1436.270-2 Part I—The Schedule.
FederalRegulations
Ask Donna
How this section applies to your facts.
Title 48—Federal Acquisition Regulations System > CHAPTER 14—DEPARTMENT OF THE INTERIOR > SUBCHAPTER F—SPECIAL CATEGORIES OF CONTRACTING > PART 1436—CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS > Subpart 1436.2—Special Aspects of Contracting for Construction
Text
The CO shall prepare the Schedule as follows:
(a) Section A, Solicitation/contract form. Use SF 1442, Solicitation, Offer, and Award (Construction, Alteration or Repair), as prescribed in FAR 36.701(a).
(b) Section B, Bid schedule. Bid schedule.
(c) Section C, Specifications/Drawings. Include specifications and drawings (See FAR Part 11) or reference other location in the uniform contract format (e.g. Section J, attachment ______).
(d) Section D, Packaging and Marking. Not applicable.
(e) Section E, Inspection and acceptance. Include inspection, acceptance, quality assurance, and reliability requirements (See FAR Part 46).
(f) Section F, Deliveries or performance. Include Suspension of Work, Liquidated Damages, Commencement, Prosecution, and Completion of Work, Variation in Quantity clauses (See FAR Part 12).
(g) Section G, Contract administration data. Include Contracting Officer's Representative/Technical Representative identification, and any required administration information (e.g., accounting and appropriation data).
(h) Section H, Special contract requirements. Include any special contract requirements which are not included in other sections of the uniform contract format.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.