(1)

Award-fee pool.

The award-fee pool is the total available award fee for each evaluation period for the life of the contract. The contracting officer shall perform an analysis of appropriate fee distribution to ensure at least 40 percent of the award fee is available for the final evaluation so that the award fee is appropriately distributed over all evaluation periods to incentivize the contractor throughout performance of the contract. The percentage of award fee available for the final evaluation may be set below 40 percent if the contracting officer determines that a lower percentage is appropriate, and this determination is approved by the head of the contracting activity (HCA). The HCA may not delegate this approval authority.

(2)

Award-fee evaluation and payments.

Award-fee payments other than payments resulting from the evaluation at the end of an award-fee period are prohibited. (This prohibition does not apply to base-fee payments.) The fee-determining official's rating for award-fee evaluations will be provided to the contractor within 45 calendar days of the end of the period being evaluated. The final award-fee payment will be consistent with the fee-determining official's final evaluation of the contractor's overall performance against the cost, schedule, and performance outcomes specified in the award-fee plan.

(3)

Limitations.

(i) The cost-plus-award-fee contract shall not be used—

(A) To avoid—

(

1

) Establishing cost-plus-fixed-fee contracts when the criteria for cost-plus-fixed-fee contracts apply; or

(

2

) Developing objective targets so a cost-plus-incentive-fee contract can be used; or

(B) For either engineering development or operational system development acquisitions that have specifications suitable for simultaneous research and development and production, except a cost-plus-award-fee contract may be used for individual engineering development or operational system development acquisitions ancillary to the development of a major weapon system or equipment, where—

(

1

) It is more adva

ther engineering development or operational system development acquisitions that have specifications suitable for simultaneous research and development and production, except a cost-plus-award-fee contract may be used for individual engineering development or operational system development acquisitions ancillary to the development of a major weapon system or equipment, where—

(

1

) It is more advantageous; and

(

2

) The purpose of the acquisition is clearly to determine or solve specific problems associated with the major weapon system or equipment.

(ii) Do not apply the weighted guidelines method to cost-plus-award-fee contracts for either the base (fixed) fee or the award fee.

(iii) The base fee shall not exceed three percent of the estimated cost of the contract exclusive of the fee.

(4) See PGI 216.405-2 for guidance on the use of cost-plus-award-fee contracts.

[76 FR 8305, Feb. 14, 2011]