Section 935
Section 935.35 Permits
a) General. Section 8 of the Act requires that the applicant
submit plans to the Department and obtain a construction permit from the
Department prior to the construction of a new migrant labor camp or a major
alteration or major extension to an existing migrant labor camp. (B)
b) Plans. Two sets of plans showing the following information
shall be submitted to the Department by the applicant to obtain a construction
permit:
1) Identification of the migrant labor camp involved and the
person or organization preparing the drawings and specifications.
2) A statement describing the scope of the work proposed and the
anticipated time schedule.
3) A plan showing location of all structures and improvements.
4) Drawings and/or specifications for proposed buildings or
structures that include all structural components and material specifications.
5) Detailed drawings and specifications of proposed potable water
source and distribution system, and a general drawing showing distances between
components of the potable water system and sources of potential contamination.
6) Detailed drawings and specifications of proposed sewage system
construction, a general arrangement drawing showing distances between
components of the sewage system and potable water systems or bodies of surface
water, and data showing estimated volume of sewage flow and soil percolation
rates for absorption fields. When a permit has been obtained or applied for
from the Environmental Protection Agency or a unit of local government for construction
of a sewage disposal system, a copy of the permit or permit application shall
be submitted.
7) Detailed drawings and specifications for proposed food service
establishment construction showing interior construction of the building,
floors, walls and ceiling, as well as details of food handling equipment to be
installed
l Protection Agency or a unit of local government for construction
of a sewage disposal system, a copy of the permit or permit application shall
be submitted.
7) Detailed drawings and specifications for proposed food service
establishment construction showing interior construction of the building,
floors, walls and ceiling, as well as details of food handling equipment to be
installed.
8) Drawings of proposed electrical distribution system
construction showing general arrangement, size and type of wiring, method of
grounding, over-current protection and type of equipment.
9) Drawings of proposed sewer and water piping within buildings
showing size and location of piping, fittings, and fixtures, as well as
materials of construction, in accordance with the Illinois Plumbing Code (77
Ill. Adm. Code 890).
10) The maximum number of persons intended to occupy any new or
remodeled housing unit shall be specified. This figure shall not exceed the
capacity of the water and sewage systems provided.
c) Flood Hazard. Prior to the issuance of a construction permit,
the permit applicant shall submit a completed "Special Flood Hazard Area
Request Form" provided by the Department. If the site is within a Special
Flood Hazard Area, the applicant shall forward to the Illinois Department of
Natural Resources the plans for the project. No project to be located in a
Special Flood Hazard Area shall be issued a permit without a statement or a
copy of the statement from the Department of Natural Resources that the
construction complies with the requirements of Executive Order 79-4 dated May
31, 1979. Construction of such items as water wells, septic tanks, underground
utilities, light poles, pavilions, playground equipment, sidewalks and
driveways as specified in Statewide Permit Number 6 issued by the Illinois
Department of Natural Resources, May 13, 1983 are exempt from the above
requirements. (C)
d) Local Approval
th the requirements of Executive Order 79-4 dated May
31, 1979. Construction of such items as water wells, septic tanks, underground
utilities, light poles, pavilions, playground equipment, sidewalks and
driveways as specified in Statewide Permit Number 6 issued by the Illinois
Department of Natural Resources, May 13, 1983 are exempt from the above
requirements. (C)
d) Local Approval. Prior to construction of a new camp, major
alteration or major extension of an existing camp, permits and zoning approval
required by local health departments and zoning boards as well as other
governmental units having jurisdiction shall be obtained by the permit
applicant. (C)
e) Existing Facilities. A permit is not required when existing
facilities are utilized for a migrant labor camp. Plans indicating the general
location of all structures and utilities shall be submitted to the Department.
The existing facilities will be inspected by the Department for compliance with
this Part. Any violations identified during the inspection of the facilities
shall be corrected, and the facilities shall be brought into essential
compliance with this Part prior to the issuance of a license. (C)
f) Repairs. A permit is not required to repair a facility in a
licensed migrant labor camp or to correct a violation of this Part when such
repair or correction is made to an existing facility and does not result in
expansion of any existing appurtenance or structure.
g) Minor Extension and Alterations. Construction at a migrant
labor camp less than a major extension or major alteration shall not require a
permit. However, prior to initiating construction, the applicant shall advise
in writing the regional office of the Department which serves the camp of the
scope of the alteration. (C)
h) EPA Approval
y existing appurtenance or structure.
g) Minor Extension and Alterations. Construction at a migrant
labor camp less than a major extension or major alteration shall not require a
permit. However, prior to initiating construction, the applicant shall advise
in writing the regional office of the Department which serves the camp of the
scope of the alteration. (C)
h) EPA Approval. The construction of all community water supply
systems and those surface discharge sewage disposal systems with flows greater
than 1,500 gallons per day requires a construction permit from the Illinois
Environmental Protection Agency. (C)