Documents
Briefs, oral arguments, agency decisions and the Federal Register.
399 results
0.15s
In the Matter of ABBEYS SPECIALIZED HAULERS
Agency decision · Agency decision
The period for submitting bids closed on May 17, 2011. DCMA awarded the shipment to Abbeys Specialized Haulers (ASH), with $16,589 to be paid to the carrier. … CBCA 2763-RATE 3 GSA’s Federal Acquisition Service submitted comments on this matter and documents in support of its position.
Civilian Board of Contract AppealsIn the Matter of BOARD OF EDUCATION FOR THE
Agency decision · Agency decision
BERC cleaned the facilities and undertook remediation efforts to preclude mold growth while it sought public assistance funding from FEMA. … But the duration of the required time period is unclear.
Civilian Board of Contract AppealsIn the Matter of LIVINGSTON PARISH
Agency decision · Agency decision
Stafford Disaster Relief and Emergency Assistance Act, 42 U.S.C. § 5121 et seq. (2006). … The Parish has taken this comment to be a commitment that the Corps would not require permitting for any actions the contractor might take in clearing waterways of debris.
Civilian Board of Contract AppealsIn the Matter of DONALD E. CONEY
Agency decision · Agency decision
Coney retired from the United States Air Force in 1994 while stationed in Europe, where he remained. When he transferred to the United States, Mr. … shipment and/or delivery to the new permanent private sector housing due to extended transit time incident to ocean transportation, strikes, customs clearance, hazardous weather, fires, floods, or other Acts
Civilian Board of Contract AppealsAPPELLANT’S MOTION TO DISMISS FOR LACK OF JURISDICTION OR, IN THE
Agency decision · Agency decision
In these consolidated appeals, the CO issued the two COFDs within that period. … Having rendered a final decision on [appellant]’s claim, the parties are before the Board on a “clean slate,” Wilner [v. United States, 24 F.3d 1397, 1402 (Fed.
Civilian Board of Contract AppealsAgency decision · Agency decision
A er no ce and comment, the new rules took effect September 17, 2018. 83 Fed. Reg. 41,009 (Aug. 17, 2018). … Air Force, with the Judge between li ga on and ADR. The program also brings in speakers Advocate General Corps.
Civilian Board of Contract AppealsIn the Matter of TOWN OF PARADISE, CALIFORNIA
Agency decision · Agency decision
Stafford Disaster Relief and Emergency Assistance Act (Stafford Act), 42 U.S.C. §§ 5121-5207 (2018), for the affected areas, authorizing individual assistance, public assistance, and state-wide hazard … Thus, the work continued beyond the period of performance specified in PW 219.
Civilian Board of Contract AppealsIn the Matter of LOGISTICS INTERNATIONAL, INC.
Agency decision · Agency decision
Sheila McDonald, Staff Judge Advocate, Surface Deployment and Distribution Command, Department of the Air Force, Scott Air Force Base, IL, appearing for Department of Defense. KULLBERG, Board Judge. … Statutory authority for GSA’s offset procedure based on this right is granted in the Federal Claims Collection Act. The rights under the act are not extinguished by 31 U.S.C. 3726(d)[.]
Civilian Board of Contract AppealsDISMISSED FOR LACK OF JURISDICTION: June 7, 2018
Agency decision · Agency decision
During that period, there were continuous issues between the VA and GVEDC over the odor of formaldehyde and the air quality within the clinic. … To address issues with the air quality, the heating, ventilation, and air conditioning (HVAC) system within the clinic was repaired.
Civilian Board of Contract AppealsIn the Matter of NICHOLAS J. THACKER
Agency decision · Agency decision
Thacker interest on $1300, at the rate prescribed by the Secretary of the Treasury for the Prompt Payment Act, 2%, for the period from September 25, 2014, until the date of payment of the $1300. … Reg. 37,391 (July 1, 2014) (setting the rate for this period).
Civilian Board of Contract AppealsAgency decision · Agency decision
issue under consideration in this matter is whether GSA owes Avalon additional compensation for constantly maintaining the DCR temperature between sixty-eight and eighty degrees Fahrenheit for the lease period … The HVAC system shall be designed to supply, on the average, 6 complete air changes per hour with a minimum of 20 percent fresh air.
Civilian Board of Contract AppealsAgency decision · Agency decision
Nor did the Court comment on the fact that the record contained no evidence that the four-year-old internal components and parts would not need to be replaced or refurbished. … Clean exterior surfaces, remove rust, and paint. d. Clean mufflers, remove rust, and paint (high temp black). This work will be conducted at OK Generators. . . .
Civilian Board of Contract AppealsIn the Matter of GAMTESSA ADDISU
Agency decision · Agency decision
TQSE After the Authorized TQSE Period Expired Mr. Addisu seeks to recover TQSE from June 1 through July 28, 2014, a period of fifty-seven days. … E.g., Department of the Air Force, 57 Comp. Gen. 664 (1978).
Civilian Board of Contract AppealsAgency decision · Agency decision
Service shall include the assembly, delivery, pick up, cleaning, repairing and storage of Government-owned HME. … The period of performance for these contracts was August 2015 to January 2017.
Civilian Board of Contract AppealsDISMISSED FOR LACK OF JURISDICTION: July 1, 2008
Agency decision · Agency decision
Battley, the trustee in bankruptcy for the estate of Martech, submitted a certified claim under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601- 613, for the recovery of the outstanding contract … Battley contends that he had recently learned that SSA had retained the contract balance, and that it had not been used to set off any debts due to the Air Force. Mr.
Civilian Board of Contract AppealsIn the Matter of MIDDLESEX COUNTY UTILITIES AUTHORITY
Agency decision · Agency decision
Stafford Disaster Relief and Emergency Assistance Act (Stafford Act), 42 U.S.C. §§ 5121–5207 (2018), the applicant, Middlesex County Utilities Authority, seeks public assistance (PA) funding in the amount … The second week of the pay period, the four teams switched.
Civilian Board of Contract AppealsMOTION TO DISMISS DENIED: December 21, 2015
Agency decision · Agency decision
Army & Air Force Exchange Service, 846 F.2d 746, 748 (Fed. Cir. 1988)). … The Assignment of Contracts Act, 41 U.S.C. § 6305 (2012), and the Assignment of Claims Act, 31 U.S.C. § 3727 (2012), are intended to prevent fraud, particularly the buying up of claims against the Government
Civilian Board of Contract AppealsDISMISSED FOR LACK OF JURISDICTION OR, ALTERNATIVELY, DENIED:
Agency decision · Agency decision
El Malik, 20-1 BCA at 182,275; see Erickson Air Crane Co. of Washington, Inc. v. United States, 731 F.2d 810, 813–14 (Fed. … acted as purchasing agents for private end users.
Civilian Board of Contract AppealsAPPELLANT’S MOTION FOR SUMMARY RELIEF IN CBCA 2775
Agency decision · Agency decision
Army & Air Force Exchange Service, 846 F.2d 746, 748 (Fed. Cir. 1998); Rocovich v. United States, 933 F.2d 991, 993 (Fed. Cir. 1991). II. … Contract Cleaning Maintenance, Inc. v. United States, 811 F.2d 586, 592 (Fed. Cir. 1987).
Civilian Board of Contract AppealsIn the Matter of ROMAN CATHOLIC CHURCH
Agency decision · Agency decision
Stafford Disaster Relief and Emergency Assistance Act (Stafford Act), 42 U.S.C. §§ 5121-5296 (2006)], an applicant is eligible for reimbursement of the costs of replacing, rather than merely repairing, … In light of acknowledged roof damage to the convent caused by Katrina and the humidity effect of hurricane waters sitting inside the building for CBCA 6469-FEMA 4 a long period of time after Katrina
Civilian Board of Contract Appeals
Ask Donna what matters in the record.
She can read the source against your case and show you exactly where the answer came from.