Construction and maintenance of plant, equipment, and facilities

OklahomaRegulations

Ask Donna

How this section applies to your facts.

Oklahoma Administrative Code › Title 165 › OAC 165:65-3-1

This text was captured on Sep 30, 2026. It is a snapshot, not a live feed, so check the official code before relying on it.

Text

(a) Water plant and system construction and maintenance. Each utility shall construct and

maintain its entire water plant and system in such condition as will enable it to furnish safe,

adequate and reliable service subject only to emergency conditions beyond its control.

(b) Construction, installation, and maintenance of systems. Transmission and distribution

systems, including transmission mains and pipe lines, distribution mains, pumps, valves, storage

tanks, meters, equipment, etc., shall be constructed, installed, and maintained in accordance with

all applicable rules and orders of the Commission and DEQ. Utilities must be able to locate water

lines consistent with the requirements of 63 O.S. §§ 142.1 et seq.

(c) Statement regarding plant, equipment, and facilities. Each utility shall submit to the

Commission annually a statement regarding its plant, equipment, and facilities in such form as the

Commission may require. Utilities other than those that purchase water shall provide appropriate

authority for their use of water (U.S. Corps of Engineers, Oklahoma Water Resources Board,

and/or other appropriate authority). All water service utilities that withdraw groundwater or divert

stream water must hold a water right from the Oklahoma Water Resources Board before placing

water to use.

(d) Plans, surveys, and permits. Each utility shall submit to the Commission a certified copy of

all plans and surveys of its waterworks which have been filed with the DEQ. A description of the

source from which the water supply is derived shall be filed with the Commission, and no new or

different source of supply shall be used until a certified copy of the certificate of the DEQ

approving the use of the new or different supply has been filed with the Commission. No utility

shall sell water or extend water service to a consumer until certified copies of all permits required

to be issued by the DEQ to the utility are filed with the Commission.

(e) Depth of mains. Water mains, except mains used exclusively for temporary or seasonal

service, shall be installed below the normal frost line or otherwise protected to prevent freezing in

accordance with DEQ.

(f) Dead ends. Insofar as practicable the utility shall design its distribution system so as to avoid

dead ends on its mains. Where dead ends exist, under circumstances that adequate water

circulation does not exist, the utility shall provide hydrants or valves for the purpose of flushing

the mains. Mains without adequate circulation shall be flushed every ninety (90) calendar days,

or more often if necessary, to maintain the proper quality of the water. Records shall be kept of

the date, place and duration of flushing mains; and such records shall be used as a guide to

determine the necessary frequency of flushing of the same mains thereafter.

OAC 165:65

OKLAHOMA CORPORATION COMMISSION

8

(g) Segmentation of systems. The design of water mains or systems hereafter constructed shall

contain valves at intervals throughout the system to facilitate repairs and minimize interruptions

of service to consumers.

(h) Grid systems. Whenever feasible, the distribution system shall be laid out in a properly

segmented grid so that in case of breaks or repairs the interruption of service to the consumers can

be kept at a minimum.

(i) Fire protection service. Specifications, location, installation, and the responsibility for the

maintenance of fire hydrants, public and private fire protection facilities and connecting mains,

and the ownership of such facilities shall be subject to negotiation between the utility and the

municipality served. Fire hydrants and public and private fire protection facilities shall conform

to the requirements of the city where installed or in the absence of city requirements, to the rules

and orders of the Commission.

(j) Valves. Each utility shall inspect the principal mainline valves on its distribution system at

least once every two (2) years. A record of each valve shall be kept showing the size, type,

location, date of inspection and the results thereof.

(k) If PUD informs the utility of any safety issues concerning the utility's plant, equipment, or

facilities by identifying the relevant Commission rule, or other applicable Federal or State laws

implicated by the safety issue, the utility shall electronically provide photographic evidence to

PUD showing completion of work and that the issue has been resolved. If the utility has the

necessary equipment it shall provide such evidence via electronic photographs or such other

method that will reasonably show the issue has been resolved.