Section 201
TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE B: AIR POLLUTION
CHAPTER I: POLLUTION CONTROL BOARD
SUBCHAPTER a: PERMITS AND GENERAL PROVISIONS
PART 201 PERMITS AND GENERAL PROVISIONS
SECTION 201.APPENDIX C PART COMPLIANCE DATES
Section 201.APPENDIX C Part
Compliance Dates
Rule
103(b)(2)
Operating permits were required
as follows:
SOURCE CLASSIFICATION
DATE OPERATING PERMIT REQUIRED
Primary Metal Industry Operations as defined by code 33 of
the “Standard Industrial Classification Manual”
By December 1, 1972
Rubber and Plastics Products Industry Operations as
defined by code 30 of the “Standard Industrial Classification Manual”
By December 1, 1972
Chemicals and Allied Products Industry Operations as
defined by code 28 of the “Standard Industrial Classification Manual”
By January 1, 1973
Food and Kindred Products Industry Operations as defined
by code 20 and Printing and Publishing Industry Operations as defined by code
27 of the “Standard Industrial Classification Manual”
By February 1, 1973
Petroleum and Coal Products Indusry Operations as defined
by code 29 of the “Standard Industrial Classification Manual” and bituminous
cement (asphalt) plants
By February 1, 1973
Stone, Clay and Glass Products and Paper and Allied
Products Industry Operations as defined by code 32 and 26 of the “Standard
Industrial Classification Manual” and all painting operations using in excess
of 5,000 gallons of paint (including thinner) per year
By March 1, 1973
Incinerators
By April 1, 1973
Electric, Gas, and Sanitary Services as defined by code 49
of the “Standard Industrial Classification Manual” and coal fired boilers
By May 1, 1973
Gas and Oil fired boilers and all other emission sources
or air pollution control equipment not listed previously in this paragraph
except equipment excluded under paragraph (i) of this Rule
June 1, 1973
Grain-Handling and Conditioning Operations
By March 1, 1976
Grain-Handling and Grain-Drying Operations
By March 1, 1976
(B) All applications for Operating Permits shall be
s
By May 1, 1973
Gas and Oil fired boilers and all other emission sources
or air pollution control equipment not listed previously in this paragraph
except equipment excluded under paragraph (i) of this Rule
June 1, 1973
Grain-Handling and Conditioning Operations
By March 1, 1976
Grain-Handling and Grain-Drying Operations
By March 1, 1976
(B) All applications for Operating Permits shall be submitted to
the Agency at least 90 days prior to the date on which an Operating Permit is
required. Provided, however, the Agency may waive this 90 day requirement when
appropriate. If necessary, to prevent an unmanageable workload as may be
deemed appropriate, the Agency may extend the dates by which Operating Permits
are required under Section 103(b)(2)(A) for a period not to exceed four
months. The Agency shall notify the persons affected and the Board in writing
of the extension at least four months before the dates set forth in Section
103(b)(2)(A).
(C) Nothing in this Rule shall preclude any person from applying
for an Operating Permit earlier than the dates specified in part (b)(2)(A) of
this Rule 103.
Rule 103(b)(6)(G)
No operating permit could be
granted unless the applicant submitted proof to the Agency that:
if subject to a future compliance date, the applicant was, on the
effective date of this Chapter, and is at the time of application for an
Operating Permit pursuant to Rule 103(b)(2), in compliance with any applicable
emission standards of the Rules and Regulations Governing the Control of Air
Pollution of the former State of Illinois Air Pollution Control Board; or was,
on the effective date of this Chapter, in full compliance with any variance
from those regulations granted by the Pollution Control Board; or has been,
since the effective date of this Chapter, granted a variance from those
regulations, and is in full compliance with such variance.
Rule 104(g)
Submission and Approval Dates
on of the former State of Illinois Air Pollution Control Board; or was,
on the effective date of this Chapter, in full compliance with any variance
from those regulations granted by the Pollution Control Board; or has been,
since the effective date of this Chapter, granted a variance from those
regulations, and is in full compliance with such variance.
Rule 104(g)
Submission and Approval Dates.
The owner or operator of an emission source subject to the following rules was
required to have a Compliance Plan and a Project Completion Schedule, where
applicable, approved by the Agency by the following dates. A Compliance Plan
and a Project Completion Schedule, where applicable, shall be submitted at
least 90 days before the following dates.
(1) By February 1, 1980. Gasoline Dispensing facilities subject
to Rule 205(p) and degreasers subject to Rule 205(k) located in Cook, DuPage,
Lake, Kane, McHenry and Will counties.
(2) By March 1, 1980. Petroleum refineries subject to Rule
205(1), except (1) (4)-(10). Gasoline dispensing facilities subject to Rule
205(p) in Boone, Madison, St. Clair, Peoria, Tazewell, Rock Island and
Winnebago counties.
(3) By April 1, 1980. Degreasers subject to Rule 205(k) located
in counties other than Cook, DuPage, Lake, Kane, McHenry or Will. Bulk
gasoline plants, bulk gasoline terminals and petroleum liquid storage tanks
subject to Rule 205(o), except (o) (3), located in Cook, DuPage, Lake, Kane,
McHenry and Will counties.
(4) By April 1, 1980. Coating lines subject to Rule 205(n),
except (n)(1)(J), and (K). Bulk gasoline plants, bulk gasoline terminals and
petroleum liquid storage tanks subject to Rule 205(o), except (o)(3), which are
located in counties other than Cook, Lake, DuPage, Kane, McHenry or Will.