§ 271.103 Risk-based hazard management program.

FederalRegulations

Ask Donna

How this section applies to your facts.

Title 49—Transportation > Subtitle B—Other Regulations Relating to Transportation > CHAPTER II—FEDERAL RAILROAD ADMINISTRATION, DEPARTMENT OF TRANSPORTATION > PART 271—RISK REDUCTION PROGRAM > Subpart B—Risk Reduction Program Requirements

This text was captured on Sep 22, 2026. It is a snapshot, not a live feed, so check the official code before relying on it.

Text

(a) General. (1) An RRP shall include an integrated, system-wide, and ongoing risk-based HMP that proactively identifies hazards and mitigates the risks resulting from those hazards.

(2) A risk-based HMP shall be fully implemented (i.e., activities initiated) within 36 months after FRA approves a railroad's RRP plan pursuant to § 271.301(d).

(b) Risk-based hazard analysis. As part of its risk-based HMP, a railroad shall conduct a risk-based hazard analysis that addresses, at a minimum, the following aspects of a railroad's system: Infrastructure; equipment; employee levels and work schedules; operating rules and practices; management structure; employee training; and other areas impacting railroad safety that are not covered by railroad safety laws or regulations or other Federal laws or regulations. A railroad shall make the results of its risk-based hazard analysis available to FRA upon request. At a minimum, a risk-based hazard analysis shall:

(1) Identify hazards by analyzing:

(i) Aspects of the railroad's system, including any operational changes, system extensions, or system modifications; and

(ii) Accidents/incidents, injuries, fatalities, and other known indicators of hazards;

(2) Calculate risk by determining and analyzing the likelihood and severity of potential events associated with identified risk-based hazards; and

(3) Compare and prioritize the identified risks for mitigation purposes.

(c) Mitigation strategies. (1) As part of its risk-based HMP, a railroad shall design and implement mitigation strategies that improve safety by:

(i) Mitigating or eliminating aspects of a railroad's system that increase risks identified in the risk-based hazard analysis; and

(ii) Enhancing aspects of a railroad's system that decrease risks identified in the risk-based hazard analysis.

(2) A railroad may use pilot projects, including pilot projects conducted by other railroads, to determine whether quantitative data suggests that a particular mitigation strategy has potential to succeed on a full-scale basis.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.