§ 1308.12 Submission and decision of Contractor's claim.

FederalRegulations

Ask Donna

How this section applies to your facts.

Title 18—Conservation of Power and Water Resources > CHAPTER XIII—TENNESSEE VALLEY AUTHORITY > PART 1308—CONTRACT DISPUTES > Subpart B—Contracting Officers

This text was captured on Sep 22, 2026. It is a snapshot, not a live feed, so check the official code before relying on it.

Text

(a) If Contractor and TVA are unable to resolve Contractor's request for relief by agreement within a reasonable time, Contractor may submit a claim to the Contracting Officer.

(b) The Contracting Officer shall issue a decision to the Contractor on a submitted claim in conformity with the contract's disputes clause. Specific findings of fact are not required, but may be made. Such findings are not binding in any subsequent proceeding except as provided in § 1308.15. The decision shall:

(1) Be in writing;

(2) State the reasons for the decision reached;

(3) Include information about the Contractor's rights of appeal under sections 7 and 10 of the Act (including time limits); and

(4) Notify the Contractor, as appropriate, of the special procedures available under §§ 1308.35 and 1308.36 at the Contractor's election. A copy of the provisions of this part shall be furnished with the decision.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

§ 1308.12 Submission and decision of Contractor's claim. · 18 CFR § 1308.12 | Frix