§ 45.73 When will DOI file its modified condition or prescription?

FederalRegulations

Ask Donna

How this section applies to your facts.

Title 43—Public Lands: Interior > Subtitle A—Office of the Secretary of the Interior > PART 45—CONDITIONS AND PRESCRIPTIONS IN FERC HYDROPOWER LICENSES > Subpart C—Alternatives Process

This text was captured on Sep 22, 2026. It is a snapshot, not a live feed, so check the official code before relying on it.

Text

(a) Except as provided in paragraph (b) of this section, if any license party proposes an alternative to a preliminary condition or prescription under § 45.71, DOI will do the following within 60 days after the deadline for filing comments on FERC's draft NEPA document under 18 CFR 5.25(c):

(1) Analyze under § 45.74 any alternative condition or prescription proposed under § 45.71 or 45.72; and

(2) File with FERC:

(i) Any condition or prescription that DOI adopts as its modified condition or prescription; and

(ii) DOI's analysis of the modified condition or prescription and any proposed alternative.

(b) If DOI needs additional time to complete the steps set forth in paragraphs (a)(1) and (a)(2) of this section, it will so inform FERC within 60 days after the deadline for filing comments on FERC's draft NEPA document under 18 CFR 5.25(c).

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.