a) The regulatory floodway is defined based on a flood event that
has a one percent annual chance of exceedence or an expected 100-year
recurrence interval. The Department encourages, but does not require, that the
100-year frequency flood event be determined based on anticipated future land
use in the watershed. When utilized, anticipated future land use should be
based on adopted local or regional land use plans.
b) The boundary of the regulatory floodway is portrayed on
Department regulatory floodway maps. To locate the regulatory floodway
boundary on any site, the regulatory floodway boundary should be scaled off the
regulatory floodway map and located on a site plan, using reference marks
common to both maps. Where interpretation is needed to determine the exact
location of the regulatory floodway boundary, the Office should be contacted
for the interpretation.
c) The regulatory floodway boundaries are determined by hydraulic
and hydrologic analyses, which calculate that portion of the flood plain which
must be preserved to store and discharge floodwaters without causing damaging
or potentially damaging increases in flood stage and flood velocities or loss
of flood storage which would result singularly or cumulatively in more than a
0.1 foot increase in flood stage or a 10% increase in velocity.
d) The need to preserve storage when defining the regulatory
floodway will be waived by the Department if all the municipalities and
counties along a hydraulically significant portion of the watershed require
effective compensatory storage for all construction and fill in the 100-year
frequency flood plain. Effective compensatory storage requires flood plain
storage volumes be replaced at the same flood frequency event as previously
existed
egulatory
floodway will be waived by the Department if all the municipalities and
counties along a hydraulically significant portion of the watershed require
effective compensatory storage for all construction and fill in the 100-year
frequency flood plain. Effective compensatory storage requires flood plain
storage volumes be replaced at the same flood frequency event as previously
existed. Additionally, legal assurances such as easements must be provided so
that the compensatory storage site will remain open to the stream system in
order to allow flood waters to reach it.
e) Determination of the flood elevation at any point along the
stream shall be made from the flood profile.