NUCLEAR REGULATORY COMMISSION

10 CFR Parts 30, 40, and 70

RIN 3150-AF38

One-Time Extension of Certain Byproduct, Source, and Special

Nuclear Materials Licenses

AGENCY: Nuclear Regulatory Commission.

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: The Nuclear Regulatory Commission (NRC) is amending its

regulations to implement, on a one-time basis, a five-year extension of

certain byproduct, source, and special nuclear materials licenses. The

provisions of the licenses under extension provide the same

authorizations and limits on licensee activities as they do now. The

final rule specifies the licenses that are not extended.

EFFECTIVE DATE: February 15, 1996.

FOR FURTHER INFORMATION CONTACT: John M. Pelchat, NRC, Region II, 101

Marietta Street, N.W., Suite 2900, Atlanta, GA 30323, telephone (404)

331-5083; or C. W. Nilsen, Office of Nuclear Regulatory Research, NRC,

Washington, DC 20555, telephone (301) 415-6209.

SUPPLEMENTARY INFORMATION:

Background

The NRC has completed the preliminary phases of an effort to

redesign the process for licensing medical, academic, and industrial

users of byproduct materials as well as some small scope users of

source and special nuclear materials. To make resources available to

expedite the development, design, and testing of the new materials

licensing process, the Commission is extending certain specific

materials licenses (``licenses'') by five years from the current

expiration dates of those licenses. Resources that would have otherwise

been used to renew these licenses will be devoted to the redesign

project. The extension will be a one-time occurrence. The Commission

does not envision that any similar extensions will be granted in the

future.

The extension granted by this rulemaking does not apply to the

licenses for power and non-power reactors, uranium milling and

processing facilities, or fuel production facilities. The extended

licenses are not considered to be the equivalent of a renewed license

because they provide the same authorizations and limits on licensee

activities as are currently applicable to each licensee. Accordingly,

the extended licenses will not be based on nor reference pending

renewal applications, including requests, if any, in those renewal

applications, for NRC approval of changes in current operations. The

frequency of licensee inspections will not change as a result of this

final rule.

The Commission concludes that it may take this action because no

legislative mandate requires that materials licenses have a five-year

term. Many years ago, materials licenses were issued for two-year

periods. As the uses of radioactive materials became more stable and

predictable, the typical duration of licenses was changed to five

years. The Commission has concluded that certain specific materials

licenses may be extended once by rule for an additional five years

beyond their stated expiration date without the normal renewal review

and without adverse effect on public health and safety. The

Commission's conclusion is based upon three factors. First, certain

specific licenses for which the Commission believes that a renewal

review should not be delayed five years will not be affected by this

rule. Licenses that may present, in the Commission's view, a greater

potential risk from a health and safety standpoint will not be

generically

extended by this rulemaking. Second, the extended licenses will not

change the authorized activities nor regulatory requirements. Third,

the NRC will continue its normal inspection program of licensed

activities, including inspections of those licenses that will be

extended by this final rule. Significant inspection findings will be

resolved through the issuance of Notices of Violations that require

written responses describing corrective actions, Confirmatory Action

Letters (CALs), or Orders that would modify, suspend, or revoke the

license and that would impose civil penalties, as appropriate.

Accordingly, the Commission has concluded that there would be

reasonable assurance of public health and safety under this rule.

Summary of Requirements and Analysis of Public Comments

The NRC is amending Parts 30, 40, and 70 of its regulations to

extend, on a one-time basis, certain byproduct, source, and special

nuclear materials licenses. These regulations specify the licenses that

are not extended by this rulemaking. The NRC received 28 letters of

public comment: twenty-one from licensees; one from an Agreement State;

none from non-Agreement States; two from consulting firms; two from

private citizens; and two from trade associations. Eighteen commenters

supported the proposed rule and one was opposed. Eight commenters

supported the rulemaking to varying degrees, but offered suggestions

for modification of the rules. One comment addressed issues to be

considered by the NRC should the rulemaking be implemented, without

stating support or opposition for the proposed rule.

Commenters supporting the proposed rule cited the cost savings to

taxpayers, affected licensees, and the general public. Some of these

commenters also supported the redesign effort of the materials

licensing process.

One commenter supported the proposed rule and suggested that the

rulemaking be amended to include the Quality Assurance program

requirements in 10 CFR Part 71. The suggested amendment is outside of

the scope of the proposed rulemaking.

Another commenter supported the proposed rule but noted there was

no mention of specific cost reductions to the licensee as a result of

this extension and stated that this point should be addressed. The NRC

recognizes that, on a one-time basis, many licensees will save the

renewal fee required by 10 CFR 170.31 as well as the costs associated

with the preparation of the renewal application. The NRC staff did not

attempt to quantify these costs, recognizing the significant

variability among licensees as to the effort required to prepare

license renewal applications. In addition, the NRC staff believes these

savings will be offset to some extent by the need for those licensees

to prepare and submit license amendment requests (and associated fees)

to request necessary changes in their programs that may have been

included in the license renewal application.

Another commenter supported the proposed rulemaking but also

suggested that the NRC reevaluate its fee structure. The fees structure

and questions relating to the assessment of fees are outside the scope

of this rulemaking.

Another commenter expressed general support for the effort to

redesign the licensing process and stated that the renewal process was

redundant, and served no useful purpose that could not otherwise be

achieved more effectively through the license amendment and inspection

processes. The commenter urged the NRC to reconsider the proposed rule

and remove the license renewal process from the regulations. The issue

of deleting the license renewal process from the regulations is beyond

the scope of this rulemaking. However, this comment will be considered

as part of the Office of Nuclear Material Safety and Safeguards'

(NMSS') initiative to review the appropriate duration of the licenses

and the certificates that it issues. In addition, for uranium recovery

facilities, the Commission staff is currently analyzing the possibility

of extending the duration of licenses for that class of licensees. Once

the staff has completed its analysis and consulted with the Commission,

the NRC will determine what, if any action it will take in extending

the duration of uranium recovery facility licenses. This final rule

extends certain materials licenses on a one-time basis and NMSS'

consideration of the appropriate duration of materials licenses is a

separate issue being considered by the NRC.

A commenter who objected to the proposed rulemaking stated that the

renewal process is valuable because it forces licensees to examine

their programs and bring records up to date. The commenter also noted

that the proposed rulemaking was indicative of the NRC's `` * * *

arrogant, deficient attitude toward safety.'' In response to the

comment, the NRC staff notes that 10 CFR 20.1101 requires all specific

licensees to develop, document, and implement a radiation protection

program commensurate with the scope and extent of licensed activities.

The regulation further requires that licensees periodically (at least

annually) review the content and the implementation of the radiation

protection program. The Commission believes that this requirement, the

criteria set out in this rulemaking, and the NRC's ongoing inspection

program are sufficient to ensure that licensees develop and implement

radiation programs and periodically review them to assess the program's

effectiveness. It must also be recognized that the NRC is not

eliminating the need to file for a renewal but is only changing the

time frame for renewal of licenses affected by this rulemaking.

An Agreement State submitted a comment concerning provisions that

the NRC should have available to ensure that persons could determine

that a specific license was extended as a result of this rulemaking.

The NRC staff is developing procedures to implement this rule,

including providing prompt notification to licensees whose licenses

have been extended by the final rule.

The Commission also sought public comments on the issue of license

duration. Ten of the persons who commented on the one-time extension

also provided specific comments regarding the appropriate duration of

material licenses. Several commenters suggested that a license term of

ten years would be appropriate. One commenter specifically suggested

that medical licenses be issued for seven years. Three commenters

suggested licenses have a term of twenty years. Another commenter

suggested that a license be initially issued for two to four years, to

allow a new licensee to demonstrate its stability. The terms of

subsequent license renewals could then be extended for up to twenty

years. The NRC will consider these comments in the development of its

policy concerning the duration of material licenses.

Other comments addressed specific components of the proposed rule.

Those comments and their resolutions are discussed below and, to the

extent possible, are arranged under the identified section of the rule

to which they are related. For the purpose of clarity, the common

elements of the comment discussion will be grouped by the nature of the

requirements, because the new regulatory requirements in 10 CFR Parts

30, 40, and 70 closely parallel each other.

Description of Rulemaking and Analysis of Specific Public Comments

The final rule was based on and mainly derived from the current

provisions in 10 CFR Parts 30, 40, and 70. Parts 30, 40, and 70 contain

the

general requirements used by the Commission to license the possession

and use of byproduct, source, and special nuclear materials. Specific

sections being added or amended by this final rulemaking include the

following:

10 CFR 30.36(a)(2), 40.42(a)(2), and 70.38(a)(2)

These paragraphs state that each specific license that has an

expiration date after July 1, 1995, has an expiration date that is 5

years after the expiration date stated in the current license, unless

it is specifically excluded by the final amendments contained in this

rule. This extends all licenses, that are not otherwise disqualified by

the regulations, by five years without the requirement for the licensee

to prepare and submit a license renewal application 30 days before the

expiration date in the current license. Licensees holding licenses that

are extended by this rule would not be required to take any action to

renew the license until 30 days before the end of the extension which

will end five years after the date currently specified on the license.

Licensees who hold licenses that are not extended by this rule will

continue to be required to either file for license renewal 30 days

before the expiration date currently specified in the license or comply

with the applicable license termination requirements specified in 10

CFR 30.36, 40.42, and 70.38.

No specific comments were received on these paragraphs.

Paragraphs 30.36(a)(3)(i), 40.42(a)(3)(j), and 70.38(a)(3)(i)

These paragraphs delineate the specific licenses that are not

extended by the final rule because an evaluation or an emergency plan

is required in accordance with 10 CFR 30.32(i), 40.31(j), or 70.22(i),

respectively. This excludes those licenses that require an evaluation

or an emergency plan, because these licenses authorize activities

involving large quantities of unsealed licensed materials that the

Commission believes may pose a significant potential for release of

radioactive materials that may result in potential exposure to the

public and contamination of the environment. Therefore, the Commission

believes that it would be prudent to review these licenses individually

during the renewal process before making a determination to extend

these licenses.

One commenter took exception to the NRC's statements, in the

proposed rule, which it believed implied that its member organizations,

many of whom are ineligible for the one-time extension based on the

size and the scope of their licensed programs and the regulatory

requirement for an emergency plan, pose relatively greater safety

risks. The commenter indicated that it did not believe these licensees

have a significant potential for release of licensed material and

public exposure. The commenter further noted that there have been no

incidents where members of the public received significant exposures

from licensed materials, that the licensees' controls were sufficient

to contain licensed materials, and that maximum credible release

scenarios showed insignificant offsite impacts.

In developing its criteria to disqualify certain material licenses

from the extension, the NRC staff considered its licensees' operations

on a scale of relative hazard. The NRC used previously-established

criteria (i.e., the need to have emergency plans, the need to have

adequate financial assurance to fund decommissioning, etc.) to

determine which licensed operations were relatively more hazardous,

thus deserving closer NRC oversight. The NRC believes that licenses

authorizing possession and use of large quantities of unsealed high-

activity radionuclides pose a greater potential for hazard than do

licenses authorizing use of sealed sources with engineered safety

features or licenses authorizing smaller quantities of lower activity

radionuclides. The NRC did not state or suggest that this group of

licensees has released licensed materials, exposed the public, or

contaminated the environment. The NRC only indicated that the scope of

activities carried out by this group of licensees, using previously

established standards, has the potential for such releases and,

accordingly, should not be generically extended by this rule. The NRC

believes that a licensee possessing sufficient quantities of licensed

materials to be subject to the requirements of 10 CFR 30.32(i),

40.31(j), or 70.22(i) should file renewal applications so the NRC staff

can review the licensee's overall operations before granting an

extended license term.

Another commenter objected to the disqualification for an extension

based on need for an evaluation or an emergency plan as required in 10

CFR 30.32(i), 40.31(j), or 70.22(i). The commenter suggested that the

disqualifier for extension based on the need for contingency planning

be structured similarly to the disqualifier based on the need for

financial assurance. In other words, amend the rule to not extend any

license whose holder is required to provide an evaluation or an

emergency plan ``. . . and who has not submitted such a plan.'' The

commenter indicated that the NRC acceptance of the required evaluation

or emergency plan should be sufficient to allow a license to be

eligible for extension. The commenter alternatively suggested that its

particular situation be evaluated on a case-by-case basis.

The NRC has concluded that licensees required to submit either an

evaluation or an emergency plan are authorized to possess and use

sufficient quantities of licensed materials to warrant closer NRC

oversight to ensure that conditions related to the evaluation have not

changed or that the emergency plan continues to be appropriate and

adequate with regard to the scope of the licensee's activities. The NRC

believes that holders of this type of license should continue to submit

this type of information in renewal applications and that these

licenses should not be subject to the one-time license extension. The

one-time extension of licenses is being pursued through rulemaking,

rather than on a case-by-case basis, so as to free the maximum amount

of NRC resources to revise the current materials licensing process. The

NRC is in the process of reviewing the appropriate duration for

materials licensees. After completing the case-by-case review that will

take place during the renewal process for those licenses not extended

by this rulemaking, the NRC may decide to grant license renewals for

periods exceeding the five-year duration typical under current practice

depending on the results of the ongoing review of license duration.

Paragraphs 30.36(a)(3)(ii), 40.42(a)(3)(ii), and 70.38(a)(3)(ii)

These paragraphs delineate the specific licenses that are not

extended under the final rule because the licenses are subject to the

financial assurance requirements specified in 10 CFR 30.35, 40.36, or

70.25; and either: (a) have not submitted a decommissioning funding

plan or certification of financial assurance for decommissioning; or

(b) have not received written notice as of February 15, 1996 that the

decommissioning funding plan or certification of financial assurance

for decommissioning is acceptable. These licenses authorize possession

of quantities and forms of licensed materials that the Commission

believes pose a potential need for extensive decontamination before

termination of the license and release of decommissioned facilities.

Therefore, the Commission believes that renewals of these licenses

should continue to be reviewed under existing procedures to

ensure that appropriate resources are available to support

decommissioning activity.

No specific comments were received on these paragraphs.

Paragraphs 30.36(a)(3)(iii), 40.42(a)(3)(iii), and 70.38(a)(3)(iii)

These paragraphs delineate the specific licenses that are not

extended under the final rule because the licenses are listed in the

Site Decommissioning Management Plan (SDMP). Generally, licenses on the

SDMP list are no longer actively using licensed materials. The

Commission believes that it is necessary in the interest of public

health and safety to review the licensee's procedures to ensure proper

evaluation of site remediation activities at facilities where the

licensee's radiation safety program may be inactive or scaled back.

No specific comments were received on these paragraphs.

Paragraphs 30.36(a)(3)(iv), 40.42(a)(3)(iv), and 70.38(a)(3)(iv)

These paragraphs delineate the specific licenses that are not

extended because the issuance, amendment, or renewal of this type of

license is not a categorical exclusion under 10 CFR 51.22(c)(14). This

excludes licenses that include activities requiring the preparation of

an environmental assessment or environmental impact statement, before

the Commission's specific authorization of that activity, from the

five-year extension. Generally, these licenses authorize the release of

licensed materials to the environment under highly controlled

conditions in conjunction with scientific research activities. The

Commission has concluded that it is important to continue reviewing

licenses that may have a greater potential for adversely impacting the

environment before making decisions on to whether to grant these

licensees' licenses with longer durations.

No specific comments were received on these paragraphs.

Paragraphs 30.36(a)(3)(v), 40.42(a)(3)(v), and 70.38(a)(3)(v)

These paragraphs delineate the specific licenses that are not

extended under the final rule because the holders of these specific

licenses have not had a prior NRC inspection as of February 15, 1996.

This ensures that the Commission has verified the effectiveness of the

licensees' radiation safety programs by onsite inspections of the

licensees' equipment and procedures used to safely possess and use

licensed materials, as a precondition to allowing five-year extensions

of licenses, under these amendments to the regulations.

No specific comments were received on these paragraphs.

Paragraphs 30.36(a)(3)(vi), 40.42(a)(3)(vi), and 70.38(a)(3)(vi)

These paragraphs delineate the specific licenses that are not

extended under the final rule if, as the result of the most recent

inspections, the holders of these specific licenses have been:

(a) Cited for a Severity Level I, II, or III violation;

(b) Subject to an Order issued by the NRC; or

(c) Subject to a Confirmatory Action Letter (CAL) issued by the

NRC.

This excludes licenses from the five-year extensions, after the NRC

has identified significant safety concerns or other regulatory issues.

Typically, these licensees are reinspected within six months, to verify

that effective corrective actions have been taken and to ensure that

the licensees' facilities, equipment, and procedures have been

adequately modified to prevent a recurrence of the identified

violations. The Commission expects its licensees to operate in strict

compliance with its regulatory requirements. Therefore, the Commission

believes that it is prudent to review license renewal applications of

licensees with recent safety-significant findings so that the NRC can

verify that the licensees have adequate personnel, facilities, and

procedures to enable them to operate at the expected level of

compliance.

A commenter objected to use of the issuance of a CAL as a

disqualifier from the one-time license extension. The NRC chose to

disqualify from the one-time extension those licenses that have

exhibited significantly declining or poor performance with regard to

compliance with the NRC regulations as documented at the time of the

most recent NRC inspection. One such indicator of significantly

declining or poor performance is the issuance of a CAL. NRC recognizes

that licensees receiving a CAL usually take the necessary corrective

actions. The NRC expects that licensees will take timely and effective

corrective actions. CALs specifically state that the failure to do so

may result in the NRC's issuance of an order modifying, suspending, or

revoking the subject license. The NRC does not believe that it should

extend these licenses without having first verified, by direct

observation as well as other evaluations, during follow-up inspections,

that the licensees' corrective actions were, in fact, effective.

Another commenter noted that a modest improvement in program safety

can be expected as a result of this rulemaking because the rule bestows

a tangible, public, and previously unexpected reward on those licensees

that have maintained programs free of significant violations.

Paragraphs 30.36(a)(3)(vii), 40.42(a)(3)(vii), and 70.38(a)(3)(vii)

These paragraphs delineate the specific licenses that are not

extended under the final rule because the Commission intends to

continue to review the submissions of these licensees who have already

submitted applications and paid fees for timely license renewal.

Renewal requests will be granted after the NRC completes its review of

those applications and determines that the applications satisfy NRC

requirements. The July 1, 1995, expiration date was chosen based on

resource considerations. The NRC staff has begun the review of many

applications for renewal of licenses with expiration dates before July

1, 1995, and believes that it is not appropriate to waste the resources

already expended in that effort. However, the NRC has not begun the

review of most of the applications for renewal of licenses with

expiration dates after July 1, 1995, and resources will be conserved by

extending those licenses.

No specific comments were received on these paragraphs.

Paragraph 70.38(a)(3)(viii)

This paragraph delineates the specific licenses that are not

extended under the final rule because the licenses authorize possession

of sufficient quantities of special nuclear material to be subject to

the criticality accident requirements of 10 CFR 70.24. This excludes

those licenses from the five-year extension because the Commission

believes that it is prudent to continue reviewing the licensees'

existing programs before granting licenses for longer durations to

ensure the adequacy of the licensees' criticality safety procedures.

No specific comments were received on this paragraph.

Paragraphs 30.37(b), 40.43(b), and 70.33(b)

These paragraphs specify that any pending license renewal

applications for specific licenses that are extended under the final

rule are automatically withdrawn. Any paid license renewal fees for

withdrawn applications will be refunded.

Two comments generally supportive of the rule expressed concern

about licensees who had already prepared

license renewal applications for submission to the NRC. One commenter

suggested that licensees whose licenses expired after July 1, 1995, and

who have prepared complete renewal applications without reference to

previously submitted documents should have the option of: (1) Having

their new renewal application reviewed and the license renewed; or (2)

having the existing license extended. The other commenter had prepared

complete license renewal applications, for its clients, that included

descriptions of the radiation safety programs updated to reflect the

revisions to 10 CFR part 20 that became effective January 1, 1994. The

commenter suggested that these applications be reviewed and the

licenses renewed, rather than extended.

The NRC believes that as many eligible licenses as possible should

be extended, to achieve the maximum resource savings possible for use

in redesigning the materials licensing process. However, the NRC also

recognizes that some licensees may want the NRC to review part or all

of their license renewal applications. Licensees whose license renewal

applications are automatically withdrawn by this rulemaking but whose

renewal applications contain revisions that they need to have

incorporated in their licenses, should submit those changes as an

amendment request accompanied by the appropriate amendment fees.

Environmental Impact: Categorical Exclusion

The NRC has determined that these regulations are the type of

actions described in the categorical exclusion in 10 CFR 51.22(c)(3).

Therefore, neither an environmental impact statement nor an

environmental assessment has been prepared for this regulation.

Paperwork Reduction Act

This final rule does not contain a new or amended information

collection requirement subject to the Paperwork Reduction Act of 1995

(44 U.S.C. 3501, et seq.). Existing requirements were approved by the

Office of Management and Budget (OMB) approval number 3150-0009 (Part

70) and 3150-0120 (Parts 30 and 40). The NRC may not conduct nor

sponsor, and a person is not required to respond to, a collection of

information unless it displays a currently valid OMB control number.

Regulatory Analysis

A regulatory analysis has not been prepared for this rule because

it is not expected to have any adverse impact on licensees subject to

the final rule. These licensees will be postponing the submission of

license renewal applications and the associated fees for five years.

Regulatory Flexibility Analysis

As required by the Regulatory Flexibility Act of 1980, 5 U.S.C.

605(b), the Commission certifies that these rules will not have a

significant economic impact on a substantial number of small entities.

These rules merely extend, on a one-time basis, certain existing

byproduct, source, and special nuclear materials licenses that meet

specified criteria by five years and therefore, will not result in any

adverse impact.

Backfit Analysis

The NRC has determined that the backfit rule, 10 CFR 50.109, does

not apply to this final rule and, therefore, that a backfit analysis is

not required for this rulemaking because these amendments do not

involve any provisions that would impose backfits as defined in 10 CFR

50.109(a)(1).

List of Subjects

10 CFR Part 30

Byproduct material, Criminal penalties, Government contracts,

Intergovernmental relations, Isotopes, Nuclear materials, Radiation

protection, Reporting and recordkeeping requirements.

10 CFR Part 40

Criminal penalties, Government contracts, Hazardous materials

transportation, Nuclear materials, Reporting and recordkeeping

requirements, Source material, Uranium.

10 CFR Part 70

Criminal penalties, Hazardous materials transportation, Material

control and accounting, Nuclear materials, Packaging and containers,

Radiation protection, Reporting and recordkeeping requirements,

Scientific equipment, Security measures, Special nuclear material.

For the reasons set out in the preamble and under the authority of

the Atomic Energy Act of 1954, as amended; the Energy Reorganization

Act of 1974, as amended; and 5 U.S.C. 552 and 553; the Nuclear

Regulatory Commission is adopting the following amendments to 10 CFR

Parts 30, 40, and 70.

PART 30--RULES OF GENERAL APPLICABILITY TO DOMESTIC LICENSING OF

BYPRODUCT MATERIAL

1. The authority citation for 10 CFR Part 30 continues to read as

follows:

Authority: Secs. 81, 82, 161, 182, 183, 186, 68 Stat. 935, 948,

953, 954, 955, as amended, sec. 234, 83 Stat. 444, as amended (42

U.S.C. 2111, 2112, 2201, 2232, 2233, 2236, 2282); secs. 201, as

amended, 202, 206, 88 Stat. 1242, as amended, 1244, 1246 (42 U.S.C.

5841, 5842, 5846).

Section 30.7 also issued under Pub. L. 95-601, sec. 10, 92 Stat.

2951 as amended by Pub. L. 102-486, sec. 2902, 106 Stat. 3123 (42

U.S.C. 5851). Section 30.34(b) also issued under sec. 184, 68 Stat.

954, as amended (42 U.S.C. 2234). Section 30.61 also issued under sec.

187, 68 Stat. 955 (42 U.S.C. 2237).

2. In 10 CFR 30.36, paragraph (a) is revised to read as follows:

Sec. 30.36 Expiration and termination of licenses and decommissioning

of sites and separate buildings or outdoor areas.

(a)(1) Except as provided in paragraph (a)(2) of this section, each

specific license expires at the end of the day on the expiration date

stated in the license unless the licensee has filed an application for

renewal under Sec. 30.37 not less than 30 days before the expiration

date stated in the existing license (or, for those licenses subject to

paragraph (a)(2) of this section, 30 days before the deemed expiration

date in that paragraph). If an application for renewal has been filed

at least 30 days before the expiration date stated in the existing

license (or, for those licenses subject to paragraph (a)(2) of this

section, 30 days before the deemed expiration date in that paragraph),

the existing license expires at the end of the day on which the

Commission makes a final determination to deny the renewal application

or, if the determination states an expiration date, the expiration date

stated in the determination.

(2) Each specific license that has an expiration date after July 1,

1995, and is not one of the licenses described in paragraph (a)(3) of

this section, shall be deemed to have an expiration date that is five

years after the expiration date stated in the current license.

(3) The following specific licenses are not subject to, or

otherwise affected by, the provisions of paragraph (a)(2) of this

section:

(i) Specific licenses for which, on February 15, 1996, an

evaluation or an emergency plan is required in accordance with

Sec. 30.32(i);

(ii) Specific licenses whose holders are subject to the financial

assurance

requirements specified in 10 CFR 30.35, and on February 15, 1996, the

holders either:

(A) Have not submitted a decommissioning funding plan or

certification of financial assurance for decommissioning; or

(B) Have not received written notice that the decommissioning

funding plan or certification of financial assurance for

decommissioning is acceptable;

(iii) Specific licenses whose holders are listed in the SDMP List

published in NUREG 1444, Supplement 1 (November 1995);

(iv) Specific licenses whose issuance, amendment, or renewal, as of

February 15, 1996, is not a categorical exclusion under 10 CFR

51.22(c)(14) and, therefore, need an environmental assessment or

environmental impact statement pursuant to Subpart A of Part 51 of this

chapter;

(v) Specific licenses whose holders have not had at least one NRC

inspection of licensed activities before February 15, 1996;

(vi) Specific licenses whose holders, as the result of the most

recent NRC inspection of licensed activities conducted before February

15, 1996, have been:

(A) Cited for a Severity Level I, II, or III violation in a Notice

of Violation;

(B) Subject to an Order issued by the NRC; or

(C) Subject to a Confirmatory Action Letter issued by the NRC.

* * * * *

(vii) Specific licenses with expiration dates before July 1, 1995,

for which the holders have submitted applications for renewal under 10

CFR 30.37 of this part.

3. In 10 CFR 30.37, a new paragraph (b) is added to read as

follows:

Sec. 30.37 Application for renewal of licenses.

* * * * *

(b) If any licensee granted the extension described in 10 CFR

30.36(a)(2) has a currently pending renewal application for the

extended license, that application will be considered withdrawn by the

licensee and any renewal fees paid by the licensee for that application

will be refunded.

PART 40--DOMESTIC LICENSING OF SOURCE MATERIAL

4. The authority citation for 10 CFR Part 40 continues to read as

follows:

Authority: Secs. 62, 63, 64, 65, 81, 161, 182, 183, 186, 68

Stat. 932, 933, 935, 948, 953, 954, 955, as amended, secs. 11e(2),

83, 84, Pub. L. 95-604, 92 Stat. 3033, as amended, 3039, sec. 234,

83 Stat. 444, as amended (42 U.S.C. 2014(e)(2), 2092, 2093, 2094,

2095, 2111, 2113, 2114, 2201, 2232, 2233, 2236, 2282); sec. 274,

Pub. L. 86-373, 73 Stat. 688 (42 U.S.C. 2021); secs. 201, as

amended, 202, 206, 88 Stat. 1242, as amended, 1244, 1246 (42 U.S.C.

5841, 5842, 5846); sec. 275, 92 Stat. 3021, as amended by Pub. L.

97-415, 96 Stat. 2067 (42 U.S.C. 2022).

Section 40.7 also issued under Public Law 95-601, sec. 10, 92 Stat.

2951 as amended by Pub. L. 102-486, sec. 2902, 106 Stat. 3123, (42

U.S.C. 5851). Section 40.31(g) also issued under sec. 122, 68 Stat. 939

(42 U.S.C. 2152). Section 40.46 also issued under sec. 184, 68 Stat.

954, as amended (42 U.S.C. 2234). Section 40.71 also issued under sec.

187, 68 Stat. 955 (42 U.S.C. 2237).

5. In Sec. 40.42, paragraph (a) is revised to read as follows:

Sec. 40.42 Expiration and termination of licenses and decommissioning

of sites and separate buildings or outdoor areas.

(a)(1) Except as provided in paragraph (a)(2) of this section, each

specific license expires at the end of the day on the expiration date

stated in the license unless the licensee has filed an application for

renewal under Sec. 40.43 not less than 30 days before the expiration

date stated in the existing license (or, for those licenses subject to

paragraph (a)(2) of this section, 30 days before the deemed expiration

date in that paragraph). If an application for renewal has been filed

at least 30 days before the expiration date stated in the existing

license (or, for those licenses subject to paragraph (a)(2) of this

section, 30 days before the deemed expiration date in that paragraph),

the existing license expires at the end of the day on which the

Commission makes a final determination to deny the renewal application

or, if the determination states an expiration date, the expiration date

stated in the determination.

(2) Each specific license that has an expiration date after July 1,

1995, and is not one of the licenses described in paragraph (a)(3) of

this section, shall be deemed to have an expiration date that is five

years after the expiration date stated in the current license.

(3) The following specific licenses are not subject to, or

otherwise affected by, the provisions of paragraph (a)(2) of this

section:

(i) Specific licenses for which, on February 15, 1996, an

evaluation or an emergency plan is required in accordance with

Sec. 40.31(j);

(ii) Specific licenses whose holders are subject to the financial

assurance requirements specified in 10 CFR 40.36, and on February 15,

1996, the holders either:

(A) Have not submitted a decommissioning funding plan nor

certification of financial assurance for decommissioning; or

(B) Have not received written notice that the decommissioning

funding plan or certification of financial assurance for

decommissioning is acceptable;

(iii) Specific licenses whose holders are listed in the SDMP List

published in NUREG 1444, Supplement 1 (November 1995);

(iv) Specific licenses whose issuance, amendment, or renewal, as of

February 15, 1996, is not a categorical exclusion under 10 CFR

51.22(c)(14) and, therefore, need an environmental assessment or

environmental impact statement pursuant to Subpart A of Part 51 of this

chapter;

(v) Specific licenses whose holders have not had at least one NRC

inspection of licensed activities before February 15, 1996;

(vi) Specific licenses whose holders, as the result of the most

recent NRC inspection of licensed activities conducted before February

15, 1996, have been:

(A) Cited for a Severity Level I, II, or III violation in a Notice

of Violation;

(B) Subject to an Order issued by the NRC; or

(C) Subject to a CAL issued by the NRC.

(vii) Specific licenses with expiration dates before July 1, 1995,

for which the holders have submitted applications for renewal under 10

CFR 40.43 of this part.

* * * * *

6. In 10 CFR 40.43, a new paragraph (b) is added to read as

follows:

Sec. 40.43 Renewal of licenses.

* * * * *

(b) If any licensee granted the extension described in 10 CFR

40.42(a)(2) has a currently pending renewal application for the

extended license, that application will be considered to be withdrawn

by the licensee and any renewal fees paid by the licensee for that

application will be refunded.

PART 70--DOMESTIC LICENSING OF SPECIAL NUCLEAR MATERIAL

7. The authority citation for 10 CFR Part 70 continues to read as

follows:

Authority: Secs. 51, 53, 161, 182, 183, 68 Stat. 929, 930, 948,

953, 954, as amended, sec. 234, 83 Stat. 444, as amended, sec. 1701,

106 Stat. 2951, 2952, 2953 (42 U.S.C. 2071, 2073, 2201, 2232, 2233,

2282, 2297f); secs. 201, as amended, 202, 204, 206, 88 Stat. 1242,

as amended, 1244, 1245, 1246 (42 U.S.C. 5841, 5842, 5845, 5846).

Sections 70.1(c) and 70.20a(b) also issued under secs. 135, 141,

Public Law 97-425, 96 Stat. 2232, 2241 (42 U.S.C.

10155, 10161). Section 70.7 also issued under Public Law 95-601, sec.

10, 92 Stat. 2951 (42 U.S.C. 5851). Section 70.21(g) also issued under

sec. 122, 68 Stat. 939 (42 U.S.C. 2152). Section 70.31 also issued

under sec. 57d, Public Law 93-377, 88 Stat. 475 (42 U.S.C. 2077).

Sections 70.36 and 70.44 also issued under sec. 184, 68 Stat. 954, as

amended (42 U.S.C. 2234). Section 70.61 also issued under secs. 186,

187, 68 Stat. 955 (42 U.S.C. 2236, 2237). Section 70.62 also issued

under sec. 108, 68 Stat. 939, as amended (42 U.S.C. 2138).

8. In 10 CFR 70.38, paragraph (a) is revised to read as follows:

Sec. 70.38 Expiration and termination of licenses and decommissioning

of sites and separate buildings or outdoor areas.

(a)(1) Except as provided in paragraph (a)(2) of this section, each

specific license expires at the end of the day on the expiration date

stated in the license unless the licensee has filed an application for

renewal under Sec. 70.33 not less than 30 days before the expiration

date stated in the existing license (or, for those licenses subject to

paragraph (a)(2) of this section, 30 days before the deemed expiration

date in that paragraph). If an application for renewal has been filed

at least 30 days before the expiration date stated in the existing

license (or, for those licenses subject to paragraph (a)(2) of this

section, 30 days before the deemed expiration date in that paragraph),

the existing license expires at the end of the day on which the

Commission makes a final determination to deny the renewal application

or, if the determination states an expiration date, the expiration date

stated in the determination.

(2) Each specific license that has an expiration date after July 1,

1995, and is not one of the licenses described in paragraph (a)(3) of

this section, shall be deemed to have an expiration date that is five

years after the expiration date stated in the current license.

(3) The following specific licenses are not subject to, nor

otherwise affected by, the provisions of paragraph (a)(2) of this

section:

(i) Specific licenses for which, on February 15, 1996, an

evaluation or an emergency plan is required in accordance with

Sec. 70.22(i);

(ii) Specific licenses whose holders are subject to the financial

assurance requirements specified in 10 CFR 70.25, and on February 15,

1996, the holders either:

(A) Have not submitted a decommissioning funding plan or

certification of financial assurance for decommissioning; or

(B) Have not received written notice that the decommissioning

funding plan or certification of financial assurance for

decommissioning is acceptable;

(iii) Specific licenses whose holders are listed in the SDMP List

published in NUREG 1444, Supplement 1 (November 1995);

(iv) Specific licenses whose issuance, amendment or renewal, as of

February 15, 1996, is not a categorical exclusion under 10 CFR

51.22(c)(14) and, therefore, need an environmental assessment or

environmental impact statement pursuant to Subpart A of Part 51 of this

chapter;

(v) Specific licenses whose holders have not had at least one NRC

inspection of licensed activities before February 15, 1996;

(vi) Specific licenses whose holders, as the result of the most

recent NRC inspection of licensed activities conducted before February

15, 1996, have been:

(A) Cited for a Severity Level I, II, or III violation in a Notice

of Violation:

(B) Subject to an Order issued by the NRC; or

(C) Subject to a CAL issued by the NRC.

(vii) Specific licenses with expiration dates before July 1, 1995,

for which the holders have submitted applications for renewal under 10

CFR 70.33 of this part.

(viii) Specific licenses issued pursuant to 10 CFR 70.31 that, as

of February 15, 1996, are also subject to the requirements in

Sec. 70.24.

* * * * *

9. In 10 CFR 70.33, a new paragraph (b) is added to read as

follows:

Sec. 70.33 Renewal of licenses.

* * * * *

(b) If any licensee granted the extension described in 10 CFR

70.38(a)(2) has a currently pending renewal application for that

extended license, that application will be considered withdrawn by the

licensee and any renewal fees paid by the licensee for that application

will be refunded.

Dated at Rockville, Maryland, this 20th day of December, 1995.

For the Nuclear Regulatory Commission.

James M. Taylor,

Executive Director for Operations.

[FR Doc. 96-346 Filed 1-11-96; 2:00 pm]

BILLING CODE 7590-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.