Section 300.215 General Requirements
IllinoisRegulations
Ask Donna
How this section applies to your facts.
Illinois Administrative Code › Title 62 MINING › CHAPTER I: DEPARTMENT OF NATURAL RESOURCES › Part 300 SURFACE MINED LAND CONSERVATION AND RECLAMATION ACT › Section 300.215 General Requirements
Text
Section 300
Section 300.215 General
Requirements
a) Each person who conducts blasting operations shall comply with
all applicable State and federal laws governing the use of explosives.
b) Each blast shall be designed, executed and detonated by a
licensed blaster. The licensed blaster must be present during each phase of
the loading and detonation process. The licensed blaster may appoint another
individual who is deemed competent and meets all requirements to handle
explosives in Illinois to detonate a blast. However, the licensed blaster must
be physically present during the detonation process.
c) All blasting shall be conducted between sunrise and sunset
except in emergency situations where unscheduled blasting is required to ensure
operator or public safety. In such cases, the operator shall notify the
Department in writing within 72 hours after the unscheduled blast, stating the reasons
for the unscheduled blast. After review of the notification, the Department
shall determine whether the unscheduled blast was an emergency and take
enforcement action if necessary.
d) Blasts consisting of explosive materials loaded into
blastholes and of which the explosives are unable to be removed and stored in a
Department certified explosive storage magazine must be attended by an
Individual Explosive License holder, Licensed Blaster, Illinois Surface Coal
Certification holder, or persons meeting the exemptions of 62 Ill. Adm. Code
200.90(d)(5) at all times. No explosives shall be left unattended.
e) Explosives may be used to clear blockage in crushing operations
at any time provided the explosive charge does not exceed one pound, and the
operator complies with all other requirements of this Part, except those found
in subsection (c).
f) Vehicles
and equipment shall not be driven over explosive material or initiating
systems.
g) Prior to firing a blast:
1) Ample
warning shall be given to allow all persons to be evacuated
tions
at any time provided the explosive charge does not exceed one pound, and the
operator complies with all other requirements of this Part, except those found
in subsection (c).
f) Vehicles
and equipment shall not be driven over explosive material or initiating
systems.
g) Prior to firing a blast:
1) Ample
warning shall be given to allow all persons to be evacuated.
2) All
access routes to the blasting zone shall be guarded or barricaded to prevent
the passage of unauthorized persons or vehicles.
h) When
a misfire is suspected, the blasting zone shall be cleared of all personnel
for:
1) a
minimum of 30 minutes when using safety fuse, detonating cord and electronic
initiation systems; or
2) a minimum of 15 minutes
for electric and shock tube initiation systems.
i) If
explosive material is suspected of burning at the blast site, persons shall be
evacuated from the endangered area and shall not return for at least one hour
after the burning or suspected burning has stopped.
j) During
the approach and progress of an electrical storm, blasting operations shall be
suspended and persons withdrawn from the blasting zone and relocated to a safe
location.
k) The
source of energy used to initiate the blast shall not be connected to the
blasting circuit until it has been confirmed that the blasting zone is clear,
and it is safe to fire the blast.
l) Blastholes
shall not be drilled where there is a danger of intersecting a misfired hole or
a hole containing explosives, blasting agents, or detonators.
m) Operators
shall assure that the blast site is free of hazards prior to the arrival of
explosives including, but not limited to, highwall safety and ground stability.
n) Tamping shall not be
done directly on a primer
Blastholes
shall not be drilled where there is a danger of intersecting a misfired hole or
a hole containing explosives, blasting agents, or detonators.
m) Operators
shall assure that the blast site is free of hazards prior to the arrival of
explosives including, but not limited to, highwall safety and ground stability.
n) Tamping shall not be
done directly on a primer.
o) Work
shall not resume in the blast area until a post-blast examination addressing
potential blast-related hazards has been conducted by a person with the ability
and experience to perform the examination.
p) Blasting
activities incident to underground mining, including all blasts within 50 feet
of the development of slopes and shafts, are considered a surface blast.