Section 2000.4015 Acquisition of Leases by RFI
IllinoisRegulations
Ask Donna
How this section applies to your facts.
Illinois Administrative Code › Title 44 GOVERNMENT CONTRACTS, GRANTMAKING, PROCUREMENT AND PROPERTY MANAGEMENT › CHAPTER XXV: SECRETARY OF STATE › Part 2000 SECRETARY OF STATE STANDARD PROCUREMENT › Section 2000.4015 Acquisition of Leases by RFI
Text
Section 2000
Section 2000.4015
Acquisition of Leases by RFI
All leases, except those falling
under the exceptions listed in Section 2000.4020 or emergency procurements
(Section 2000.4045) will be acquired as follows:
a) All leases will be procured by a Request for Information
(RFI). RFIs will contain at a minimum the following information:
1) A description of the general type of property to be leased.
2) The proposed use of the property.
3) The proposed term of the lease.
4) The preferred location of the property.
5) The general information such as size of space, configuration
desired, and any other appropriate requirements.
6) The address to which requests for proposal may be sent.
7) The date by which responses are due.
8) Response forms and instructions for completing forms.
9) A copy of spatial and performance guidelines required to meet
the needs of the SOS Department that will occupy the real property being
procured.
b) Notice of the RFI shall be published at least 14 days prior to
the deadline for responding in the Bulletin.
c) Responses.
1) The
Request for Information may include a form or format for submitting responses.
If a form or format is specified, vendor shall submit responses as instructed.
2) The RFI response must detail how the respondent will meet all
required criteria set forth in the RFI.
d) Proposal packages must, at a minimum, include:
1) A Proposal Form.
2) A copy of the agency program requirements.
3) The date by which proposals must be submitted.
e) All responses to the RFI will be publicly opened on the
announced opening date. Names of all parties submitting proposals will be made
available to the public.
f) Secretary of State representatives may conduct discussions
with respondents to further clarify the needs of the State or obtain further
information on responses
The date by which proposals must be submitted.
e) All responses to the RFI will be publicly opened on the
announced opening date. Names of all parties submitting proposals will be made
available to the public.
f) Secretary of State representatives may conduct discussions
with respondents to further clarify the needs of the State or obtain further
information on responses.
g) Based on the responses to the RFI, the Chief Procurement
Officer (CPO) or a designee will make a written determination of which RFIs
submitted are responsive to the State's basic criteria.
h) Secretary of State representatives will enter into
negotiations with all parties submitting responsive RFIs for the purpose of
obtaining the best terms for the State. A written record of all negotiations
will be maintained by the Secretary of State.
i) A Secretary of State representative will review all relevant
information and recommend to the CPO which proposal should be accepted.
j) The CPO will make the final award, which will be announced in
the Bulletin.
k) The lease will be reduced to writing and executed by all
parties.
l) If the lowest-priced proposal is not selected, the CPO will
publish notice, along with the reasons for such selection, in the next
available edition of the Bulletin.
m) The Secretary of State reserves the right to reject any and all
proposals and to request and evaluate "best and final" proposals.
All decisions on compliance, evaluations, terms, and conditions will be made
solely at the Secretary of State's discretion and made to favor the State.