Section 364.105 Pre-applications and Priority Scoring Summaries
IllinoisRegulations
Ask Donna
How this section applies to your facts.
Illinois Administrative Code › Title 35 ENVIRONMENTAL PROTECTION › CHAPTER II: ENVIRONMENTAL PROTECTION AGENCY › Part 364 PROCEDURES AND REQUIREMENTS FOR DETERMINING CONSTRUCTION GRANT PRIORITIES FOR MUNICIPAL SEWAGE TREATMENT WORKS NEEDS › Section 364.105 Pre-applications and Priority Scoring Summaries
Text
Section 364
Section 364.105
Pre-applications and Priority Scoring Summaries
a) A municipality may submit a pre-application and a priority
scoring summary at any time. The pre-application must identify the scope of
the project, and include a cost estimate and schedule for completion of the
project. The priority scoring summary must include data to allow calculation
of the Grant Priority Index in accordance with the requirements of this Part.
b) A municipality is not required to renew a pre-application or a
priority scoring summary unless the scope, schedule, scoring data or grant request
differs from that of the previous year, and unless the municipality has not yet
advised IEPA of the changes.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.