Ch. 14, § 4. Blasting Standards

WyomingRegulations

Ask Donna

How this section applies to your facts.

Wyoming Administrative Code › Agency 020 Environmental Quality, Dept. of › Program 0007 Land Quality - Non Coal › Chapter 14 Blasting for Noncoal Surface Mining Operations › § 4

This text was captured on Sep 30, 2026. It is a snapshot, not a live feed, so check the official code before relying on it.

Text

(a) General.

(i) Blasting shall be conducted to prevent injury to persons, damage to public or private property outside the permit area, adverse impacts on any underground mine, and change in the course, channel, or availability of ground or surface waters outside the permit area. Any failure to comply with these requirements shall be documented and the Administrator shall be notified in writing within 30 days.

(ii) All federal, state, and local laws and regulations applicable to obtaining, owning, transporting, storing, handling, and using explosive materials shall be followed.

(iii) Where blasting is conducted in the vicinity of utility lines or rights-of-way, the blaster shall notify the representatives of the utility at least twenty-four hours in advance of blasting, specifying the location and the intended time of such blasting. Verbal notice shall be confirmed with written notice. In an emergency situation, the time limit shall not apply where approved by the Administrator.

(iv) All blasting shall be conducted during the time approved by the Administrator and announced on the blasting schedule. Based on public requests or other considerations, including the proximity to residential areas, the Administrator may limit the area covered, timing and sequence of blasting. Blasting shall be conducted between sunrise and sunset unless night-time blasting is approved by the Administrator based on public protection and annoyance considerations.

(v) Blasting may not be conducted at times different from those announced in the blasting schedule except in conditions where operator or public safety requires unscheduled detonation or for emergency blasting actions. Reasons for unscheduled detonation shall be documented.

(vi) Warning and all-clear signals of different character that are audible within the blast area shall be given. All persons within the blast area shall be notified of the meanings of the signals in the blasting schedule.

(vii) Area of control. The blaster-in-charge shall be responsible for determining the blast area, based on site conditions and ensuring that the blast area is secure. Access to the blasting area shall be controlled to protect the public and livestock from the effects of blasting and to prevent unauthorized entry. Access control shall continue until the blaster-in-charge has determined that no unusual circumstances such as imminent slides or undetonated charges exist and access to and travel in or through the area can safely resume.

(viii) Areas in which charged (loaded) holes are awaiting firing shall be guarded or barricaded and posted against unauthorized entry.

(ix) The Blasting Plan shall be part of the Mine Plan for the area to be mined and shall include a plan to comply with Section 4 and Section 5 of this Chapter and include the following:

(A) Types of explosives and detonation equipment to be used and the size, timing and frequency of blasts.

(B) Methods to control adverse effects of blasting.

(C) Blasters shall use every reasonable precaution including, but not limited to, warning signals, flags, barricades, mats, or other effective means to ensure the safety of the general public and workers.

(D) Holes shall not be drilled where there is a danger of intersecting another hole containing explosive material.

(E) During the time that holes are being loaded or are loaded with explosive materials, blasting agents, or detonators, the blast site shall be off limits to all, but those persons authorized to engage in the drilling and loading operation or who are otherwise authorized to enter the site.

(F) After blasting, no person will be allowed to return to the blast area until the blaster-in-charge has performed the following:

(I) The blaster shall allow sufficient time for smoke and fumes to dissipate and for the dust to settle before returning to or approaching the blast area; and

(II) The blaster shall inspect the entire site for misfire before allowing other personnel to return to the blast area. Where a misfire is found or suspected, the blaster-in-charge shall provide the proper safeguards for excluding all personnel from the blast area. Misfire shall be addressed in accordance with the instructions of the manufacturer of the explosive material.

(III) Access control shall continue until the blaster-in-charge has determined that no unusual circumstances such as imminent slides or undetonated charges exist and access to and travel in or through the area can safely resume.

(x) During the approach of and for the duration of an electrical storm, all personnel shall move to a safe location.

(xi) No person shall smoke or possess an open flame within fifty feet of any location where explosives are being handled, used or stored except for approved devices for lighting safety fuses.

(xii) No firearms shall be discharged into or in the vicinity of a vehicle containing explosive material, or into or in the vicinity of a location where explosives materials are being handled, used, or stored.

(xiii) No person under the influence of intoxicating beverages, narcotics, or other dangerous drugs shall be permitted to handle explosive materials.

(xiv) No blasting operation shall be performed in a manner contrary to the instructions of the manufacturer of the explosive materials being used.

(xv) The use of safety fuse, cap and fuse, or electric detonators shall require a blasting plan approved by the Administrator to limit adverse effects and accidental initiation.

(b) Limitations.

(i) Airblast shall not exceed the values specified below at any dwelling, public building, school, church, and community or institutional building outside the permit area, unless the building is owned by the operator and not leased to another, or, if leased, the lessee signs a waiver relieving the operator from meeting the limitations. If necessary to prevent damage, the Administrator shall specify lower maximum allowable airblast levels.

Lower Frequency limit of measuring

system, Hz (-3dB)1,2

Maximum level in dB

2 Hz system (linear from 4 Hz to 125 Hz)

133 peak

1 Blasting seismographs used to monitor ground vibrations and airblast shall comply with the International Society of Explosives Engineers (ISEE) document, "Performance Specifications for Blasting Seismographs" or use the best available technology as approved by the Administrator.

2 Blasting seismographs shall be deployed in the field according to ISEE document, "Field Practice Guidelines for Blasting Seismographs" or use the best available technology as approved by the Administrator.

(A) The operator shall conduct periodic monitoring to ensure compliance with the airblast standards. The Administrator shall request monitoring in certain instances, including but not limited to complaints, blasting in sensitive areas, and in areas where there is reason to believe airblast limits may be exceeded.

(ii) Flyrock shall not be cast from the blasting site in an uncontrolled manner that could result in personal injury or property damage. Flyrock shall not be propelled from the blast site onto property for which the owner has not provided a written waiver to the blasting operation.

(iii) In all blasting operations except as specified below, the maximum ground vibration shall not exceed the values approved in the blasting plan. The maximum ground vibration at the location of any dwelling, public building, school, church, community or institutional building outside the permit area shall not exceed the values established by paragraph (iv), the scaled-distance equation of paragraph (v), the blasting level chart of paragraph (vi), or by the Administrator under paragraph (vii). All other engineered structures such as water towers, pipelines, tunnels, dams, impoundments, and underground mines, shall be protected from damage by establishment of a maximum allowable limit on ground vibration, submitted by the operator in the blasting plan and approved by the Administrator. The ground vibration standards do not apply to structures owned by the operator and not leased to another, or, if leased, the lessee signs a waiver relieving the operator from meeting the limitations.

(iv) Maximum peak particle velocity applicable when seismograph records are provided for each blast:

Distance (D) from the

Blasting Site in feet

Maximum allowable peak particle velocity (Vmax) for ground vibration in inches/second1,3,4

Scaled distance factor to be applied without seismic monitoring2

0 to 300

1.25

50

301 to 5000

1.00

55

5001 and beyond

0.75

65

1 Ground vibration shall be measured as the particle velocity. Particle velocity shall be recorded in three mutually perpendicular directions. The maximum allowable peak particle velocity shall apply to each of the three measurements.

2 Applicable to the scaled-distance equation of Paragraph (v).

3 Blasting seismographs used to monitor ground vibrations and airblast shall comply with the ISEE document, "Performance Specifications for Blasting Seismographs" or use the best available technology as approved by the Administrator.

4 Blasting seismographs shall be deployed in the field according to the ISEE document, "Field Practice Guidelines for Blasting Seismographs" or use the best available technology as approved by the Administrator.

(v) An operator may use the scaled-distance equation, W=(D/Ds)2 to determine the allowable charge weight of explosives to be detonated in any eight millisecond period, without seismic monitoring; where W = the maximum weight of explosives, in pounds; D = the distance, in feet, from the blasting site to the nearest protected structure; and Ds = the scaled-distance factor, which may initially be approved by the Administrator using the values for scaled-distance factor listed in paragraph (iv) above.

(A) Upon written request by the operator with seismographic records, the Administrator may authorize a modified scaled-distance factor for engineered structures. The modified scaled-distance factor shall be determined such that particle velocity of the predicted ground vibration will not exceed the prescribed maximum allowable peak particle velocity of paragraph (iv) above, at a 95 percent confidence level.

(vi) An operator may use the ground vibration limits in Figure 1 (blasting-level chart) to determine the maximum allowable ground vibration. A seismograph record including both particle velocity and vibration frequency levels shall be provided for each blast. The method for the analysis of the predominant frequency contained in the blasting records shall be approved by the Administrator before application of this alternative blasting criterion.

FIGURE 1

ALTERNATIVE BLASTING LEVEL CRITERIA

Blast Vibration Frequency, Hz

(Source modified from OSM training material)

(vii) The maximum allowable ground vibration shall be reduced by the Administrator beyond the limits otherwise provided by paragraphs (iv)-(vi), if necessary to provide damage protection. The Administrator may require an operator to conduct seismic monitoring of any or all blasts or may specify the location at which the measurements are taken and the degree of detail necessary in the measurements.

(c) Blast Design.

(i) Anticipated blast design(s) shall be submitted if blasting operations will be conducted within:

(A) 1,000 feet of any building used as a dwelling, public building, school, church, or community or institutional building outside the permit area; or

(B) 500 feet of an active or abandoned underground mine.

(ii) The blast design may be presented as part of a permit application or at a time, before the blast, approved by the Administrator.

(iii) The blast design shall contain sketches of the drill patterns, delay periods, and decking and shall indicate the type and amount of explosives to be used, critical dimensions, and the location and general description of structures to be protected, as well as a discussion of design factors to be used, which protect the public and meet the applicable airblast, flyrock, and ground-vibration standards in (b) above.

(iv) The blast design shall be prepared and signed by a certified blaster.

(v) The Administrator may require changes to the design submitted.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.