278.019 Deadlines for commission to issue final orders -- Failure to meet deadline deemed approval
KentuckyStatutes
Ask Donna
How this section applies to your facts.
KY Code › Title XXIV › Chapter 278 › Section 278.019
Text
278.019 Deadlines for commission to issue final orders -- Failure to meet deadline
deemed approval.
(1) Except as otherwise provided in KRS 278.010 to KRS 278.450, if the commission
fails to issue a final order on any application submitted to it by a utility pursuant to
KRS 278.018, 278.020, 278.216, 278.218, 278.271, and 278.300 within eight (8)
months of the acceptance of the filing of the application, then the application shall
be deemed approved by the commission and the relief requested shall be deemed to
be granted.
(2) The commission shall complete and issue a final order on all eight (8) month and
two (2) year reviews of the operation of a utility's environmental surcharge and fuel
adjustment clause within eight (8) months of commencing the review.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.