Opinion

Boone Coleman Construction, Inc. v. Village of Piketon

  • 145 Ohio St. 3d 450
  • 50 N.E.3d 502
  • 2016 Ohio 628
Court
Ohio Supreme Court
Filed
Feb 24, 2016
Status
Published
Author
Pfeifer
On the bench
French, Kennedy, Lanzinger, O'Connor, O'Donnell, O'Neill, Pfeifer
Cited by
36 cases

explaining that Boone Coleman Construction submitted the lowest bid, was hired for the project, and then the parties entered into a written contract

How later courts described this case

  • explaining that Boone Coleman Construction submitted the lowest bid, was hired for the project, and then the parties entered into a written contract
  • explaining that the interpretation of a contract is a question of law that courts review de novo.

Written by the judges who cited it.

The opinion

Pfeifer, J.,

dissenting.

{¶ 45} We should dismiss this case as having been improvidently accepted and allow the court of appeals decision to stand. That court reached a sound and proper conclusion that is fair to both parties. Furthermore, no new legal issue is at stake.

{¶ 46} Instead, this court has taken a bad situation and made it worse. Boone Coleman already suffered a loss from performing additional work for which it was not paid. On top of that, this court now determines that Boone Coleman must pay a penalty because it didn’t complete the contract on time, never mind that Boone Coleman claims that part of the problem was that Piketon provided inaccurate site information. This is akin to frontier justice: we do it because we can, not because it makes sense.

{¶ 47} Barring a dismissal, the sensible approach to this case, the approach taken by the court of appeals, is to declare the liquidated-damages clause to be unreasonable and disproportionate. Equities do matter — even in a contract case. Given the circumstances of this case, which include Piketon allegedly providing inaccurate site plans to Boone Coleman, the court of appeals got it right. It disallowed Boone Coleman’s requests for additional payment because they were not properly submitted and refused to enforce the liquidated-damages clause because it was so unreasonable and disproportionate as to amount to a penalty.

{¶ 48} Because the court is neither dismissing the ease nor affirming the court of appeals, I dissent.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.