§ 60.2045 Who must prepare a siting analysis?
FederalRegulations
Ask Donna
How this section applies to your facts.
Title 40—Protection of Environment > CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY > SUBCHAPTER C—AIR PROGRAMS > PART 60—STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES > Subpart CCCC—Standards of Performance for Commercial and Industrial Solid Waste Incineration Units > Preconstruction Siting Analysis
Text
(a) You must prepare a siting analysis if you plan to commence construction of an incinerator after December 1, 2000.
(b) You must prepare a siting analysis for CISWIs that commenced construction after June 4, 2010, or that commenced reconstruction or modification after August 7, 2013.
(c) You must prepare a siting analysis if you are required to submit an initial application for a construction permit under 40 CFR part 51, subpart I, or 40 CFR part 52, as applicable, for the reconstruction or modification of your CISWI.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.