Boone Coleman Construction, Inc. v. Village of Piketon

  • 145 Ohio St. 3d 450
  • 50 N.E.3d 502
  • 2016 Ohio 628
Court
Ohio Supreme Court
Filed
Feb 24, 2016
Status
Published
On the bench
French, Kennedy, Lanzinger, O'Connor, O'Donnell, O'Neill, Pfeifer
Cited by
36 cases
Authority
More cited than 43.1%

explaining that Boone Coleman Construction submitted the lowest bid, was hired for the project, and then the parties entered into a written contract

How later courts described this case

  • explaining that Boone Coleman Construction submitted the lowest bid, was hired for the project, and then the parties entered into a written contract
  • explaining that the interpretation of a contract is a question of law that courts review de novo.

Written by the judges who cited it.

The opinion

[Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as

Piketon v. Boone Coleman Constr., Inc., Slip Opinion No. 2016-Ohio-628.]

NOTICE

This slip opinion is subject to formal revision before it is published in an

advance sheet of the Ohio Official Reports. Readers are requested to

promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65

South Front Street, Columbus, Ohio 43215, of any typographical or other

formal errors in the opinion, in order that corrections may be made before

the opinion is published.

SLIP OPINION NO. 2016-OHIO-628

BOONE COLEMAN CONSTRUCTION, INC., APPELLEE, v. THE VILLAGE OF

PIKETON, APPELLANT.

[Until this opinion appears in the Ohio Official Reports advance sheets, it

may be cited as Piketon v. Boone Coleman Constr., Inc., Slip Opinion No.

2016-Ohio-628.]

Contracts―Public works―Enforceable liquidated-damages clause distinguished

from unenforceable penalty―Samson Sales tripartite test

applied―Provision for liquidated damages of $700 per day for delay of

completion upheld―Reasonableness of provision determined by per diem

amount rather than aggregate amount of damages assessed―If provision

was reasonable at the time of formation and bears reasonable relation to

actual damages, provision will be enforced.

(No. 2014-0978—Submitted June 9, 2015—Decided February 24, 2016.)

APPEAL from the Court of Appeals for Pike County,

No. 13CA836, 2014-Ohio-2377.

_____________________

SUPREME COURT OF OHIO

O’CONNOR, C.J.

{¶ 1} In this appeal arising from a public-road-construction contract, we

consider our precedent on contractual liquidated-damages provisions. We

expressly extend that precedent to public-works contracts, vacate the judgment of

the court of appeals, and remand this cause to that court for reconsideration in light

of our opinion.

RELEVANT BACKGROUND

{¶ 2} In 2007, appellant, the village of Piketon, solicited bids for the “Pike

Hill Roadway and Related Improvements” project. The project included the

installation of a traffic light at the intersection of U.S. Route 23 and Market Street

in Piketon and improvements to the roadway.

{¶ 3} Appellee, Boone Coleman Construction, Inc., submitted the lowest

bid and was hired for the project. The parties entered into a contract in which

Piketon agreed to pay Boone Coleman $683,300 to complete the work. The contract

expressly provided that the time for completing the project was “of the essence”1

1

The relevant provisions of the contract stated:

ARTICLE 4—CONTRACT TIMES

4.01. Time of the Essence

A. All time limits for Milestones, if any, Substantial Completion, and

completion and readiness for final payment as stated in the Contract Documents

are of the essence of the Contract.

4.02 Days to Achieve Substantial Completion and Final Payment

A. The Work will be substantially completed within 120 days after the

date when the Contract Times commence to run as provided in paragraph 2.03 of

the General Conditions, and completed and ready for final payment in accordance

with paragraph 14.07 of the General Conditions within 120 days after the date

when the Contract Times commence to run.

4.03 Liquidated Damages

A. CONTRACTOR and OWNER recognize that time is of the essence

of this Agreement and that OWNER will suffer financial loss if the Work is not

completed within the time(s) specified in paragraph 4.02 above, plus any

extensions thereof allowed in accordance with Article 12 of the General

Conditions. The parties also recognize the delays, expense, and difficulties

involved in proving in a legal or arbitration [proceeding] the actual loss suffered

2

January Term, 2016

and that the project had to be substantially completed within 120 days of the date

of commencement of the project. A liquidated-damages provision made clear that

Boone Coleman would pay $700 to Piketon for each day after the specified

completion date that the contract was not substantially completed.

{¶ 4} The date of commencement of the project was set for July 30, 2007.

Thus, the contract required that the project be substantially completed 120 days

later on November 27, 2007. Piketon granted Boone Coleman’s first request for an

extension, which moved the completion date to May 30, 2008. But when Boone

Coleman sought another extension, Piketon refused to grant it and notified Boone

Coleman that it would assess the contractually specified liquidated damages of

$700 per day if the project was not completed by May 30, 2008. Boone Coleman

did not do so, and on July 7, 2008, Piketon informed Boone Coleman that it was

assessing damages of $700 per day, as of May 31, 2008, until the completion of the

project.

{¶ 5} Boone Coleman did not complete the project until July 2, 2009―well

over a year (397 days) after the parties’ extended completion date of May 30, 2008.

{¶ 6} Boone Coleman brought suit against Piketon in the Pike County

Common Pleas Court. Among other things, it alleged that Piketon had improperly

by OWNER if the Work is not completed on time. Accordingly, instead of

requiring any such proof, OWNER and CONTRACTOR agree that as liquidated

damages for delay (but not as a penalty), CONTRACTOR shall pay OWNER

$700.00 for each day that expires after the time specified in paragraph 4.02 for

Substantial Completion until the Work is substantially complete.

(Boldface, underlining, and capitalization sic.)

3

SUPREME COURT OF OHIO

failed to pay $147,477 of the contract price for the construction.2 Piketon

counterclaimed for liquidated damages.

{¶ 7} Piketon moved for summary judgment. The trial court granted

Piketon’s motion and entered judgment in its favor, awarding Piketon $277,900 in

liquidated damages.

{¶ 8} Boone Coleman appealed, asserting that the trial court erred in

awarding Piketon liquidated damages. The appellate court agreed. Citing our

decision in Samson Sales, Inc. v. Honeywell, Inc., 12 Ohio St.3d 27, 465 N.E.2d

392 (1984), it held, “[W]hen we view the contract as a whole in its application, we

conclude the amount of damages is so manifestly unreasonable and

disproportionate that it is plainly unrealistic and inequitable.” (Emphasis added.)

2014-Ohio-2377, 13 N.E.3d 1190, at ¶ 40. It concluded that because the “resulting

amount [of liquidated damages] is manifestly inequitable and unrealistic, courts are

justified in determining the provision to be an unenforceable penalty.” Id. at ¶ 43,

citing Samson Sales at 28. It reversed that portion of the trial court’s judgment and

remanded for further proceedings.

{¶ 9} We granted Piketon’s request for discretionary review and agreed to

address two related propositions of law:

2

In its complaint, Boone Coleman asserted that the liquidated-damages provision was a penalty and

also argued that it should have been awarded additional compensation based on work it performed

to correct subsurface road problems and to perform revisions on the retaining wall and traffic signal.

The trial court denied that relief and the appellate court affirmed, holding that “Boone Coleman did

not follow the parties’ unambiguous notice provisions to claim additional compensation. And the

contract explicitly precluded recovery for additional costs related to subsurface conditions

encountered by Boone Coleman.” 2014-Ohio-2377, ¶ 4. Nevertheless, the dissenting opinion

asserts, “Boone Coleman already suffered a loss from performing additional work for which it was

not paid” and seemingly gives credence to Boone Coleman’s claim that Piketon provided inaccurate

site information. It seems, then, that the dissent’s insistence on adhering to its own conclusion,

without regard to the facts of this case or the law controlling it, is where “frontier justice” comes

into play. In any event, Boone Coleman did not seek this court’s review of the holdings that it had

been paid properly, and it is therefore not discussed further in this opinion.

4

January Term, 2016

When evaluating the enforceability of a liquidated damages

provision in a construction contract, the court must conduct its

analysis prospectively, based on the per diem amount of the

liquidated damages at the time the contract is executed, and not

retrospectively, based on the total liquidated damages that

ultimately accrue.

Liquidated damages are not deemed a penalty simply

because a project consists of new construction of an improvement

that did not exist previously and no proof of actual damages is

required to enforce liquidated damages pursuant to such a contract.

140 Ohio St.3d 1451, 2014-Ohio-4414, 17 N.E.3d 598.

ANALYSIS

Standard of Review for Contractual Liquidated-Damages Provisions

{¶ 10} We review the interpretation of a contract, a question of law, de

novo. Arnott v. Arnott, 132 Ohio St.3d 401, 2012-Ohio-3208, 972 N.E.2d 586,

¶ 14. Similarly, the question of whether a contract clause provides for liquidated

damages or an unenforceable penalty is a question of law that we also review de

novo. Lake Ridge Academy v. Carney, 66 Ohio St.3d 376, 380, 613 N.E.2d 183

(1993).

Substantive Law on Liquidated Damages

{¶ 11} Simply stated, liquidated damages are damages that the parties to a

contract agree upon, or stipulate to, as the actual damages that will result from a

future breach of the contract. Sheffield-King Milling Co. v. Domestic Science

Baking Co., 95 Ohio St. 180, 183, 115 N.E. 1014 (1917).

{¶ 12} “ ‘The effect of a clause for stipulated damages in a contract is to

substitute the amount agreed upon as liquidated damages for the actual damages

resulting from breach of the contract, and thereby prevents [sic] a controversy

5

SUPREME COURT OF OHIO

between the parties as to the amount of damages.’ ” Dave Gustafson & Co., Inc. v.

South Dakota, 83 S.D. 160, 164, 156 N.W.2d 185 (1968), quoting 22 American

Jurisprudence 2d, Damages, Section 235, at 321 (1965). “ ‘If a provision is

construed to be one for liquidated damages, the sum stipulated forms, in general,

the measure of damages in case of a breach, and the recovery must be for that

amount. No larger or smaller sum can be awarded even though the actual loss may

be greater or less.’ ” Id., quoting Section 235 at 321. Put another way, “a liquidated

damages clause in a contract is an advance settlement of the anticipated actual

damages arising from a future breach.” Carrothers Constr. Co., L.L.C. v. S.

Hutchinson, 288 Kan. 743, 754, 207 P.3d 231 (2009).

{¶ 13} The common law viewed liquidated-damages provisions “with a

gimlet eye,” Dist. Cablevision Ltd. Partnership v. Bassin, 828 A.2d 714, 723

(D.C.App.2003), but that historical antipathy dissipated as parties to contracts,

attorneys, and the courts recognized that such provisions serve valuable purposes.

{¶ 14} “Today the law does not look with disfavor upon ‘liquidated

damages’ provisions in contracts. When they are fair and reasonable attempts to

fix just compensation for anticipated loss caused by breach of contract, they are

enforced.” Priebe & Sons, Inc. v. United States, 332 U.S. 407, 411, 68 S.Ct. 123,

92 L.Ed. 32 (1947). The modern rule is “to look with candor, if not with favor”

upon liquidated-damages provisions in contracts when those provisions were

“deliberately entered into between parties who have equality of opportunity for

understanding and insisting upon their rights.” Wise v. United States, 249 U.S. 361,

365, 39 S.Ct. 303, 63 L.Ed. 647 (1919). See also Bassin at 724, quoting Wilmington

Trust Co. v. Aerovias de Mexico, S.A. de C.V., 893 F.Supp. 215, 218

(S.D.N.Y.1995) (“ ‘Relevant to this inquiry is the sophistication of the parties and

whether both sides were represented by able counsel who negotiated the contract at

arms length without the ability to overreach the other side’ ”).

6

January Term, 2016

{¶ 15} Part of the appeal of liquidated-damages provisions is that they allow

the contracting parties to “protect themselves against the difficulty, uncertainty, and

expenses that necessarily follow judicial proceedings when trying to ascertain

damages.” Carrothers Constr. Co., 288 Kan. at 754, 207 P.3d 231. This benefit is

particularly valuable when “actual damages are likely to be difficult to quantify in

the event that the contract is breached.” Bassin, 828 A.2d at 723. Liquidated-

damages provisions thereby “promot[e] prompt performance of contracts” and

“adjust[] in advance, and amicably, matters the settlement of which through courts

would often involve difficulty, uncertainty, delay and expense.” Wise at 366.

{¶ 16} Ohio has long recognized liquidated-damages provisions as valid

and enforceable, see Samson Sales, 12 Ohio St.3d at 28, 465 N.E.2d 392, citing

Jones v. Stevens, 112 Ohio St. 43, 146 N.E. 894 (1925); Lange v. Werke, 2 Ohio St.

519 (1853), as long as the provisions are not ones for penalties, Samson Sales, id.

And therein lies the rub. “The difficult problem, in each case, is to determine

whether or not the stipulated sum is an unenforceable penalty or an enforceable

provision for liquidated damages.” Dave Gustafson & Co., 83 S.D. at 165, 156

N.W.2d 185.

{¶ 17} In addressing whether a contract includes a permissible liquidated-

damages provision or an unenforceable penalty, one of our appellate courts has

explained that a “penalty” is

“a sum inserted in a contract, not as the measure of compensation

for its breach, but rather as a punishment for default, or by way of

security for actual damages which may be sustained by reason of

nonperformance, and it involves the idea of punishment. A penalty

is an agreement to pay a stipulated sum on breach of contract,

irrespective of the damage sustained. Its essence is a payment of

money stipulated as in terrorem of the offending party, while the

7

SUPREME COURT OF OHIO

essence of liquidated damages is a genuine covenanted pre-estimate

of damages. The amount is fixed and is not subject to change;

however, if the stipulated sum is deemed to be a penalty, it is not

enforceable and the nondefaulting party is left to the recovery of

such actual damages as he can prove.”

(Emphasis sic.) Piper v. Stewart & Inlow, 5th Dist. Licking No. CA-2530, 1978

WL 217430, *1 (June 14, 1978), quoting 22 American Jurisprudence 2d, Damages,

Section 213, at 298 (1965).

{¶ 18} In Samson Sales, we set forth Ohio’s tripartite test to determine

whether a contractual provision should be considered a liquidated-damages

provision or an unenforceable penalty. We held:

Where the parties have agreed on the amount of damages,

ascertained by estimation and adjustment, and have expressed this

agreement in clear and unambiguous terms, the amount so fixed

should be treated as liquidated damages and not as a penalty, if the

damages would be (1) uncertain as to amount and difficult of proof,

and if (2) the contract as a whole is not so manifestly

unconscionable, unreasonable, and disproportionate in amount as to

justify the conclusion that it does not express the true intention of

the parties, and if (3) the contract is consistent with the conclusion

that it was the intention of the parties that damages in the amount

stated should follow the breach thereof.

Samson Sales, 12 Ohio St.3d 27, 465 N.E.2d 392, at syllabus.

{¶ 19} Valid and enforceable liquidated-damages provisions are those

intended by the parties to give reasonable compensation for damages, but

8

January Term, 2016

provisions that impose amounts that are “manifestly inequitable and unrealistic”

are deemed unenforceable penalties. Id. at 28. Since Samson Sales, we have

reiterated its holding once, in Lake Ridge Academy v. Carney, 66 Ohio St.3d 376,

380, 613 N.E.2d 183 (1993), and have not departed from its teachings. This case

requires that we consider our precedent in a context we have not previously

addressed: public-works-construction contracts.

Liquidated Damages in Public-Works-Construction Contracts

{¶ 20} The benefits of liquidated-damages provisions in building and

construction contracts are well documented. R. Harper Heckman & Benjamin R.

Edwards, Time is Money: Recovery of Liquidated Damages by the Owner, 24

Constr.Lawyer 28, 29 (Fall 2004). The provisions create firm expectations and

allow the parties to allocate damages caused by delays in completing construction.

Id. The ability to agree about damages is particularly important in public-works-

construction contracts because “[i]t is uniquely difficult to calculate damages to the

general public interest caused by a contractor’s breach of its agreement to provide

public improvements.” Carrothers Constr. Co., 288 Kan. at 756, 207 P.3d 231.

{¶ 21} In a public-roadway-construction contract, each delay in completing

the project adds to inconvenience, increased costs, and loss of use of the roadway.

Dave Gustafson & Co., 83 S.D. at 167, 156 N.W.2d 185. But “ ‘each day’s delay,

while unquestionably injurious, is injurious frequently in ways that are difficult to

estimate.’ ” Id., quoting 5 Williston on Contracts, Section 785, 733 (3d Ed.1961).

{¶ 22} We recognize that liquidated-damages provisions in public-

construction projects play an important civic purpose in that they help foster timely

completion of the project, thereby avoiding the loss of billions of taxpayers’ dollars

caused by contractors’ delays. See, e.g., Scott M. Tyler, No (Easy) Way Out:

“Liquidating” Stipulated Damages for Contractor Delay in Public Construction

Contracts, 44 Duke L.J. 357, 358-359 (1994); Christian, Public Entities in Nevada

Beware, 12-OCT Nevada Lawyer 16. We are not alone in that recognition. The

9

SUPREME COURT OF OHIO

Supreme Court and many state and federal appellate courts also recognize that

liquidated-damages provisions in public contracts are particularly valuable given

the unique difficulty in calculating the damages associated with a public

contractor’s breach of its promise to timely complete a public-improvement project.

See, e.g., Priebe & Sons, 332 U.S. at 411, 68 S.Ct. 123, 92 L.Ed. 32 (recognizing

that liquidated-damages provisions “serve a particularly useful function when

damages are uncertain in nature or amount or are unmeasurable, as is the case in

many government contracts”); Hovas Constr., Inc. v. W. Line Consol. School Dist.

Bd. of Trustees, 111 So.3d 663, 666-667 (Miss.App.2013); Carrothers Constr. Co.,

288 Kan. at 756, 207 P.3d 231 (the unique difficulty of calculating damages when

a contractor breaches a public-works contract “should be an important

consideration in such cases and weigh favorably in finding a liquidated damages

provision to be reasonable”); Fortune Bridge Co. v. Dept. of Transp., 242 Ga. 531,

533-534, 250 S.E.2d 401 (1978) (noting that “damages flowing from the

contractor’s failure to complete [public] roadway and bridges in a timely fashion

are, as a practical matter, incapable of proof”); Brooks v. Wichita, 114 F. 297, 299

(8th Cir.1902) (recognizing that liquidated-damages provisions are the only way

for a city to obtain adequate compensation for breach of a public contract; the

damages sustained by the public in such cases are not capable of “judicial

ascertainment” because they are “too remote, conjectural, and speculative” to

prove); Dade Cty. Pub. Health Trust v. Romart Constr., Inc., 577 So.2d 636, 638,

669 (Fla.App.1991) (fact that public entity may have suffered no monetary loss

from breach does not render liquidated-damages provision unconscionable,

because public project was intended for public use, not for profit).

{¶ 23} We agree with those courts that find that “the protection of the public

interest is a proper consideration in determining [the] validity of a liquidated

damages provision.” Carrothers Constr. Co., 288 Kan. at 756, 207 P.3d 231. The

Ohio General Assembly requires that every state-funded public-improvement-

10

January Term, 2016

construction contract include a liquidated-damages provision. R.C. 153.19. Many

states have similar requirements. Dave Gustafson & Co., 83 S.D. at 166, 156

N.W.2d 185; Fortune Bridge Co., 242 Ga. at 534, 250 S.E.2d 401; see also Bale

Contracting, Inc. v. Westerville, 7 Ohio App.3d 271, 272, 455 N.E.2d 517 (10th

Dist.1982) (recognizing the materiality of a completion date in a public-works-

construction project and that a bid for such a project is incomplete when it fails to

specify the time for performance, citing R.C. 153.19).

{¶ 24} With these principles in mind, we turn to the appellate court’s

opinion in this case.

The Appellate Court’s Analysis of the Liquidated-Damages Provision

{¶ 25} In considering whether the liquidated-damages provision in this case

constituted an unenforceable penalty, the court of appeals properly applied the first

and third parts of the test in Samson Sales, 12 Ohio St.3d 27, 465 N.E.2d 392. The

appellate court recognized that “the damages incurred as a result of a delay [by

Boone Coleman in completing the project] were uncertain as to amount and

difficult to prove” and that “the plain and unambiguous language of the liquidated

damages clause is consistent with the conclusion that the parties intended that

damages in the amount of $700 per day would follow the contractor’s breach of the

project completion deadline.” 2014-Ohio-2377, 13 N.E.3d 1190, ¶ 38 and 39,

citing Samson Sales. But the appellate court concluded that the provision did not

pass the second prong of the Samson Sales test. The second prong requires a court

reviewing a liquidated-damages provision to consider whether “the contract as a

whole is not so manifestly unconscionable, unreasonable, and disproportionate in

amount as to justify the conclusion that it does not express the true intention of the

parties.” Samson Sales, at syllabus.

{¶ 26} Even though the appellate court had already determined that the

provision reflected the parties’ intentions, the appellate court focused solely on the

aggregate amount of the penalty, $277,900, in relation to the total value of the

11

SUPREME COURT OF OHIO

contract, $683,300. See 2014-Ohio-2377, ¶ 42. Only after finding that the

liquidated-damages aggregate award constituted a third of the total contract price

did the court determine that the application of the provision rendered it an

unenforceable penalty. 2014-Ohio-2377, ¶ 40. For several reasons, it was error to

do so.

{¶ 27} First, the appellate court relied heavily on a decision of one of its

sister courts, Harmon v. Haehn, 7th Dist. Mahoning No. 10 MA 177, 2011-Ohio-

6449. But Harmon is wholly distinguishable here.

{¶ 28} Given “the wide range and variety of contracts, and of their subject-

matter, it is sometimes difficult to determine whether the terms thus agreed upon in

advance actually provide for damages or for a penalty.” Sheffield-King Milling Co.,

95 Ohio St. at 183, 115 N.E. 1014. See also Lange, 2 Ohio St. at 533 (noting that

in evaluating a liquidated-damages provision, “Arbitrary rules can not help us, and

judicial decisions are of less value than upon most other questions, as each case

depends so peculiarly on its own circumstances”). Thus, when courts review

liquidated-damages provisions, they often look to similar provisions in contracts

that govern similar subject matter. See, e.g., Kurtz v. W. Property, L.L.C., 10th

Dist. Franklin No. 10AP-1099, 2011-Ohio-6726, ¶ 33 (in case involving delay in

sale of real estate, cases involving breaches in other contexts are “readily

distinguishable”).

{¶ 29} Here, Harmon is of limited value because it arose from a private

commercial real estate lease rather than a public-works-construction contract.

2011-Ohio-6449, ¶ 1. That distinction is particularly relevant because the actual

damages at issue in Harmon were far easier to quantify than those at issue here.

{¶ 30} Moreover, the Harmon decision involved a liquidated-damages

provision that contemplated a lump sum. Piketon and Boone Coleman did not

contract for a lump sum. Rather, the parties contracted for a per diem measure of

damages which, as Chief Justice Marshall recognized, is more likely to be an

12

January Term, 2016

enforceable liquidated-damages provision than an unenforceable penalty: “[T]he

agreement to pay a specified sum weekly during the failure of the party to perform

the work, partakes much more of the character of liquidated damages than the

reservation of a sum in gross.” Tayloe v. T. & S. Sandiford, 20 U.S. 13, 18, 5 L.Ed.

384 (1822). In failing to recognize this distinction, the appellate court committed

its second error.

{¶ 31} More importantly, the appellate court’s myopic focus on the

reasonableness of the total amount of liquidated damages in application, rather than

on the reasonableness of the per diem amount in the contract terms, was not proper.

The correct analysis looks at whether it was conscionable to assess $700 per day in

liquidated damages for each day that the contract was not completed rather than

looking at the aggregate amount of the damages awarded. Accord Carrothers

Constr. Co., 288 Kan. at 759, 207 P.3d 231.

{¶ 32} Although per diem amounts vary greatly in the case law, courts have

upheld liquidated-damages provisions in public-construction contracts with per

diem amounts similar to those at issue here. See, e.g., Sec. Fence Group, Inc. v.

Cincinnati, 1st Dist. Hamilton No. C-020827, 2003-Ohio-5263 (enforcing a per

diem liquidated-damages provision in a public-bridge-replacement project that

imposed $600 per day); see also Carter Steel & Fabricating Co. v. Ohio Dept. of

Transp., 102 Ohio Misc.2d 1, 721 N.E.2d 1115 (Ct. of Cl.1999) (impliedly

recognizing the validity of a liquidated-damages per diem provision in bridge-

construction project that imposed $600 in liquidated damages per day, but refusing

to enforce it against subcontractor who had no control over delay); Hovas Constr.,

111 So.3d at 667 (upholding as reasonable a $500 per diem assessment of liquidated

damages in public-construction contract); Carrothers Constr. Co., 288 Kan. at 759,

207 P.3d 231 ($850 per diem assessment of liquidated damages held reasonable in

public-construction contract). In fact, courts have upheld far greater amounts of

per diem damages in construction contracts. See, e.g., Dade Cty. Pub. Health Trust,

13

SUPREME COURT OF OHIO

577 So.2d at 638 (upholding as “perfectly reasonable” a liquidated-damages

provision imposing $2,500 in damages per day in public-construction project for

medical facility); Bethlehem Steel Corp. v. Chicago, 350 F.2d 649 (7th Cir.1965)

(upholding a liquidated-damages provision imposing $1,000 in damages per day in

public-construction project for elevated highway, even though contractor’s delay

did not prevent highway from opening to public on date scheduled). See also Unruh

& Worden, 34 Santa Clara L.Rev. 1, at fn. 1 (in commercial construction contracts,

“a typical per diem liquidated damages provision might provide that the general

contractor pay the owner/developer $10,000 for each calendar day” of delay).

{¶ 33} Moreover, the per diem liquidated damages imposed by the contract

between Piketon and Boone Coleman reflect the Ohio Department of

Transportation’s 2013 Construction and Material Specifications. Those

specifications not only require liquidated damages be deducted from any sum owed

the contractor for each day by which the contractor exceeds the completion date,

but set out the specific amount of the per diem damages.3 The per diem damages

are thus consistent with Ohio public policy.

3

The Ohio Department of Transportation’s 2013 document entitled “Construction and Material

Specifications” is available at http://www.dot.state.oh.us/Divisions/ConstructionMgt

/Specification%20Files/2013%20CMS%2011142012%20FINAL.PDF. Section 108.07 provides:

Failure to Complete on Time. If the Contractor fails to complete the Work

by the Completion Date, then the Director, if satisfied that the Contractor is making

reasonable progress, and deems it in the best interest of the public, may allow the

Contractor to continue in control of the Work. The Department will pay the Contractor

for Work performed on the Project less any liquidated damages incurred.

(Boldface sic.)

The 2013 schedule of liquidated damages, found in Table 108.07-1, provides that the

amount of liquidated damages to be deducted for each calendar day of an “overrun in time” varies

depending on the original amount of the contract. For contracts between 0 and $500,000, the

amount of per diem liquidated damages is $500; for contracts between $500,000 and $2,000,0000,

the amount of per diem liquidated damages is $1,000; for contracts between $2,000,0000 and

$10,000,000, the amount of per diem liquidated damages is $1,500; for contracts between

14

January Term, 2016

{¶ 34} Finally and most importantly, we note that the appellate court stated

that its conclusion resulted from viewing “the contract as a whole in its

application.” (Emphasis added.) 2014-Ohio-2377, ¶ 3. The use of the phrase “in

its application” is not part of our test from Samson Sales. The appellate court’s use

of this invented perspective resulted in a distorted analysis of our precedent.

{¶ 35} We reaffirm that Ohio law requires a court, when considering a

liquidated-damages provision, to “examine it in light of what the parties knew at

the time the contract was formed.” Jones, 112 Ohio St. 43, 146 N.E. 894, at

paragraph one of the syllabus; Miller v. Blockberger, 111 Ohio St. 798, 146 N.E.

206 (1924), paragraph one of the syllabus; Sec. Fence Group, 2003-Ohio-5263,

¶11. Accord Priebe & Sons, 332 U.S. at 412, 68 S.Ct. 123, 92 L.Ed. 32. “If the

provision was reasonable at the time of formation and it bears a reasonable (not

necessarily exact) relation to actual damages, the provision will be enforced.”

(Emphasis added.) Lake Ridge Academy at 382.

{¶ 36} This prospective or “front end” analysis of a liquidated-damages

provision focuses on the reasonableness of the clause at the time the contract was

executed rather than looking at the provision retrospectively, i.e., ascertaining the

reasonableness of the damages with the benefit of hindsight after a breach. See

generally Heckman & Edwards, 24 Constr.Law. at 30-31; Hovas Constr., 111

So.3d at 668-669 (Maxwell, J., concurring); Carrothers Constr. Co., 288 Kan. 743,

207 P.3d 231, at paragraph nine of the syllabus. The prospective approach properly

focuses on whether (1) the parties evaluated, at the time of contract formation, the

probable loss resulting from delay in completing the construction, (2) the parties

clearly intended to use liquidated damages in case of a delay because actual

$10,00,000 and $50,000,000, the per diem amount is $2,600; and for contracts over $50,000,000,

the per diem amount is $3,200.

15

SUPREME COURT OF OHIO

damages would be difficult to ascertain, and (3) the parties reached an agreement

as to a per diem amount for delays. Carrothers Constr. Co. at 757. See also Hutton

Contracting Co., Inc. v. Coffeyville, 487 F.3d 772, 781 (10th Cir.2007), quoting

Kelly v. Marx, 428 Mass. 877, 881, 705 N.E.2d 1114 (1999) (recognizing that

prospective analysis “ ‘resolve[s] disputes efficiently by making it unnecessary to

wait until actual damages from a breach are proved’ ” and “ ‘eliminates uncertainty

and tends to prevent costly future litigation’ ”); William Schwartzkopf & John J.

McNamara, Calculating Construction Damages, Section 13.02, at 257-258 (2d

Ed.2015) (“The reasonableness of the forecast or estimate [in a liquidated-damages

provision] is usually determined in view of the facts known at the time of

contracting, and not at the time of the breach or delayed completion” [emphasis

sic]).

{¶ 37} Here, the appellate court improperly engaged in retrospective

analysis, i.e., it looked, with hindsight, to the aggregate application of the per diem

liquidated damages to conclude that the provision was unconscionable. But it did

not determine that the per diem amount was unconscionable at the time the parties

entered into the contract. The question whether the liquidated-damages provision

is conscionable “must be viewed by the court from the standpoint of the parties at

the time of the contract, and not ex post facto when the litigation is up for trial.

Contracts are always so construed and a stipulation for liquidated damages is no

exception.” Jacobs v. Shannon Furniture Co., 22 Ohio C.D. 51, 53, 1910 WL 1170

(1910), citing Sun Printing & Pub. Assn. v. Moore, 183 U.S. 642, 672, 22 S.Ct. 240,

46 L.Ed. 366 (1902), and Knox Rock-Blasting Co. v. Grafton Stone Co., 64 Ohio

St. 361, 266, 60 N.E. 563 (1901). Moreover, when the appellate court determined

that the award was an unenforceable penalty because the amount was “so

unreasonably high and so disproportionate to the consideration paid,” 2014-Ohio-

2377, ¶ 40, the court failed to fully consider that the amount was large only because

16

January Term, 2016

Boone Coleman failed to complete the project for more than a year after the agreed-

upon completion date, with full awareness of the consequences.

{¶ 38} By the appellate court’s reasoning, the same provision might have

been enforceable if Boone Coleman’s delay had been briefer, e.g., two days, two

weeks, or even two months, but not so long as to accrue the significant damages

that arose here. It is a perverse rule of law to hold that a court can relieve a

breaching party of the consequences it agreed to by refusing to enforce a per diem

liquidated-damages provision solely because the breach was an egregious one. We

decline to adopt that rationale and vacate the judgment of the appellate court in this

cause.

{¶ 39} We remind our appellate courts that in engaging in prospective

analysis, the appellate court’s role is not to determine what the parties should have

contracted for based on the court’s understanding of the damages after the breach.

Lake Ridge Academy, 66 Ohio St.3d at 382, 613 N.E.2d 183. This court has made

clear for over 150 years that judges have no more power to disregard a valid

liquidated-damages provision than they do to disregard any other contractual

provision. Lange, 2 Ohio St. at 533; see also Knox Rock-Blasting Co. at 367-368.

The proper course is to enforce contracts according to their plain meaning and “not

to undertake to be wiser than the parties.” Jones, 112 Ohio St. at 56, 146 N.E. 894.

“It is certainly not incumbent on the appellate courts * * * to change the contracts

of people, after the fact, in the name of public policy.” Court Rooms of Am., Inc.

v. Diefenbach, 425 N.E.2d 122, 124 (Ind.1981).

“The parties themselves best know what their expectations

are in regard to the advantages of their undertaking and the damages

attendant on its failure, and when they have mutually agreed on the

amount of such damages in good faith and without illegality, it is as

17

SUPREME COURT OF OHIO

much the duty of the court to enforce that agreement as it is the other

provisions of the contract.”

Sheffield-King Milling Co., 95 Ohio St. at 185, 115 N.E. 1014, quoting Knox Rock-

Blasting Co. at 368.

CONCLUSION

{¶ 40} Benjamin Franklin advised us to remember that “time is money.”

United States v. One 1971 Corvette Stingray, E.D.Pa. No. 89-5398, 1990 WL 4374,

*1 (Jan. 18, 1990), citing Benjamin Franklin, Advice to a Young Tradesman (1748).

Boone Coleman would have done well to follow that advice.

{¶ 41} Boone Coleman entered a contract that required it to perform the

project within 120 days. It took four times that long to do so. It may not avoid the

result of the valid liquidated-damages provision it negotiated through able counsel.

“There is no sound reason why persons competent and free to contract may not

agree upon this subject [of liquidated damages] as fully as upon any other, or why

their agreement, when fairly and understandingly entered into with a view to just

compensation for the anticipated loss, should not be enforced.” Wise, 249 U.S. at

365, 39 S.Ct. 303, 63 L.Ed. 647.

{¶ 42} The appellate court erred in its use of a retrospective analysis to find

that the total amount of damages awarded to Piketon was so unreasonable as to

constitute a penalty, and in failing to focus on the per diem nature of the liquidated

damages. Accordingly, we vacate the judgment of the Fourth District Court of

Appeals and remand the cause to that court to reconsider the enforceability of the

liquidated-damages provision in light of this opinion.

Judgment vacated

and cause remanded.

O’NEILL, J., concurs.

18

January Term, 2016

O’DONNELL, LANZINGER, KENNEDY, and FRENCH, JJ., concur in judgment

only.

PFEIFER, J., dissents.

_________________

KENNEDY, J., concurring.

{¶ 43} I agree with the majority opinion. However, I would exclude the

first paragraph of the majority’s conclusion.

{¶ 44} Therefore, I respectfully concur.

O’DONNELL, J., concurs in the foregoing opinion.

_________________

PFEIFER, J., dissenting.

{¶ 45} We should dismiss this case as having been improvidently accepted

and allow the court of appeals decision to stand. That court reached a sound and

proper conclusion that is fair to both parties. Furthermore, no new legal issue is at

stake.

{¶ 46} Instead this court has taken a bad situation and made it worse. Boone

Coleman already suffered a loss from performing additional work for which it was

not paid. On top of that, this court now determines that Boone Coleman must pay

a penalty because it didn’t complete the contract on time, never mind that Boone

Coleman claims that part of the problem was that Piketon provided inaccurate site

information. This is akin to frontier justice: we do it because we can, not because

it makes sense.

{¶ 47} Barring a dismissal, the sensible approach to this case, the approach

taken by the court of appeals, is to declare the liquidated-damages clause to be

unreasonable and disproportionate. Equities do matter―even in a contract case.

Given the circumstances of this case, which include Piketon allegedly providing

inaccurate site plans to Boone Coleman, the court of appeals got it right. It

disallowed Boone Coleman’s requests for additional payment because they were

19

SUPREME COURT OF OHIO

not properly submitted and refused to enforce the liquidated-damages clause

because it was so unreasonable and disproportionate as to amount to a penalty.

{¶ 48} Because the court is neither dismissing the case nor affirming the

court of appeals, I dissent.

_________________

Stephen C. Rodeheffer and John A. Gambill, for appellee.

Kegler Brown Hill & Ritter, L.P.A., Eric B. Travers, and Timothy A.

Kelley, for appellant.

Bricker & Eckler, L.L.P., Jack R. Rosati Jr., and Adam F. Florey, urging

reversal for amici curiae, County Commissioners Association of Ohio, Ohio

Municipal League, Ohio School Boards Association, and Ohio Township

Association.

_________________

20