As applied to construction of a
major stationary source or major modification "commence" means that
the owner or operator has obtained all necessary preconstruction approvals or
permits and either has:
a) Begun, or caused to begin, a continuous program of actual
on-site construction of the source, to be completed within a reasonable time;
or
b) Entered into binding agreements or contractural obligations,
which cannot be cancelled or modified without substantial loss to the owner or
operator, to undertake a program of actual construction of the source to be
completed within a reasonable time.
c) For purposes of this Secton, a "reasonable time"
shall be determined considering but not limited to the following factors: The
nature and size of the project, the extent of design engineering, the amount of
off-site preparation, whether equipment can be fabricated or can be purchased,
when the project begins (considering both the seasonal nature of construction
activity and the existence of other projects competing for construction labor
at the same time, the place of the environmental permit in the sequence of
corporate and overall governmental approval), and the nature of the permittee
(private, public, regulated, etc).