BUCKLEY, Circuit Judge,

concurring in part and dissenting in part:

I am in substantial agreement with the majority on all but its essential conclusion. As I find that neither the potential post-construction hearing on conformity with the license’s acceptance criteria nor the section 2.206 proceeding is a permissible substitute for the pre-operational hearing mandated by section 189(a)(1) when read in conjunction with section 185, I must dissent.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.