Section 663.640 Compliance with Procurement Requirements for Construction Contracts
IllinoisRegulations
Ask Donna
How this section applies to your facts.
Illinois Administrative Code › Title 35 ENVIRONMENTAL PROTECTION › CHAPTER II: ENVIRONMENTAL PROTECTION AGENCY › Part 663 PROCEDURES FOR ISSUING LOANS FROM THE PUBLIC WATER SUPPLY LOAN PROGRAM TO PROVIDE FUNDING FOR LEAD SERVICE LINE REPLACEMENT › Section 663.640 Compliance with Procurement Requirements for Construction Contracts
Text
Section 663.640 Compliance with Procurement Requirements
for Construction Contracts
a) Loan
Applicant Responsibility
The loan applicant shall be
responsible for selecting the low, responsive, and responsible bidder or other
contractor in accordance with applicable requirements of State, federal, and
local laws and ordinances, as well as for the specific requirements of the loan
agreement directly affecting procurement. The loan applicant shall also be
responsible for the initial resolution of complaints based upon alleged
violations. Any complaints made to the Agency concerning any alleged violation
of law in the procurement of construction services or materials for a project
involving construction work will be referred to the loan applicant for
resolution. The loan applicant shall promptly determine each complaint on its
merits and shall allow the complainant and any other party who may be adversely
affected to state in writing or at a conference the basis for their views
concerning the proposed procurement. The loan applicant shall promptly send by
certified mail to the complainant and other affected parties a written summary
of its determination, substantiated by an engineering or legal opinion
providing a justification for its determination.
b) Time
Limitations
Complaints should be made as early
as possible during the procurement process, preferably prior to the bid
opening, to avoid disruption of the procurement process. The complaint shall
be mailed (certified mail, return receipt requested) or otherwise delivered no
later than 5 working days after the complainant becomes aware of an alleged
violation. Unless all bids are rejected, if there is no agreement between the
parties within 7 days following the loan applicant's response, the matter shall
be resolved in accordance with subsection (c)
ement process. The complaint shall
be mailed (certified mail, return receipt requested) or otherwise delivered no
later than 5 working days after the complainant becomes aware of an alleged
violation. Unless all bids are rejected, if there is no agreement between the
parties within 7 days following the loan applicant's response, the matter shall
be resolved in accordance with subsection (c).
c) Remedies
All claims, counter-claims,
disputes, and other matters in question between the recipient and the
contractor arising out of, or relating to, a subagreement or its breach shall
be decided by arbitration if the parties agree, or in a court of competent
jurisdiction within the State.
d) Deferral
of Procurement Action
If the determination of a
complaint by the loan applicant is adverse to the complainant, the loan
applicant shall defer issuance of its solicitation or award or notice to
proceed under the contract (as appropriate) for 7 days after mailing or
delivery of the determination. If the determination (whether made by the loan
applicant, the arbitrator or the court) is favorable to the complainant, the
terms of the solicitation shall be revised or the contract shall be awarded, as
appropriate, in accordance with the determination.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.