Rev. Proc. 2017-19

FederalIRS revenue procedures

Ask Donna

How this section applies to your facts.

Internal Revenue Bulletin › IRB 2017 › Revenue Procedure › Rev. Proc. 2017-19

This text was captured on Aug 14, 2026. It is a snapshot, not a live feed, so check the official code before relying on it.

Text

Rev. Proc. 2017-19

SECTION 1. PURPOSE

This revenue procedure provides a safe harbor under which the Internal

Revenue Service (Service) will not challenge the treatment of an Energy

Savings Performance Contract (ESPC) Energy Sales Agreement (ESA)

between an Energy Service Company (ESCO) and a Federal Agency (FA)

as a service contract under § 7701(e)(3) of the Internal Revenue Code

(Code). The revenue procedure also provides an example of an ESPC

ESA.

SECTION 2. BACKGROUND

.01. 42 U.S.C § 8287 authorizes FAs to enter into ESPC ESAs with

ESCOs for the purpose of achieving energy savings and benefits ancillary

to energy savings. It also sets forth certain requirements for such ESPC

ESAs. The ESPC ESA project structure is intended to facilitate onsite

renewable energy generation projects.

.02. The Office of Management and Budget (OMB) issued OMB

Memorandum M-12-21 to provide further guidance to FAs regarding

ESPCs that include third-party owned and operated onsite renewable

energy generation assets and how they will be treated for Federal

budgeting purposes. Specifically, OMB Memorandum M-12-21 requires

title to the renewable energy generation asset to transfer to the FA at the

end of the ESPC term.

.03. The ESPC ESA is a type of ESPC that facilitates third-party owned

and operated onsite energy generation projects in compliance with ESPC

authority and OMB Memorandum M-12-21. An ESPC ESA may also

include the implementation of other energy and water conservation

measures as part of a comprehensive project.

able energy generation asset to transfer to the FA at the

end of the ESPC term.

.03. The ESPC ESA is a type of ESPC that facilitates third-party owned

and operated onsite energy generation projects in compliance with ESPC

authority and OMB Memorandum M-12-21. An ESPC ESA may also

include the implementation of other energy and water conservation

measures as part of a comprehensive project.

2

.04. The example in Section 5 of this revenue procedure illustrates a

typical ESPC ESA that would satisfy the requirements of 42 U.S.C § 8287

and OMB Memorandum M-12-21.

.05. Section 48(a) provides for an investment tax credit for certain energy

property, including solar energy property described in § 48(a)(3)(A)(i).

.06. Section 50(b)(4)(A)(i) disallows the investment tax credit if the

property is used by the United States, any State or political subdivision

thereof, any possession of the United States, or any agency or

instrumentality of any of the foregoing. This disallowance applies to

property used under a lease unless the term of such lease is less than 6

months.

.07. Section 7701(e) provides rules to determine, for federal income tax

purposes, whether a contract that purports to be a service contract should

be treated as a lease of property. Section 7701(e)(1) generally provides

that a service contract will be treated as a lease of property if it is properly

treated as a lease of property, taking into account all relevant factors

including whether or not:

the service recipient is in physical possession of the property;

the service recipient controls the property;

the service recipient has a significant economic or possessory

interest in the property;

the service provider does not bear any risk of substantially diminished

receipts or substantially increased expenditures if there is

nonperformance under the contract;

the service provider does not use the property concurrently to provide

significant services to entities unrelated to the service recipient; and

the total con

has a significant economic or possessory

interest in the property;

the service provider does not bear any risk of substantially diminished

receipts or substantially increased expenditures if there is

nonperformance under the contract;

the service provider does not use the property concurrently to provide

significant services to entities unrelated to the service recipient; and

the total contract price does not substantially exceed the rental value

of the property for the contract period.

3

.08. Notwithstanding the general rule of § 7701(e)(1), § 7701(e)(3)

provides special rules for contracts or arrangements involving solid waste

disposal, a cogeneration or alternative energy facility, and clean water

facilities. Section 7701(e)(3)(D) provides that an “alternative energy facility”

means a facility producing electrical or thermal energy if the primary energy

source for the facility is not oil, natural gas, coal or nuclear power. Section

7701(e)(3)(A) provides that a purported service contract with respect to this

type of facility will be treated as a service contract.

.09. Section 7701(e)(4) provides that the special rule in § 7701(e)(3) will

not apply, and thus the general rule in § 7701(e)(1) will apply, to any

contract with respect to the facilities described in § 7701(e)(3) if:

the service recipient (or a related entity) operates the facility;

the service recipient (or a related entity) bears any significant

financial burden if there is nonperformance under the contract, unless

this burden is due to (i) reasons beyond the control of the service

provider, (ii) a temporary shut-down for repairs, maintenance, or

capital improvements, or (iii) the bankruptcy or other financial

difficulty of the service provider;

the service recipient (or a related entity) receives any significant

financial benefit if the operating costs of such facility are less than the

standards of performance or operation under the contract, unless the

benefit arises from reduced payments by the service

repairs, maintenance, or

capital improvements, or (iii) the bankruptcy or other financial

difficulty of the service provider;

the service recipient (or a related entity) receives any significant

financial benefit if the operating costs of such facility are less than the

standards of performance or operation under the contract, unless the

benefit arises from reduced payments by the service recipient

because of increased production or efficiency or the recovery of

energy or other products; and

the service recipient (or a related entity) has an option or obligation to

purchase all or part of the facility at a fixed and determinable price,

other than for the fair market value of the facility.

SECTION 3. SCOPE

.01. The safe harbor in section 4 of this revenue procedure applies to any

ESPC ESA between an ESCO and a FA for the provision of electricity

through an alternative energy facility, as defined in § 7701(e)(3)(D), that

4

satisfies the requirements of 42 U.S.C § 8287 and OMB Memorandum M-

12-21. It may not be relied upon, in whole or part, for any other kind of

transaction.

.02. The safe harbor provided in section 4 of this revenue procedure

applies only if all the requirements of section 4 are satisfied.

.03. The safe harbor provided in section 4 of this revenue procedure

provides guidance to ESCO taxpayers that are establishing or participating

in an ESPC ESA with a FA in lieu of providing a letter ruling to those ESCO

taxpayers. Therefore, the Service will not rule on whether an ESPC ESA

between an ESCO and FA will be considered a service contract under §

7701(e)(3).

SECTION 4. SAFE HARBOR

.01 Safe harbor. If an ESPC ESA entered into between an ESCO and a FA

satisfies all of the requirements of section 4.02 of this revenue procedure,

the Service will not challenge the treatment of the ESPC ESA as a service

contract under § 7701(e)(3).

.02 Requirements. The ESPC ESA must satisfy the following

requirements:

d a service contract under §

7701(e)(3).

SECTION 4. SAFE HARBOR

.01 Safe harbor. If an ESPC ESA entered into between an ESCO and a FA

satisfies all of the requirements of section 4.02 of this revenue procedure,

the Service will not challenge the treatment of the ESPC ESA as a service

contract under § 7701(e)(3).

.02 Requirements. The ESPC ESA must satisfy the following

requirements:

(1) Term. The total term of the ESPC ESA cannot exceed 20 years in

length. The term must be consistent with and appropriate for the scope and

scale of the renewable project.

(2) Other Federal guidance. The ESPC ESA must satisfy the requirements

of 42 U.S.C § 8287 and OMB Memorandum M-12-21.

(3) Operation of Alternative Energy Facility. Under no circumstances will

the FA attempt to operate the renewable energy generation asset. In the

event of a shut-down or mechanical issue, FA will immediately notify the

ESCO or its designated contractor.

(4) Risk. The ESCO bears all financial risk for non-performance, except to

the extent such non-performance is attributable to a temporary shut-down

of the facility for repairs, maintenance, or capital improvements.

5

(5) Reduced Costs. The contract price for electricity will not be reduced if

operating costs should diminish.

(6) Equipment Purchase. The FA may have the option to purchase, or may

be required to purchase, the renewable energy generation asset at the end

of the contract term, for its fair market value (FMV) at the time of the

purchase.

SECTION 5. EXAMPLE

ESCO contracts with FA under an ESPC ESA to install, maintain ownership

of (until the end of the contract), and provide operation and maintenance of

a renewable energy generation asset at a federal site. The FA will

purchase all of the electricity generated onsite at a rate that is less than the

FA’s current and forecasted electricity rate.

• The contract term is 20 years

ECTION 5. EXAMPLE

ESCO contracts with FA under an ESPC ESA to install, maintain ownership

of (until the end of the contract), and provide operation and maintenance of

a renewable energy generation asset at a federal site. The FA will

purchase all of the electricity generated onsite at a rate that is less than the

FA’s current and forecasted electricity rate.

• The contract term is 20 years.

• The contract price, including operation and maintenance, is

based on a fixed per-kWh basis and must be paid for by the FA

from the energy savings provided under the project.

o The ESCO bears all financial risk for non-performance.

o The contract price does not vary if the operating costs are

lower than expected.

• The FA will purchase the renewable energy generation asset at

FMV as appraised at the time of the sale by the end of the

contract term, consistent with OMB Memorandum 12-21.

o The ESCO will transfer a portion of the payments it

receives from the FA into a reserve account held by the

ESCO for the FA’s future purchase of the onsite

renewable energy assets. The amount charged for each

payment period will include both the price of power and

an amount for the reserve account (separate and in

addition to the price of power).

o The ESCO’s deposit into the reserve account will be

based on the estimated future FMV of the on-site

renewable energy generation assets. To ensure that the

reserve account has sufficient funds for the FMV

purchase by the FA at the end of the contract term, there

may be periodic reappraisals of the onsite renewable

for the reserve account (separate and in

addition to the price of power).

o The ESCO’s deposit into the reserve account will be

based on the estimated future FMV of the on-site

renewable energy generation assets. To ensure that the

reserve account has sufficient funds for the FMV

purchase by the FA at the end of the contract term, there

may be periodic reappraisals of the onsite renewable

6

assets and contract modifications (if and as necessary).

Any excess reserve account funds after the onsite

renewable asset purchase may be used to offset the final

ESPC ESA payments. Alternatively, in the event of

termination, funds in the reserve account at that time may

be used to satisfy any termination liability of the FA, and

any excess amounts will be returned to the FA.

o The FMV will be determined at the time of sale by a

mutually agreed upon independent appraiser with

expertise in the relevant onsite renewable energy asset

industry. The valuation made by the appraiser shall be

binding upon the parties in the absence of fraud or error.

• The ESPC ESA includes a schedule for each year which

establishes the maximum termination liability of the FA in the

event of termination prior to the end of the contract term.

This ESPC ESA satisfies the requirements of the safe harbor in section 4 of

this revenue procedure and the Service will not challenge the treatment of

the ESPC ESA as a service contract under § 7701(e)(3).

SECTION 6. EFFECTIVE DATE

This revenue procedure is effective for transactions entered into on or after

the date of publication in the Internal Revenue Bulletin. If an ESPC ESA

entered into between an ESCO and a FA prior to this date satisfies all of

the requirements of the safe harbor provided in section 4 of this revenue

procedure, the Service will not challenge the treatment of the ESPC ESA

as a service contract under § 7701(e)(3).

SECTION 7

ective for transactions entered into on or after

the date of publication in the Internal Revenue Bulletin. If an ESPC ESA

entered into between an ESCO and a FA prior to this date satisfies all of

the requirements of the safe harbor provided in section 4 of this revenue

procedure, the Service will not challenge the treatment of the ESPC ESA

as a service contract under § 7701(e)(3).

SECTION 7. DRAFTING INFORMATION

The principal author of this revenue procedure is Philip Tiegerman of the

Office of Associate Chief Counsel (Passthroughs & Special Industries). For

further information regarding this revenue procedure contact Philip

Tiegerman at (202) 317-6853.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.