A. A utility may only charge a small generator interconnection request fee for a Level 2, Level 3, or Level 4 interconnection request.

B. A utility may not charge interconnection request fees for interconnection requests determined to be under PJM Interconnection, LLC jurisdiction pursuant to Regulation .01 of this chapter .

C. The utility shall specify the interconnection [processing] request fees charged under this regulation in its tariff.