Section 300.30 Fees
IllinoisRegulations
Ask Donna
How this section applies to your facts.
Illinois Administrative Code › Title 62 MINING › CHAPTER I: DEPARTMENT OF NATURAL RESOURCES › Part 300 SURFACE MINED LAND CONSERVATION AND RECLAMATION ACT › Section 300.30 Fees
Text
Section 300
Section 300.30 Fees
a) Fees Generally
Each application for a permit shall require a separate fee
payment. Permit fees are not to accompany the application. After receipt of
the application, the Department will request the permit fee before issuance of
the permit. The fee shall be in the form of a check made payable to the Illinois
Department of Natural Resources, Office of Mines and Minerals.
b) Permit Fee Calculation
1) Surface Mining Permit
The fee for a surface mining permit shall be $150 for every
acre and fraction of an acre of land to be permitted. The permit fee shall only
be paid once on an acre of land regardless of the number of permit periods it
is mined, but, with respect to areas where the overburden is to be removed
again and upon which the surety bonds have been released, a new permit, fees
and bond will be required.
2) Refuse Disposal Permits
The fee for a gob refuse disposal permit and for a slurry
pond refuse disposal permit shall be calculated in the same manner as the fee
to engage in surface mining. The permit fee shall only be paid once on an acre
of land regardless of the active life of a disposal area.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.