OAR 860-082-0040. Insurance
OregonRegulations
Ask Donna
How this section applies to your facts.
Oregon Administrative Rules › Chapter 860 Public Utility Commission › Division 82 SMALL GENERATOR INTERCONNECTION RULES › OAR 860-082-0040
Text
(1) A public utility may not require an applicant or an interconnection customer with a small generator facility with a nameplate rating of 200 kilowatts or less to obtain liability insurance in order to interconnect with the public utility’s transmission or distribution system.
(2) A public utility may require an applicant or an interconnection customer with a small generator facility with a nameplate rating greater than 200 kilowatts to obtain prudent amounts of general liability insurance in order to interconnect to the public utility’s transmission or distribution system.