§ 4.1 Initial cost statement.

FederalRegulations

Ask Donna

How this section applies to your facts.

Title 18—Conservation of Power and Water Resources > CHAPTER I—FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY > SUBCHAPTER B—REGULATIONS UNDER THE FEDERAL POWER ACT > PART 4—LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT COSTS > Subpart A—Determination of Cost of Projects Constructed Under License

This text was captured on Sep 22, 2026. It is a snapshot, not a live feed, so check the official code before relying on it.

Text

(a) Notification of Commission. When a project is constructed under a license issued under the Federal Power Act, the licensee shall, within one year after the original project is ready for service, file with the Commission a letter, in quadruplicate, declaring that the original costs have been booked in compliance with the Commission's Uniform System of Accounts and the books of accounts are ready for audit.

(b) Licensee's books. The licensee's books of accounts for each project shall be maintained in such a fashion that each year's additions, betterments, and deletions to the project may be readily ascertained.

(c) Availability of information to the public. The information made available to the Commission in accordance with this section must be available to the public for inspection and copying when specifically requested.

(d) Compliance with the Act. Compliance with the provisions of this section satisfies the filing requirements of section 4(b) of the Federal Power Act (16 U.S.C. 797(b)).

[Order 53, 44 FR 61948, Oct. 29, 1979]

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

§ 4.1 Initial cost statement. · 18 CFR § 4.1 | Frix