DEPARTMENT OF DEFENSE

48 CFR Parts 1, 5, 14, and 36

[FAC 90-45; FAR Case 96-305; Item XIII]

RIN 9000--AH17

Federal Acquisition Regulation; Two-Phase Design Build Selection

Procedures

AGENCIES: Department of Defense (DOD), General Services Administration

(GSA), and National Aeronautics and Space Administration (NASA).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: The Civilian Agency Acquisition Council and the Defense

Acquisition Regulations Council have agreed on a final rule to amend

the Federal Acquisition Regulation (FAR) to implement Section 4105 of

the Clinger-Cohen Act of 1996 (Public Law 104-106), which authorizes

the use of two-phase design-build procedures for construction

contracting. This regulatory action was not subject to Office of

Management and Budget review under Executive Order 12866, dated

September 30, 1993, and is not a major rule under 5 U.S.C. 804.

EFFECTIVE DATE: January 1, 1997.

FOR FURTHER INFORMATION CONTACT: Mr. Jack O'Neill at (202) 501-3856 in

reference to this FAR case. For general information, contact the FAR

Secretariat, Room 4035, GS Building, Washington, DC 20405 (202) 501-

4755. Please cite FAC 90-5, FAR case 96-305.

SUPPLEMENTARY INFORMATION:

A. Background

A proposed rule with request for public comment was published in

the Federal Register at 61 FR 41212, August 7, 1996. Comments were

received from 77 respondents. After analysis of the public comments and

further consideration of the proposed language, the rule was revised at

FAR 36.104, 36.301(b)(2), and 36.303-1 to more closely conform to the

provisions of Section 4105 of Public Law 104-106. In addition, examples

of phase-two evaluation factors have been added at FAR 36.303-(a).

B. Regulatory Flexibility Act

This final rule may have a significant economic impact on a

substantial number of small entities within the meaning of the

Regulatory Flexibility Act, 5 U.S.C. 601 et seq., because the rule

reduces the cost of proposal preparation for those offerors not

selected for Phase Two, when two-phase design-build procedures are

used. A Final Regulatory Flexibility Analysis (FRFA) has been prepared

and is summarized as follows:

We estimate that approximately 1,465 small businesses responding

to two-phase design-build solicitations annually may save proposal

costs on an average of eight separate solicitations each. This final

rule imposes no new reporting or recordkeeping requirements.

A copy of the FRFA will be provided to the Chief Counsel for

Advocacy for the Small Business Administration. A copy of the FRFA may

be obtained from the FAR Secretariat. Comments are invited. Comments

from small entities concerning the affected FAR subpart will be

considered in accordance with 5 U.S.C. 610. Such comments must be

submitted separately and cite 5 U.S.C 601, et seq. (FAR Case 96-305),

in correspondence.

C. Paperwork Reduction Act

The Paperwork Reduction Act does not apply because the changes to

the FAR do not impose recordkeeping or information collection

requirements, or collections of information from offerors, contractors,

or members of the public which require the approval of the Office of

Management and Budget under 44 U.S.C. 3501, et seq.

List of Subjects in 48 CFR Parts 1, 5, 14, and 36

Government procurement.

Dated: December 24, 1996.

Edward C. Loeb,

Director, Federal Acquisition Policy Division.

Therefore, 48 CFR Parts 1, 5, 14, and 36 is amended as set forth

below:

1. The authority citation for 48 CFR Parts 1, 5, 14, and 36

continues to read as follows:

Authority: 40 U.S.C. 486(c); 10 U.S.C. chapter 137; and 42

U.S.C. 2473(c).

PART 1--FEDERAL ACQUISITION REGULATION SYSTEM

1.106 [Amended]

2. Section 1.106 is amended in the list following the introductory

paragraph by removing the FAR segment ``36.302'' and inserting

``36.213-2''.

PART 5--PUBLICIZING CONTRACT ACTIONS

3. Section 5.204 is amended by revising the first sentence to read

as follows:

5.204 Presolicitation notices.

Contracting officers shall publicize presolicitation notices in the

CBD (see 15.404 and 36.213-2). * * *

PART 14--SEALED BIDDING

4. Section 14.202-1 is amended in paragraph (a) by revising the

first parenthetical to read as follows:

14.202-1 Bidding time.

(a) * * * (For construction contracts, see 36.213-3(a)). * * *

* * * * *

5. Section 14.211 is amended by revising the first sentence of

paragraph (a) to read as follows:

14.211 Release of acquisition information.

(a) Before solicitation. Information concerning proposed

acquisitions shall not be released outside the Government before

solicitation except for presolicitation notices in accordance with

14.205-4(c) or 36.213-2, or long-range acquisition estimates in

accordance with 5.404, or synopses in accordance with 5.201. * * *

* * * * *

PART 36--CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS

6. Section 36.102 is amended by adding, in alphabetical order, the

definitions ``Design'', ``Design-bid-build'', ``Design-build'', and

``Two-phase design-build selection procedures'' to read as follows:

36.102 Definitions.

* * * * *

Design, as used in this part, means defining the construction

requirement (including the functional relationships and technical

systems to be used, such as architectural, environmental, structural,

electrical, mechanical, and fire protection), producing the technical

specifications and drawings, and preparing the construction cost

estimate.

Design-bid-build, as used in this part, means the traditional

delivery method where design and construction are sequential and

contracted for separately with two contracts and two contractors.

Design-build, as used in this part, means combining design and

construction in a single contract with one contractor.

* * * * *

Two-phase design-build selection procedures, as used in this part,

is a selection method in which a limited number of offerors (normally

five or fewer) is selected during Phase One to submit detailed

proposals for Phase Two (see subpart 36.3).

7. Section 36.104 is added to read as follows:

36.104 Policy.

Unless the traditional acquisition approach of design-bid-build

established under the Brooks Architect-Engineers Act (41 U.S.C. 541, et

seq.) or another acquisition procedure authorized by law is used, the

contracting officer shall use the two-phase selection procedures

authorized by 10 U.S.C. 2305a or 41 U.S.C. 253m when entering into a

contract for the design and construction of a public building,

facility, or work, if the contracting officer makes a determination

that the procedures are appropriate for use (see subpart 36.3). Other

acquisition procedures authorized by law include the procedures

established in this part and other parts of this chapter and, for DoD,

the design-build process described in 10 U.S.C. 2862.

Subpart 36.3 [Redesignated as 36.213 and Amended]

36.301-36.304 [Redesignated as 36.213-1--36.213-4]

8. Subpart 36.3 is redesignated as section 36.213 and the heading

is revised to read ``Special procedures for sealed bidding in

construction contracting.''; and sections 36.301 through 36.304 are

redesignated as 36.213-1 through 36.213-4, respectively.

Subpart 36.4 [Removed]

36.401 [Removed]

36.402 [Redesignated as 36.214]

36.403 [Redesignated as 36.215]

9. Subpart heading 36.4 and section 36.401 are removed; and

sections 36.402 and 36.403 are redesignated as 36.214 and 36.215,

respectively, and the section headings revised to read as follows:

36.214 Special procedures for price negotiation in construction

contracting.

36.215 Special procedure for cost-reimbursement contracts for

construction.

10. Subpart 36.3, consisting of sections 36.300 through 36.303-2,

is added to read as follows:

Subpart 36.3--Two-Phase Design-Build Selection Procedures

Sec.

36.300 Scope of subpart.

36.301 Use of two-phase design-build selection procedures.

36.302 Scope of work.

36.303 Procedures.

36.303-1 Phase One.

36.303-2 Phase Two.

Subpart 36.3--Two-Phase Design-Build Selection Procedures

36.300 Scope of subpart.

This subpart prescribes policies and procedures for the use of the

two-phase design-build selection procedures authorized by 10 U.S.C.

2305a and 41 U.S.C. 253m.

36.301 Use of two-phase design-build selection procedures.

(a) During formal or informal acquisition planning (see part 7), if

considering the use of two-phase design-build selection procedures, the

contracting officer shall conduct the evaluation in paragraph (b) of

this section.

(b) The two-phase design-build selection procedures shall be used

when the contracting officer determines that this method is

appropriate, based on the following:

(1) Three or more offers are anticipated.

(2) Design work must be performed by offerors before developing

price or cost proposals, and offerors will incur a substantial amount

of expense in preparing offers.

(3) The following criteria have been considered:

(i) The extent to which the project requirements have been

adequately defined.

(ii) The time constraints for delivery of the project.

(iii) The capability and experience of potential contractors.

(iv) The suitability of the project for use of the two-phase

selection method.

(v) The capability of the agency to manage the two-phase selection

process.

(vi) Other criteria established by the head of the contracting

activity.

36.302 Scope of work.

The agency shall develop, either in-house or by contract, a scope

of work that defines the project and states the Government's

requirements. The scope of work may include criteria and preliminary

design, budget parameters, and schedule or delivery requirements. If

the agency contracts for development of the scope of work, the

procedures in subpart 36.6 shall be used.

36.303 Procedures.

One solicitation may be issued covering both phases, or two

solicitations may be issued in sequence. Proposals will be evaluated in

Phase One to determine which offerors will submit proposals for Phase

Two. One contract will be awarded using competitive negotiation.

36.303-1 Phase One.

(a) Phase One of the solicitation(s) shall includ--

(1) The scope of work;

(2) The phase-one evaluation factors, including--

(i) Technical approach (but not detailed design or technical

information);

(ii) Technical qualifications, such as--

(A) Specialized experience and technical competence;

(B) Capability to perform;

(C) Past performance of the offeror's team (including the

architect-engineer and construction members); and

(iii) Other appropriate factors (excluding cost or price related

factors, which are not permitted in Phase One);

(3) Phase-two evaluation factors (see 36.303-2); and

(4) A statement of the maximum number of offerors that will be

selected to submit phase-two proposals. The maximum number specified

shall not exceed five unless the contracting officer determines, for

that particular solicitation, that a number greater than five is in the

Government's interest and is consistent with the purposes and

objectives of two-phase design-build contracting).

(b) After evaluating phase-one proposals, the contracting officer

shall select the most highly qualified offerors (not to exceed the

maximum number specified in the solicitation in accordance with 36.303-

1(a)(4)) and request that only those offerors submit phase-two

proposals.

36.303-2 Phase Two.

(a) Phase Two of the solicitation(s) shall be prepared in

accordance with part 15, and include phase-two evaluation factors,

developed in accordance with 15.605. Examples of potential phase-two

technical evaluation factors include design concepts, management

approach, key personnel, and proposed technical solutions.

(b) Phase Two of the solicitation(s) shall require submission of

technical and price proposals, which shall be evaluated separately, in

accordance with part 15.

11. Subpart 36.4 is added and reserved to read as follows:

Subpart 36.4--Commercial Practices [Reserved]

[FR Doc. 96-33217 Filed 12-31-96; 8:45 am]

BILLING CODE 6820--EP

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Federal Acquisition Regulation; Two-Phase Design Build Selection Procedures · 62 FR 271 | Frix