Sec. 9. Each tier 1 contractor must contribute in:

(1) work performed by the tier 1 contractor's employees;

(2) materials supplied directly by the tier 1 contractor;

(3) services supplied directly by the tier 1 contractor's employees; or

(4) any combination of subdivisions (1) through (3);

at least fifteen percent (15%) of the tier 1 contractor's total contract price as determined at the time the contract is awarded.

As added by P.L.252-2015, SEC.12.