DENIED: July 30, 2024
Agency decision
Ask Donna
What actually matters in this document.
Text
DENIED: July 30, 2024
CBCA 7618
UNITED FACILITY SERVICES CORPORATION,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
William Weisberg of Law Offices of William Weisberg PLLC, McLean, VA, counsel
for Appellant.
Justin S. Hawkins, Office of General Counsel, General Services Administration,
Washington, DC, counsel for Respondent.
Before Board Judges LESTER, RUSSELL, and GOODMAN.
LESTER, Board Judge.
Respondent, the General Services Administration (GSA), is seeking to recover money
from appellant, United Facility Services Corporation (UFS), for damages caused by a burst
frozen water pipe in a federal courthouse building in Memphis, Tennessee, for which UFS,
by contract, was providing operations and maintenance (O&M) services. UFS filed this
appeal to challenge the Government’s claim. This decision is being issued following the
parties’ presentation of witness testimony at a hearing on April 17, 2024.
Previously, by decision dated February 27, 2024, the Board granted summary
judgment to GSA on its argument that UFS had breached its contractual obligation to
respond within no more than thirty minutes to an emergency call about the burst pipe,
CBCA 7618
2
entitling GSA to damages. United Facility Services Corp. v. General Services
Administration, CBCA 7618, 24-1 BCA ¶ 38,535, at 187,319. GSA’s recoverable damages
for UFS’s four-hour delay, to be established at the hearing, would be the difference between
the damage that would necessarily have resulted within that thirty-minute response-time
grace period and the full damage that actually occurred.
There was a second potential breach of contract, however, that was not addressed in
the February 27 summary judgment decision. Under its contract, UFS was required to make
reasonable attempts to protect the building from damage caused by reasonably foreseeable
freezing temperatures. GSA’s summary judgment motion did not address that issue, and it
remained open for development at the hearing.
During the hearing, UFS’s president volunteered that he had long known that piping
in the area of the burst pipe was too close to an uninsulated exterior wall of the building and
that, as he had previously told GSA on several occasions, the pipe was going to freeze and
burst when it got too cold outside. After learning of the impending freezing temperatures in
February 2021 (which was predicted days in advance of the weather event), UFS did nothing
to attempt to limit damage or protect the uninsulated pipes from freezing, instead believing
that GSA was at fault for not providing better insulation. In fact, UFS let all of its building
engineers stay home during the weather event and then let its project manager leave the
building for more than four hours, even though, as UFS’s president acknowledged, UFS
knew that pipes were likely to freeze and burst. Although UFS is not strictly liable under its
contract for the fact that a pipe burst, it is liable under the terms of its contract for damages
from a burst that, as here, it could reasonably have foreseen and made no effort to prevent.
Further, having accepted this contract knowing of the conditions in the building, it cannot
validly complain that GSA should have given it a better building to maintain.1
1
UFS suggests in its post-hearing briefing that the Board, in its summary
judgment decision, held that UFS was not liable for failing to attempt to protect the building
from freezing temperatures. The Board made no such ruling. GSA’s motion for summary
judgment focused solely on UFS’s failure to have an employee on-site when the pipe burst.
During briefing, neither party sought a ruling on the adequacy of UFS’s preparations for
freezing temperatures or knowledge of the likelihood of a pipe burst. Further, in a
scheduling order issued a few hours after its summary judgment decision, the Board notified
the parties that the April 17 hearing would “address all unresolved issues in this appeal
(including quantum issues).” Order (Feb. 27, 2024) at 2. And, at the beginning of the
April 17 hearing, the Board indicated that its “summary judgment decision did not find that
[UFS] was strictly liable for the mere fact that a pipe burst, but [that] if GSA wants to pursue
such an argument, it can do so here,” since “[t]he summary judgment motion just didn’t
address that.” Hearing Transcript at 8. It was clear that UFS’s liability for breach of its
CBCA 7618
3
Having breached its obligation to attempt to protect the building from reasonably
foreseeable (and, in this case, anticipated) damage, UFS is responsible for the damage caused
by the burst pipe. Because GSA has established through virtually uncontroverted evidence
that it incurred $526,478.46 to remedy the damage caused by the flooding, it is entitled to
recover that amount from UFS.
Findings of Fact
I.
UFS’s Contract
On September 30, 2016, GSA and UFS executed a fixed-price contract, no. GS-04-P16-EW-A-7021 (contract 7021), under which UFS would provide O&M services at the
Clifford David-Odell Horton Federal Courthouse (Odell courthouse) in Memphis, Tennessee,
for a twelve-month period beginning November 1, 2016, preceded by a thirty-day phase-in
period running from October 1 through 31, 2016. Appeal File, Exhibit 2A at 63, 65.2 The
contract contained four one-year options, all of which GSA exercised, that extended UFS’s
performance under the contract to October 31, 2021. Exhibit 1 at 16-17, 31-32, 42-43,
54-55.
As detailed in the Board’s February 27 decision, see United Facility Services, 24-1
BCA at 187,312-14, UFS’s contract required it to “provide staff to ensure services are
continued without disruption to the tenant” and to “ensure employees maintain
communications access with the [contracting officer] or his/her designee to allow contact by
the Government at all times during normal working hours and to effectively communicate
with Government personnel.” Exhibit 2A at 102 (clause C.8.1). It also required UFS to
provide staff “as necessary to meet all requirements of the contract” and “to ensure services
are continued without disruption to the tenant,” id. at 103 (clause C.8.1); “maintain
uninterrupted utilities services . . . so as to preserve the asset value of the facility and its
systems and to otherwise minimize operating costs to the Government without compromising
other Contract objectives or requirements,” id. at 111 (clause C.21.1); and have “a system
for onsite work force personnel to report potentially hazardous conditions in the building to
the [contracting officer] or designee” and to “provide reasonable assistance to security or
emergency response personnel as needed.” Id. at 117-18 (clause C.29). It required UFS to
“respond to emergency service request[s],” including those dealing with “broken water pipes,
. . . immediately (within the shortest possible time consistent with the mechanic’s location)
during normal working hours and within 30 minutes.” Id. at 114 (clause C.23.2). And it
contractual obligation to protect piping in the building from freezing temperatures was an
open issue for the hearing.
2
Unless otherwise noted, all exhibits are found in the appeal file.
CBCA 7618
4
provided that UFS “shall provide all labor, materials and equipment necessary for the
protection of Government personnel, equipment, furnishings, buildings, and facility
accessories (such as parking lots, fences, etc.) from damage caused by Contractor’s
negligence.” Id. at 118 (clause C.30).
Another contract provision, clause C.21.8, required UFS to “be responsible for any
necessary operation and prevention of damage to equipment during on and off duty hours . . .
due to inclement weather, high wind events, or freezing temperatures.” Exhibit 2A at 113.3
Similarly, clause C.29 required UFS to “make reasonable efforts to prevent hazardous
conditions and property damage” at the Odell courthouse, albeit without expressly
mentioning freezing temperatures. Id. at 117.
The contract also contained clause C.40.9, titled “Force Majeure (Uncontrollable
Events),” which read as follows:
The Contractor shall not be responsible for deficiencies or breakdowns caused
by vandalism, misuse by people other than Contractor employees, abuse by
people other than Contractor employees, or acts of God including natural
disasters unless the Contractor could have reasonably foreseen such events
and prepared accordingly to prevent such deficiencies or breakdowns.
Exhibit 2A at 131 (emphasis added).
II.
UFS’s Knowledge of Building Conditions
When awarded contract 7021, UFS had already been providing O&M services at the
Odell courthouse for the prior five years under a predecessor contract. Hearing Transcript
at 153-54. As UFS’s president, Steven R. Brown, testified at the hearing, when GSA
awarded contract 7021 in 2016, UFS was “very aware that this [was] an older building and
3
Although the contract did not contain a specific definition or list of the
“equipment” that UFS was to protect from damage, the piping at issue here is sufficiently
tied to the sprinkler system equipment to be covered under clause C.21.8. See Exhibit 2A
at 82 (in clause C.1.1, describing UFS’s “equipment and systems” responsibilities as
including, among other things, (1) plumbing and domestic water equipment and (2) fire
protection and life safety systems and equipment, including sprinkler systems); see also
Schaeffer Piano Manufacturing Co. v. National Fire Extinguisher Co., 148 F. 159, 164-68
(7th Cir. 1906) (describing sprinkler system as “equipment”); Toll Brothers Inc. v. Century
Surety Co., No. 07-1296, 2013 WL 3009721, at *1 (E.D. Pa. June 17, 2013) (same).
CBCA 7618
5
that it was very poorly maintained for many, many years.” Id. at 154. Mr. Brown described
the building’s known condition as follows:
From the mechanical equipment all the way down to exit overhead garage
doors, which we were in charge of maintaining[, t]he systems within the
building were very tired. And, the government was not renovating the
building. There w[ere] no upgrades being done. It was held together with duct
tape and a hammer half the time. And I’m being nice about it. There w[ere]
coils in the building that were leaking into courtrooms. And equipment just
being broken and then just left instead of it being replaced, it would just be
taken out of service.
Id. at 155.
In fact, Mr. Brown testified specifically about UFS’s knowledge of uninsulated piping
in parts of the building that were exposed to outside air and the likelihood that such piping
would freeze and potentially burst if outdoor temperatures were sufficiently below freezing:
[F]rom the minute we took this building the 10 years prior to our last day of
the contract, we had complained about non-insulated pipes in the building that
w[ere] exposed to outside air. There [are] plenums, which allow fresh air to
come in and out of the building. And you’re talking about 7, 12 degrees
during the winter in a snow storm. It is no shock that they finally had a real
pipe burst, but it’s not the first time. There’s documented, many documented
instances where they’ve had coils freeze over and break.
Hearing Transcript at 166-67.
By February 2021, the date of the incident at issue, UFS had already had nine years
of familiarity with the state of the building. Hearing Transcript at 153-54.
III.
The Incident
As National Weather Service records indicate, temperatures in Memphis fell below
freezing on the evening of February 10, 2021, and remained there for the next nine days,
falling to lows of 14° on February 14 and 9° on February 15 and a record low of 1° on
February 16, 2021. https://www.weather.gov/wrh/climate?wfo=meg (last visited July 28,
2024). In addition, on February 14 and 15, 2021, a total of 5.3 inches of snow fell in
Memphis. Id. This weather was far from typical for the area.
CBCA 7618
6
On February 16, 2021, at approximately 1:00 p.m. Central Time (CT), a frozen pipe
that was related to the building’s sprinkler system burst inside a locked room at the Odell
courthouse, causing flooding. Exhibit 6 at 415; Respondent’s Motion for Summary
Judgment, Statement of Undisputed Material Facts (SUMF) ¶ 3; Appellant’s Statement of
Material Facts (SMF) ¶ 1.
Before the pipe burst, the UFS project manager, who had checked in at the building
that morning, had departed for what turned out to be a lunch of more than four hours, and
there were no other UFS employees in the building. Exhibit 6 at 415, 421; Respondent’s
SUMF ¶¶ 4-5, 7; Appellant’s SMF ¶ 1; Complaint ¶ 6. The two UFS mechanics who were
normally at the building during normal business hours were not at work that day, having been
allowed to stay home because of inclement weather, and UFS’s administrator had called out
sick that day. Exhibit 6 at 415.
The GSA building manager was notified at approximately 1:00 p.m. CT by a
twenty-four-hour automated monitoring system that a brown liquid was coming from the
locked room and that the fire department needed access to it. Exhibit 6 at 421. At 1:04 p.m.
CT, the GSA building manager called the UFS project manager about the flooding, but the
UFS project manager did not respond. Exhibit 6 at 415, 421; Respondent’s SUMF ¶ 6. The
GSA building manager then contacted the Federal Protective Service (FPS) for assistance.
Exhibit 6 at 421. The UFS project manager did not return to the building until almost four
hours later (arriving by approximately 4:41 p.m. CT) because of what he said was
“something personal.” Id. at 422; Respondent’s SUMF ¶ 7.4 By the time that the UFS
project manager arrived and cut off the flow of water, the basement, first floor, and
mezzanine levels of the building had suffered substantial flooding.
IV.
Work to Repair Damage Caused by the Pipe Burst
On March 3, 2021, the GSA contracting officer executed a $75,000 task order to UFS,
separate and apart from contract 7021, for water extraction services at the Odell courthouse,
services that UFS had begun providing through a subcontractor on February 16, 2021.
4
At the hearing, UFS’s president testified that, as he understood it, the UFS
project manager’s delay in returning to the building was caused by weather and that he began
trying to return as soon as he received GSA’s emergency call. Hearing Transcript at 180-83.
That testimony, which is hearsay, is inconsistent with all other evidence in the record. While
UFS had listed its project manager as a fact witness, it elected not to call him. Therefore,
there was no explanation of what he originally told GSA was a “personal” reason for his
delayed return. In such circumstances, we reject the UFS president’s unsupported
explanation for the project manager’s delayed return.
CBCA 7618
7
Exhibit 7 at 424-46; Hearing Transcript at 157. GSA paid UFS in full for the extraction work
on March 26, 2021. Exhibits 9, 10; Hearing Transcript at 51-52, 157.
On or about June 7, 2021, after seeking competitive offers from six contractors with
existing indefinite-delivery indefinite-quantity contracts, GSA awarded a task order to
Katmai Support Services, L.L.C. (Katmai), in the amount of $451,478.46 for “build back
repairs required due to water intrusion” from the burst pipe at the Odell courthouse.
Exhibit 11 at 448-49; see Hearing Transcript at 42-44. GSA paid Katmai the contract price
for its work on March 11, 2022. Exhibits 12, 13.
The costs of the UFS water extraction work and the Katmai “build back” work, which
total $526,478.46,5 were necessarily incurred to repair damage from the burst pipe, are
reasonable, and are adequately supported in the record.6 See Hearing Transcript at 38-48.
Although GSA suffered other damage from the burst pipe, including destruction of furniture,
it is not seeking compensation for that damage.
V.
GSA’s Demands for Reimbursement
The contracting officer sent a demand letter to UFS on June 2, 2021, notifying UFS
of its “liability for major damage caused in the [Odell courthouse] due to [the] pipe burst on
February 16, 2021.” Exhibit 3 at 402. She indicated that, “[a]s a result of the extensive
damage done to the building, several floors of office/tenant spaces have to be renovated to
bring the spaces back to its [sic] original state for occupancy. The amount of water dispersed
was extensive and caused major flooding to the first floor, the Mezzanine, the basement, and
office tenant spaces and equipment.” Id. at 403. She indicated that, at that time (which was
a few days before the June 7, 2021, task order award to Katmai), GSA had estimated its total
damage as $451,478.46. Id. In support of her payment demand, the contracting officer cited
several provisions of the contract that she believed UFS had violated, including clauses
C.8.1, C.21.1, C.21.8, C.29, and C.30. Id. at 403-04. She asserted that UFS’s “failure to
adequately perform the duties outlined above resulted in the damage to the building.” Id. at
404.
5
In its post-hearing brief, GSA repeatedly tells us that it is entitled to
reimbursement of $529,478.46, which is $3000 more than the total of the two contracts that
it cites in support of its claimed damages. It appears that GSA’s identified total is a
mathematical error. Because the two contracts upon which GSA relies to support its claimed
damages total $526,478.46, that is the total damage amount that GSA has established.
6
To the extent that UFS’s witness questioned whether these costs include an
upgrade to the facility, see Hearing Transcript at 168-69, the evidence is too speculative to
merit a reduction in the established damages.
CBCA 7618
8
By letter dated June 9, 2021, UFS responded to GSA’s demand letter and disclaimed
any responsibility for the damages to the building, which it asserted were caused by an act
of God that was excusable under the contract’s Force Majeure clause (clause C.40.9):
This clause was written for just this situation. An emergency inclement
weather event was in progress. Snowfall and temperatures both reached
historical levels (one high, one low). Travel was treacherous. The Mayor had
declared a State of Emergency. This was a classic force majeure event. As
such, the contractor is not liable for any part of the $451,478.46 in damages
referenced in your letter.
Exhibit 4 at 406-07.
The contracting officer responded by letter dated October 14, 2021, asserting that the
Force Majeure clause “only applies to damages caused by Acts of God ‘unless the Contractor
could have reasonably foreseen such events and prepared accordingly to prevent such
deficiencies or breakdowns.’” Exhibit 6 at 419. She represented that, “although the pipe
freezing and bursting may be considered an Act of God, the Contractor could reasonably
have foreseen the subsequent damage and prepared accordingly to prevent the deficiencies
and breakdowns that followed.” Id. She identified GSA’s total damages at that point as
$529,478.46. Id. at 422.
On December 7, 2022, the GSA contracting officer issued a final decision, which
incorporated the contracting officer’s demand letter from June 2, 2021, and demanded the
payment of $505,492.92 (an unexplained decrease in the dollar amount identified in the
October 14, 2021, letter, as well as a lower figure than that being sought here) for “damages
caused at the Odell [courthouse] as a result of the pipe burst and flooding due to the
contractor’s failure to adequately perform the duties outlined in the terms and conditions of
the contract.” Exhibit 6 at 413. The contracting officer included in the decision a notice of
UFS’s appeal rights under the CDA. Id. at 414.
VI.
Proceedings Before the Board
UFS filed its notice of appeal with the Board on December 20, 2022, challenging the
contracting officer’s assertion of the government claim. On November 9, 2023, after the
parties had completed discovery, GSA filed its motion for partial summary judgment, which
the Board granted on February 27, 2024. In its decision, the Board found that GSA had
established UFS’s breach of its obligation to respond to emergency calls within thirty
minutes. United Facility Services, 24-1 BCA at 187,319. The Board then scheduled a
hearing on all issues remaining in the appeal, including but not limited to quantum, to
commence April 17, 2024. By order dated April 11, 2024, the Board directed that, because
CBCA 7618
9
the claim at issue is a government claim (for which the Government bore the burden of
proof), GSA should present its case-in-chief first at the hearing, followed by UFS.
At the commencement of the April 17 hearing, GSA indicated that, in addition to
establishing the amount of its damages, it intended to pursue at the hearing its argument that,
in addition to breaching an obligation to respond to emergency calls within thirty minutes,
UFS had also breached its separate contractual obligation to exercise reasonable care in
preventing damage to the building in response to freezing temperatures. Hearing Transcript
at 21-22. GSA then called two witnesses: the contracting officer for the Katmai “build
back” reconstruction contract and the contracting officer’s representative for contract 7021,
who prepared an independent government estimate for the cost of remedying the water
damage to the building. They established the costs that GSA incurred to remedy the water
damage to the courthouse, but neither witness was at the courthouse during the flooding, and
neither was able to segregate the damage that occurred within the first thirty minutes after
the pipe burst from the total damage that GSA suffered. Similarly, neither could address
questions from counsel for UFS about whether flooding in the first thirty minutes after the
pipe burst was sufficient to cause tiles in the basement, which were secured to the floor with
an asbestos glue, to delaminate, creating friability issues that may have significantly affected
GSA’s overall restoration costs. GSA closed the presentation of its case-in-chief without
addressing those proximate cause issues.
UFS then presented its witness, Mr. Brown. Like GSA’s witnesses, Mr. Brown was
not at the Odell courthouse when the flooding occurred. He testified, though, that he was
very familiar with the building from years of having dealt with it under two contracts. He
testified that the pipe that burst was in a controlled internal space but, as he long had known,
“was exposed to outside. It was a bearing wall pipe. It was attached to a bearing wall, and
then it was . . . outside air right near it. So, that’s why the pipe froze. And the pipe was
broken in multiple spots, not in one. So it wasn’t a one-break. This was a fatigued pipe.”
Hearing Transcript at 173. He also testified that, as UFS had long known, the pipe was not
wrapped or insulated. Id. at 169. He represented that “[a]nything that is exposed to outside
air in a building with an environment like this one, or basically the state, their winters, their
springs, has to be insulated. There was conversation about insulating the pipes. Nothing was
ever done.” Id. Nevertheless, he also testified that “[w]e are a maintenance contractor. We
maintain what is given to us. So, our job is to keep it running at all extent. Whatever we
have to do to keep it running.” Id. at 170.
At the parties’ request, the Board allowed the parties to submit sequential post-hearing
briefing. GSA filed its post-hearing brief on June 21, 2024; UFS filed its response brief on
July 1, 2024; and GSA filed its reply brief on July 11, 2024.
CBCA 7618
10
Discussion
I.
UFS’s Breach, and GSA’s Damages
“The party alleging a breach of contract”—here, the Government—“bears the burden
of proving the breach.” Technical Assistance International, Inc. v. United States, 150 F.3d
1369, 1373 (Fed. Cir. 1998). Further, “before the contractor may be held liable for damage
to property . . . pursuant to [the breach], there must appear by a preponderance of the
evidence, besides the fact of damage . . . , (1) that the damage was ‘occasioned,’ i.e., caused,
in whole or in part by (2) negligence or fault on the part of the contractor, (3) in the
performance of [or failure to perform] work under the contract.” American Stevedores, Inc.,
ASBCA 5286, 60-2 BCA ¶ 2686, at 13,557; see MOPAC Contracting/Engineering, Inc.,
AGBCA 83-144-1, 87-2 BCA ¶ 19,707, at 99,784 (“In assessing damages, the Government
bears the burden of proof.”). That is, after establishing a contract breach, the Government
must show that the contractor’s negligence was the proximate cause of the damages that the
Government is seeking. Harold J. Redding & Associates, ASBCA 1611, 1955 WL 8984
(Nov. 14, 1955).
The Board previously found UFS liable for a breach of the contract requirement
mandating that UFS respond to emergency calls within thirty minutes. Had UFS satisfied
that contract obligation, the water flowing out of the burst pipe would have lasted no more
than thirty minutes, given the uncontested fact established on summary judgment that, “[t]o
stop the flow of water into the room in which the pipe had burst,” access to which the
missing UFS project manager controlled, “all that was necessary was to turn a valve that was
located in the room near the pipe.” United Facility Services, 24-1 BCA at 187,314. Further,
at the hearing, GSA established that it incurred a total of $526,478.46 in repairing damage
caused by the burst pipe. What GSA did not present at the hearing was any evidence
comparing the water damage that the building would have suffered during the initial
thirty-minute grace period that UFS had to respond to the emergency call and the actual
damages that GSA ultimately suffered as a result of the four-hour delay.
“The remedy for breach of contract is damages sufficient to place the injured party in
as good a position as it would have been had the breaching party fully performed.” Indiana
Michigan Power Co. v. United States, 422 F.3d 1369, 1373 (Fed. Cir. 2005). Normally, we
would calculate proximate cause damages by “perform[ing] the necessary comparison
between the breach and non-breach worlds”—in this case, the total costs that GSA actually
incurred and the potentially more limited costs that GSA would have incurred from flooding
even if UFS had responded within thirty minutes of the emergency call—and then award
GSA the difference between those two calculations. Yankee Atomic Electric Co. v. United
States, 536 F.3d 1268, 1273 (Fed. Cir. 2008).
CBCA 7618
11
GSA’s failure to present any evidence allowing for a breach/non-breach world
comparison would be problematic if not for UFS’s breach of another contract obligation that
eliminates the need for such a comparison. UFS’s contract expressly required that UFS “be
responsible for any necessary operation and prevention of damage to equipment during on
and off duty hours . . . due to inclement weather . . . or freezing temperatures,” Exhibit 2A
at 113 (emphasis added), and “make reasonable efforts to prevent hazardous conditions and
property damage” at the Odell courthouse. Id. at 117. UFS was supposed to have “a system
for onsite work force personnel to report potentially hazardous conditions in the building to
the [contracting officer] or designee” and to “provide reasonable assistance to security or
emergency response personnel as needed.” Id. at 117-18. And it was “required to perform
the services required by the Contract and as identified by the [contracting officer] or their
designee [t]o the extent allowed during all emergency situations.” Id. at 179. These
provisions do not impose strict liability on UFS for every pipe that bursts, but they impose
an obligation on UFS to make reasonable efforts to protect against known dangers when it
becomes aware that freezing temperatures may affect the building.
UFS has admitted that it did not do that. It made clear that it was aware of predictions
of unusual weather and freezing temperatures coming to Memphis and had long known the
piping at issue was uninsulated, near exterior walls subject to outdoor airflow, and likely to
freeze and burst. Despite this knowledge, UFS made no effort to monitor the pipes or
attempt to reduce the possibility that they would freeze. In the circumstances here, the fact
that UFS knew of the likelihood of burst pipes but had no engineers or other personnel on
site during the weather event and made no effort to protect the building (through, for
example, strategically placed temporary heaters or insulated tarps) constituted a breach of
its obligations under the contract. Absent this breach, GSA would have suffered no damage,
given either that the pipe at issue would not have burst or, if it had, a responsible UFS
employee would have been there monitoring the pipes during what UFS calls an
unprecedented freeze. The responsible UFS employee could quickly have unlocked the room
in question and turned the valve to stop water flow. Exhibit 6 at 422; Respondent’s SUMF
¶ 9. Based upon this contract breach, GSA is entitled to recover the entire $526,478.46 that
it incurred to remedy the water damage.
II.
UFS’s Defenses to the Breach
A.
UFS’s “Act of God” Defense
Like it did in response to GSA’s summary judgment motion, UFS argues that it cannot
be held liable for the burst pipe because it was caused by an “Act of God”—that is, freezing
temperatures that were extreme for the Memphis area. The contract defines “Acts of God”
as “unanticipated grave natural disasters or other natural phenomenon of an exceptional,
inevitable, and irresistible character; the effects of which could not have been prevented or
CBCA 7618
12
avoided by the exercise of due care or foresight.” Exhibit 2A at 85 (clause C.2.3) (emphasis
added). “If the [contractor] could not reasonably foresee any injury as the result of his act
[or failure to act], or if his conduct was reasonable in light of what he could anticipate, there
is no negligence, and no liability.” Peter Kiewit Sons’ Co., IBCA 1789, 90-1 BCA ¶ 22,525,
at 113,057 (1989) (quoting William L. Prosser, Handbook on the Law of Torts 250 (4th ed.
1971)). Nevertheless, a “contractor would ordinarily be liable for loss or damage resulting
partly from an act of God . . . if their intervening negligence was of such magnitude that it
substantially increased the damage that would otherwise have occurred—in other words, if
they, rather than the natural occurrence, should be considered the supervening or proximate
cause of the damage.” Id. at 113,059.
Here, clause C.21.8 of UFS’s contract expressly required UFS to “be responsible for
any necessary operation and prevention of damage to equipment . . . due to inclement
weather . . . or freezing temperatures,” Exhibit 2A at 113, and clause C.29 similarly required
UFS to “make reasonable efforts to prevent hazardous conditions and property damage” at
the Odell courthouse. Id. at 117. As we discussed in our February 27 summary judgment
decision, UFS cannot blame an “act of God” for its failure to meet contractual obligations
that required it to anticipate and attempt to protect against reasonably foreseeable
occurrences. “A force majeure clause interpreted to excuse the [contractor] from the
consequences of the risk he expressly assumed [and the work to address emergencies that he
expressly agreed to perform] would nullify a central term of the contract.” United Facility
Services, 24-1 BCA at 187,318 (quoting Northern Indiana Public Service Co. v. Carbon
County Coal Co., 799 F.2d 265, 275 (7th Cir. 1986)).
In this case, there is no question that the freezing temperatures which caused the pipe
in the Odell courthouse to burst were reasonably foreseeable. They were predicted days
earlier, they had been ongoing for several days before the pipe burst, and UFS had agreed in
its contract to take responsibility for trying to protect the building from freezing temperatures
when reasonably foreseeable. The contract placed upon UFS an obligation to make
reasonable efforts to minimize the possibility of damage. See Sovereign Construction Co.,
GSBCA 712, 1964 BCA ¶ 4148, at 20,187 (Although a severe “drop in temperature was an
act of nature for which neither party to the contract was responsible[,] . . . [t]his does not . . .
absolve Appellant from its contractual obligation to have prevented the freeze [of pipes in
the building] since the evidence indicates Appellant could have done so.” (citations
omitted)). The evidence in this case makes clear that UFS made no effort to avoid frozen
pipes. It allowed all of its building engineers to stay home on the day in question, despite
knowing of uninsulated piping that, as Mr. Brown testified, was prone to freezing and
bursting. The record is devoid of any attempt by UFS to shield or heat areas of the building
that UFS knew had pipes prone to freezing. And UFS allowed the only employee that it had
on-site the day the pipe burst (and the only one with a key to the room in question) to leave
CBCA 7618
13
for more than four hours. In the circumstances here, UFS’s actions amount to a breach of
its contract obligation to attempt to protect the building from freezing temperatures.
B.
UFS’s Recharacterization of the Contract Requirements
At the hearing, UFS’s president asserted that “it [was] not [UFS’s] responsibility to
sit as a babysitter and almost sit there and wait for pipes to break.” Hearing Transcript at
176. He testified that UFS’s “job is to notify them and let them know that hey, you have a
possibility that eventually you’re going to have a pipe freeze.” Id. at 176. “[I]t is my
responsibility to have people onsite, but not when it’s an emergency, or you can’t drive or
get to work.” Id. at 177; see id. at 177-78 (“You can’t predict when a pipe is going to freeze,
or if something is going to break down. You can advise the government of what’s going on,
but I can’t sit there and say okay, you don’t want to spend money on this so I’ll have a guy
stand under a pipe when it gets below 32 degrees. That’s not our job.”); id. at 180 (“You’re
paying me to do the [preventative maintenance] in your building . . . on items that run on a
daily basis. If there’s an act of God, or excessive freezing, or a hurricane, you’re not paying
me for that.”). Mr. Brown’s characterization of UFS’s contract conflicts with the actual
contract language. See Exhibit 2A at 113, 117. UFS cannot avoid liability for breach by
misdescribing the contract requirements.
C.
UFS’s Complaints About Building Conditions
UFS also blames GSA for handing it a building to maintain that did not have all of the
upgrades and protections that UFS thinks it should have had, and it attempts to shift
responsibility for deficiencies in the building and the piping to GSA. Yet, UFS’s remedy for
its complaints about the building was simple: it did not have to bid for or accept this
contract. But it did, even though it knew of the building’s condition. In doing so, UFS
voluntarily assumed certain contractual responsibilities, including duties that it was required
to perform when it became aware of an impending weather event that UFS could reasonably
foresee might affect the building. Having accepted the contract with knowledge of the
building’s deficiencies, it could not ignore a weather emergency and blame GSA for not
giving it a better building to operate and maintain.
In these circumstances, UFS is responsible for all damage resulting from the burst
pipe, which GSA has established totals $526,478.46.
III.
CDA Interest
In its post-hearing reply brief, GSA asks us to apply interest pursuant to the Contract
Disputes Act (CDA), 41 U.S.C. §§ 7101–7109 (2018), to its damages award. Although the
CDA provides for interest on contractor claims, see id. § 7109(a)(1), it contains no
CBCA 7618
14
corresponding provision providing interest to the Government on a successful government
claim. Odyssey International, Inc., ASBCA 62085, et al., 21-1 BCA ¶ 37,861, at 183,851;
see Maggie’s Landscaping, Inc., ASBCA 56748, 11-2 BCA ¶ 34,807, at 171,293 (“No CDA
interest shall run on the amount of the government’s claim.”), reconsideration granted on
other grounds, 11-2 BCA ¶ 34,849; John Cibinic, Jr., James F. Nagle & Ralph C. Nash, Jr.,
Administration of Government Contracts 1097 (5th ed. 2016) (“[T]he Act does not provide
for interest on government claims.”). GSA has not identified any other basis, outside the
CDA, for an award of interest. GSA’s request for interest is denied.
Decision
UFS’s appeal is DENIED, and GSA’s claim, as adjusted, is granted. UFS shall pay
$526,478.46 to GSA as compensation for damage caused by UFS’s breach of its contractual
obligation to attempt to protect the Odell courthouse from freezing temperatures. GSA is not
entitled to CDA interest.
Harold D. Lester, Jr.
HAROLD D. LESTER, JR.
Board Judge
We concur:
Beverly M. Russell
BEVERLY M. RUSSELL
Board Judge
Allan H. Goodman
ALLAN GOODMAN
Board Judge
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.