Service pipes and meter sets
OklahomaRegulations
Ask Donna
How this section applies to your facts.
Oklahoma Administrative Code › Title 165 › OAC 165:65-3-3
Text
(a) Upon application by any bona fide applicant for water service, the utility shall provide a tap
and a corporation cock at the main, furnish and install a service pipe of suitable material and
capacity, furnish and install a shut-off cock, a meter box, and all other fittings necessary to set a
meter on the applicant's property abutting upon any public way in which the utility has an adjacent
water distribution main.
(b) Where additional meters are furnished by the utility for the convenience of the consumer, a
charge for such meters may be made in accordance with a schedule approved by and on file with
the Commission.
(c) The utility may charge the residential applicant a tap-on charge specified in its tariff or rules
of service on file with and approved by the Commission for furnishing and installing the necessary
material and coupling devices, providing the meter setting and connecting the meter to the
consumer's house service line. The charge shall be a non-recurring charge for the premises,
notwithstanding later change in ownership or consumers there served. Subsequent consumers may
be charged a service initiation fee, provided such fee is listed in the utility's approved tariff. The
meter box, meter, and all other fittings used in connecting service and serving the meter shall
remain the property of the utility. When it is necessary to make a tap-on of a size larger than
required for a residential consumer, the tap-on and meter setting cost shall be charged the consumer
as specified in the tariff or Rules of Service, or if no such charge is there stated, at the actual cost
to the utility.
(d) Where the utility and the consumer cannot agree upon the location, dimensions and type of
installation to be made, the utility shall advise the consumer of the CSD and provide the telephone
number to the consumer to address the problem and seek resolution. If the problem remains
unsolved, either the consumer or the utility may file an application with the Commission for
hearing and final determination.
(e) Where circumstances require the meter to be set at a point other than the property or curb line,
the proper service pipes shall be installed by the utility from the main to the meter. If the meter is
located inside the property line at the consumer's request, the consumer shall pay the cost of the
service pipe from the property or curb line to the meter and for installation thereof, under uniform
rates to be adopted by the utility and approved by and on file with the Commission. The utility
shall own and maintain all service lines and equipment up to the outflow side of the meter wherever
installed.
(f) The utility shall provide each service connection with an individual shut-off cock. No tandem
service shall be allowed.
(g) The size, design, material, and installation of the consumer's service pipe shall conform to any
code, ordinances or requirements of the city or town where installed, or where no such
requirements exist, to the rules and orders of the Commission and the Service Rules of the utility
filed with and approved by the Commission. No service pipe shall be less than three-fourths inch
(3/4") nominal size. All service pipes shall be laid underground at a depth sufficient to prevent
OAC 165:65
OKLAHOMA CORPORATION COMMISSION
10
freezing, except where service is not intended to be used during freezing weather and the pipes are
actually drained during such periods.
(h) In the installation of a service pipe the consumer shall not install any tee or branch connection
without consent of the utility. The consumer shall leave the trench open and pipe uncovered until
it has been inspected by the utility or inspection waived. The service pipe shall be provided with
a suitable shut-off cock by the consumer. The consumer is responsible for maintenance of all
service pipes from the outflow side of the meter.
(i) When the installation of a service pipe requires a trench to remain open on the consumer's
property for an inspection or waiver of inspection, the utility shall perform the inspection, or
request that the inspection be performed if done by a third party, within fourteen (14) calendar
days of the installation.
(j) All open trenches shall be clearly marked for the safety of the public using, at a minimum,
caution tape or flags.
165:65-3-4.
Extension of mains
(a) General. A utility shall extend its distribution mains to serve the consumers within the
corporate limits of a municipality served by the utility, or any recorded addition thereof, or within
a reasonable distance from the utility’s existing distribution system in accordance with the
provisions of this Chapter.
(b) Free extension. A utility shall extend its distribution system, as needed, up to one hundred
feet (100') per residence without cost to the one requesting service. In arriving at the length of
such main extension necessary to render service to the consumer, the distance shall be measured
along lines of proper construction from the nearest distribution main with adequate capacity.
(c) Extension above free limit-advance. If the extension necessary to furnish service is greater
than allowed as a free extension under subsection (b) of this Section, a utility may require an
advance of the cost of the main extension over the free limit. However, the utility shall not
arbitrarily or with disparity impose the obligation of requiring an advance, but rather shall
determine whether to require an advance and the amount thereof on a case-by-case basis.
Whenever such advance is made, the utility shall be required to refund to the consumer who made
the advance an amount equal to the cost of one hundred feet (100') of free extension for each
additional consumer whose service line is connected to such main within a period of ten (10) years
from the making of the extension. No refunds shall be made for consumers connected to future
extensions tied into such an extension. This refund will cease after ten (10) years from the making
of the extension but the total of all refunds shall not exceed the original advance. The advance
shall not draw interest.
(d) Extensions above free limit-revenue basis. The Commission may authorize a utility to make
extensions above the free limit upon receipt of a lesser advance, or no advance, when the gross
anticipated annual revenue from an extension will provide the utility with an adequate return on
its investment pursuant to a formula or other method approved by the Commission. After such
authorization, the utility shall make extensions when requested by the consumer pursuant to such
approved formula or method.
(e) Extension above free limit-special contract. In lieu of making an extension pursuant to
subsections (c) or (d) of this Section, a utility may make an extension above the free limit with a
OAC 165:65
OKLAHOMA CORPORATION COMMISSION
11
lesser advance or no advance, when the utility has entered into an agreement whereby the one
proposing to provide the advance guarantees a minimum annual revenue from the extension to the
utility. Such an agreement shall be deemed a special contract governed by OAC 165:65-9-7
(f) Determining cost of extension. In determining the amount of advance, if any, which shall be
made for an extension pursuant to this Section, the total construction cost of the extension shall
first be determined in accordance with the approved system of accounts for water utilities and from
such total construction cost there shall be deducted:
(1) Costs incident to any increase in size of the main in excess of that required to adequately
and satisfactorily provide service, costs incident to future expansion or to continue a
construction plan of the utility, and costs necessary to correct inadequate capacity.
(2) The total construction cost of that portion of the extension constituting a free extension,
which includes meters, service regulators, stopcocks, and service connections.
(g) Extensions applicable in prospective real estate subdivisions. In lieu of an extension
pursuant to other provisions of this Section, a utility may require a developer desiring an extension
to a prospective real estate subdivision to make an advance equal to the estimated cost of the
extension before construction is started, and such advance shall not draw interest. At least annually
for a period not to exceed ten (10) years, the utility shall refund to the developer a sum equivalent
to the cost of the free extension under subsection (b) of this Section for each consumer connected
to the extension during the calendar year. In no case will the total amount refunded exceed the
amount advanced to the utility. Consumers locating on an extension made pursuant to this Section
will not be required to make an advance for an extension
(h) Extension above free limit. If the extension above the free limit is of such length and the
future anticipated revenues therefrom so small that it is doubtful that the extension would ever
make a fair return on the investment, the utility or any interested person or entity may apply to the
Commission for an appropriate order after notice and hearing.
(i) Property of extension. Every extension shall at all times be the property of the utility
regardless of whether an advance or contribution is made for its construction. Any unrefunded
portion of an advance shall become the property of the utility.
(j) Filing an extension policy. In lieu of the extension provisions described in subsections (b)
through (i) of this Section, a water utility may file with the Commission an Extension of Facilities
Policy governing reasonable extensions of facilities to consumers. This plan must be approved by
the Commission.
(k) Other extensions of facilities. A utility may implement a policy whereby consumers who
request water service requiring the installation of new distribution mains may apply to the utility
for service in compliance with Commission-approved tariffs, and may negotiate with the utility to
perform some of the work necessary to install the new mains. If a mutually acceptable agreement
is reached, the utility and the consumer shall enter a written agreement which conforms with the
requirements provided in the utility's Commission-approved tariff. The utility shall own any
distribution main installed pursuant to this subsection, and shall be responsible for proper
maintenance and operation of the line.
[Source: Amended at 16 Ok Reg 2380, eff 7-1-99]