Adjustment of royalties.
FederalRegulations
Ask Donna
How this section applies to your facts.
Title 48 CFR: Federal Acquisition Regulations System › Chapter 1 › Part 27 › Subpart 27.2 › § 27.202-3: Adjustment of royalties.
Text
(a) If at any time the contracting officer believes that any royalties paid, or to be paid, under a contract or subcontract are inconsistent with Government rights, excessive, or otherwise improper, the contracting officer shall promptly report the facts to the office having cognizance of patent matters for the contracting activity concerned. (b) In coordination with the cognizant office, the contracting officer shall promptly act to protect the Government against payment of royalties— (1) With respect to which the Government has a royalty-free license; (2) At a rate in excess of the rate at which the Government is licensed; or (3) When the royalties in whole or in part otherwise constitute an improper charge. (c) In appropriate cases, the contracting officer in coordination with the cognizant office shall demand a refund pursuant to any refund of royalties clause in the contract (see 27.202-4) or negotiate for a reduction of royalties. (d) For guidance in evaluating information furnished pursuant to 27.202-1, see 31.205-37. See also 31.109 regarding advance understandings on particular cost items, including royalties.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.