Section 3702.50 Requirements for Approval of Permits for Removal of Dams
IllinoisRegulations
Ask Donna
How this section applies to your facts.
Illinois Administrative Code › Title 17 CONSERVATION › CHAPTER I: DEPARTMENT OF NATURAL RESOURCES › Part 3702 CONSTRUCTION AND MAINTENANCE OF DAMS › Section 3702.50 Requirements for Approval of Permits for Removal of Dams
Text
Section 3702
Section 3702.50 Requirements
for Approval of Permits for Removal of Dams
a) Dependent upon the size, height, reservoir impounding
capacity, upstream and downstream channel conditions, existing reservoir
sediment deposits, degree of hazard in case of failure, as well as any other
considerations which might be peculiar to a particular dam, the following OWR
requirements shall be met unless the applicant establishes that one or more
specific requirements for a permit to remove a dam are not applicable.
b) A reasonable method to accomplish the following requirements
will be accepted. It is strongly recommended that applicants contact OWR prior
to initiation of studies and at any time during the development of the permit
application if questions should arise.
1) Reservoir Dewatering – The reservoir shall be dewatered with a
method and timing such that the downstream channel shall not overflow to a
degree to cause damage.
2) Effecting Breach – A breach shall be made in such a manner as
to be safe under all reasonably anticipated storm events.
3) Size of Breach – The waterway cross sectional area of the
final breach shall be sufficient to at least pass the 100-year frequency flood
with negligible backwater effect.
4) Control of Erosion at Site of Breach During and After
Breaching Operations – Erosion of the dam embankment and adjacent area shall be
controlled during and after breaching operations by proper breach procedure,
use of appropriate structural measures, and necessary maintenance measures
thereafter.
5) Downstream Channel Impacts – Effects of the breach on the
downstream channel shall be assessed. Increases in water levels downstream of
the breach over that which occurred prior to construction of the dam shall be
negligible unless the owner can show that no damage results from such
increases
,
use of appropriate structural measures, and necessary maintenance measures
thereafter.
5) Downstream Channel Impacts – Effects of the breach on the
downstream channel shall be assessed. Increases in water levels downstream of
the breach over that which occurred prior to construction of the dam shall be
negligible unless the owner can show that no damage results from such
increases. If increases in water levels are not negligible or if damage can
result from the breach, OWR will require the owner to mitigate such damages.
6) Restoration of Original Channel Upstream of Breach – The
original channel shall be restored, or an alternate channel shall be required
to provide flows approximating the original flow regime (restoration to the
extent possible, of the channel and stream flows to original conditions prior
to construction of the dam) through the bed of the reservoir from the breach to
the upstream end of the area impacted by the reservoir.
7) Control of Sediment Deposits in Reservoir – Measures shall be
undertaken to minimize movement of reservoir sediment deposits through the
breach.
8) Restoration of Reservoir Lake Bed – The bed of the reservoir
within the 100-year flood plain shall be restored to a condition whereby it can
serve a reasonable flood plain use.
9) Plan for Maintenance – A plan for providing regular
maintenance of the breach, outlet channel, inlet channel, and reservoir bed
will be required by OWR, for the period of time necessary to establish plant
cover or other erosion and sedimentation control.