Section 466.45 Pre-Application Report
IllinoisRegulations
Ask Donna
How this section applies to your facts.
Illinois Administrative Code › Title 83 PUBLIC UTILITIES › CHAPTER I: ILLINOIS COMMERCE COMMISSION › Part 466 ELECTRIC INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES FACILITIES › Section 466.45 Pre-Application Report
Text
Section 466.45 Pre-Application Report
a) A
potential applicant may submit a formal written request form along with a
non-refundable fee of $300 for a pre-application report on a proposed project
at a specific site. The EDC shall provide the pre-application data described in
Section 466.50(b) to the potential applicant within 20 business days after
receipt of the completed pre-application report request form and payment of the
$300 fee. The pre-application report produced by the EDC is non-binding and
does not confer any rights; the potential applicant must file an application
before it can interconnect with the EDC's system. The written pre-application report
request form shall include the following information:
1) project
contact information, including name, address, phone number and email address;
2) project
location (street address with nearby cross streets, town, and GPS coordinates
in decimal format);
3) meter
number, pole number, EDC account number or other equivalent information
identifying proposed point of interconnection, if available;
4) generator
type (e.g., solar, wind, combined heat and power, energy storage or inverter
system, or fuel cells);
5) total
generation capacity and total storage capacity (alternating current kVA);
6) single
or three-phase generator configuration;
7) whether
new electric service is required for the site. Include the existing minimum and
maximum on-site electrical demand (in kVA) and describe any expected changes to
the minimum or maximum on-site electrical demand (in kVA), including the timing
of those changes; and
8) the number
and capacity of each generator unit to be interconnected at the site specified
in the pre-application report request
lectric service is required for the site. Include the existing minimum and
maximum on-site electrical demand (in kVA) and describe any expected changes to
the minimum or maximum on-site electrical demand (in kVA), including the timing
of those changes; and
8) the number
and capacity of each generator unit to be interconnected at the site specified
in the pre-application report request.
b) Using
the information provided in the pre-application report request form described
in subsection (a), the EDC will identify the distribution facilities that are
likely to serve the proposed point of interconnection if the project is
constructed, including: substation/area bus, substation transformer or
distribution circuit, as applicable. This identification by the EDC does not
guarantee, after application of the relevant review process, that the EDC will
use the distribution facilities identified in the pre-application report to
connect to the project. The potential applicant must request additional pre-application
reports if information about multiple points of interconnection is requested.
Subject to subsection (c), the pre-application report shall include the
following information:
1) Identification of up to two distribution
circuits within one quarter mile of the proposed point of interconnection,
including the following information:
A) Substation
and circuit identifying information;
B) Feeder
configuration (e.g., radial or network);
C) Number
and size of phase conductors at the point of interconnection;
D) Distance
to three-phase (if applicable);
E) Primary
circuit voltage at the point of interconnection;
F) Existing
aggregate generation capacity interconnected to the identified substations and circuits;
G) Aggregate
generation capacity and non-binding estimated costs associated with projects
earlier in the queue and planned for the identified substations and circuits;
H) Capacity
of the substation transformer, sub
Primary
circuit voltage at the point of interconnection;
F) Existing
aggregate generation capacity interconnected to the identified substations and circuits;
G) Aggregate
generation capacity and non-binding estimated costs associated with projects
earlier in the queue and planned for the identified substations and circuits;
H) Capacity
of the substation transformer, substation circuit equipment, and lowest rated
circuit equipment between the proposed point of interconnection and the
substation/area bus identified;
I) Circuit
peak and minimum load: estimated if actual is unavailable (i.e., minimum load
from 10 a.m. to 4 p.m. Central Prevailing Time for fixed panel photovoltaic
(PV) systems, from 8 a.m. to 6 p.m. for PV systems using tracking systems, or
absolute minimum for non-PV and energy storage systems);
J) Approximate
circuit distance between the proposed point of interconnection and the
identified substation or area bus;
K) Size
and type of relevant protective devices between the proposed point of
interconnection and the substation/area bus identified, including:
i) Lowest rated upstream
recloser, where applicable; and
ii) Lowest
rated upstream fuse, where applicable;
L) Number
of regulating devices between the proposed point of interconnection and the
substation/area bus identified; and
M) For the
EDC's proposed point of interconnection, all existing or anticipated
constraints that might affect the interconnection.
2) Disclosure
from the EDC as to whether the aggregate contingent upgrades of the systems
earlier in the queue are estimated to exceed the following thresholds, if such
estimates are available:
A) Distribution
facility replacement/upgrades of $50,000;
B) Substation
transformer replacement/upgrades of $100,000; or
C) Transmission
replacement/upgrades of $100,000.
c) The
pre-application report need only include existing data
gent upgrades of the systems
earlier in the queue are estimated to exceed the following thresholds, if such
estimates are available:
A) Distribution
facility replacement/upgrades of $50,000;
B) Substation
transformer replacement/upgrades of $100,000; or
C) Transmission
replacement/upgrades of $100,000.
c) The
pre-application report need only include existing data. A pre-application
report request does not obligate the EDC to conduct a study or other analysis
of the proposed generator in the event that data is not available. The
information concerning "available capacity" provided within the
pre-application report represents the best information available to the EDC at
the time of reporting and does not imply that an interconnection up to this
level may be completed without impacts.