications
proposed by the dam owner will be processed as new dams in accordance with subsection
(d)(1)(A).
2) Change in Dam Classification
Upon receipt
and verification of information indicating that significant change in the
degree of threat to life or property from a dam failure has occurred since the
dam's original classification, the classification of that dam shall be changed
to reflect the new hazard potential. Upon reclassification, the dam owner
shall be subject to the applicable dam safety requirements for the current
classification (subsection (c)).
e) Removal of Dams
The owner of a
Class I, II or III dam who wishes to remove a dam shall obtain, prior to the
initiation of the dam removal, an OWR permit to remove the dam in accordance
with Section 3702.50 governing the removal of dams.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.