(a) 40 U.S.C. chapter 31, subchapter III, Bonds (formerly known as the Miller Act), requires performance and payment bonds for any construction contract exceeding $150,000, except that this requirement may be waived— (1) by the contracting officer for as much of the work as is to be performed in a foreign country upon finding that it is impracticable for the contractor to furnish such bond, or (2) As otherwise authorized by the Bonds statute or other law. (b)(1) Pursuant to 40 U.S.C. 3132, for construction contracts greater than $35,000, but not greater than $150,000, the contracting officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives: (i) A payment bond. (ii) An irrevocable letter of credit (ILC). (iii) A tripartite escrow agreement. The prime contractor establishes an escrow account in a federally insured financial institution and enters into a tripartite escrow agreement with the financial institution, as escrow agent, and all of the suppliers of labor and material. The escrow agreement shall establish the terms of payment under the contract and of resolution of disputes among the parties. The Government makes payments to the contractor's escrow account, and the escrow agent distributes the payments in accordance with the agreement, or triggers the disputes resolution procedures if required. (iv) Certificates of deposit. The contractor deposits certificates of deposit from a federally insured financial institution with the contracting officer, in an acceptable form, executable by the contracting officer. (v) A deposit of the types of security listed in 28.204-1 and 28.204-2. (2) The contractor shall submit to the Government one of the payment protections selected by the contracting officer

Certificates of deposit. The contractor deposits certificates of deposit from a federally insured financial institution with the contracting officer, in an acceptable form, executable by the contracting officer. (v) A deposit of the types of security listed in 28.204-1 and 28.204-2. (2) The contractor shall submit to the Government one of the payment protections selected by the contracting officer. (c) The contractor shall furnish all bonds or alternative payment protection, including any necessary reinsurance agreements, before receiving a notice to proceed with the work or being allowed to start work. [48 FR 42286, Sept. 19, 1983, as amended at 61 FR 31652, June 20, 1996; 70 FR 57454, Sept. 30, 2005; 71 FR 57368, Sept. 28, 2006; 75 FR 53134, Aug. 30, 2010; 79 FR 24210, Apr. 29, 2014; 80 FR 38298, July 2, 2015]

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.