a) General
Practices. This Section contains the requirements for new construction in
Illinois in accordance with the Radon Resistant Construction Act [420 ILCS
52]. The following required construction methods are intended to resist radon
entry and prepare the building for post-construction radon mitigation, if
necessary. These techniques are required in all areas of Illinois.
b) Subfloor
Preparation. A layer of gas-permeable material shall be placed under all
concrete slabs and other floor systems that directly contact the ground and are
within the walls of the living spaces of the buildings, to facilitate future
installation of a sub-slab depressurization system, if needed. The gas
permeable layer shall consist of one of the following:
1) A
uniform layer of clean aggregate, a minimum of 4 inches (102 mm) thick. The
aggregate shall consist of material that will pass through a 2 inch (51 mm)
sieve and be retained by a ¼ inch (6.4 mm) sieve; or
2) A
uniform layer of sand (native or fill), a minimum of 4 inches (102 mm) thick, overlain
by a layer or strips of geo-textile drainage matting designed to allow the
lateral flow of soil gases. The geotextile matting shall have a
cross-sectional area of not less than 12 square inches (77 sq. cm) and shall be
placed, at a minimum, along the entire inside perimeter of the foundation at a
distance of 12 to 18 inches (30 to 46 cm) distance from the foundation wall to
the edge of the drainage matting. Deviation from the 12 to 18 inches (30 to 46
cm) distance to the foundation wall shall be allowed to avoid obstacles such as
plumbing and other utilities; or
3) Other
materials, systems or floor designs with demonstrated capability to permit
depressurization across the entire subfloor area.
c) Soil Gas
Retarder
ce from the foundation wall to
the edge of the drainage matting. Deviation from the 12 to 18 inches (30 to 46
cm) distance to the foundation wall shall be allowed to avoid obstacles such as
plumbing and other utilities; or
3) Other
materials, systems or floor designs with demonstrated capability to permit
depressurization across the entire subfloor area.
c) Soil Gas
Retarder. A minimum 6-mil (0.15 mm) (or 3-mil (0.075 mm) cross‑laminate)
polyethylene or equivalent flexible sheeting material shall be placed on top of
the gas permeable layer prior to casting the slab or placing the floor assembly
to serve as a soil gas retarder by bridging any cracks that develop in the slab
or floor assembly and to prevent concrete from entering the void spaces in the
aggregate base material. The sheeting shall cover the entire floor area with
separate sections of sheeting lapped at least 12 inches (305 mm). The sheeting
shall fit closely around any pipe, wire or other penetrations of the material.
All punctures or tears in the material shall be sealed or covered with
additional sheeting.
d) Entry
Routes. Potential radon entry routes shall be closed in accordance with the
following:
1) Floor
openings around bathtubs, showers, water closets, pipes, wires or other objects
that penetrate concrete slabs or other floor assemblies shall be filled with a
polyurethane caulk or equivalent sealant applied in accordance with the
manufacturer's recommendations.
2) All
concrete control joints, isolation joints, construction joints and any other
joints in concrete slabs or between slabs and foundation walls shall be sealed
with a polyurethane caulk. Gaps and joints shall be cleared of loose material
and filled with polyurethane caulk applied in accordance with the manufacturer's
recommendations.
3) Condensate
drains shall be trapped or routed through non-perforated pipe to daylight
n joints, construction joints and any other
joints in concrete slabs or between slabs and foundation walls shall be sealed
with a polyurethane caulk. Gaps and joints shall be cleared of loose material
and filled with polyurethane caulk applied in accordance with the manufacturer's
recommendations.
3) Condensate
drains shall be trapped or routed through non-perforated pipe to daylight.
4) Sump
pits open to soil or serving as the termination point for subslab or exterior
drain tile loops shall be covered with a gasketed or otherwise sealed lid.
Sump pits shall not be used as a primary suction point in a sub-slab
depressurization system. Sumps used as a floor drain shall have a lid equipped
with a trapped inlet.
5) Hollow
block masonry foundation walls shall be constructed with either a continuous
course of solid masonry, one course of masonry grouted solid, or a solid
concrete beam at or above finished ground surface to prevent passage of air
from the interior of the wall into the living space. Where a brick veneer or
other masonry ledge is installed, the course immediately below that ledge shall
be sealed. Joints, cracks or other openings around all penetrations of both
exterior and interior surfaces of masonry block or wood foundation walls below
the ground surface shall be filled with polyurethane caulk or equivalent
sealant. Penetrations of concrete walls shall be filled.
6) The
exterior surfaces of concrete and masonry block walls below the ground surface
shall be damp-proofed in accordance with Section R406 of the 2012 International
Residential Code for One- and Two-Family Dwellings (copyrighted 2011 by the
International Code Council, Inc.; incorporated by reference in accordance with
Section 422.15).
7) Air-handling
units shall be sealed to prevent air from being drawn into the unit. Units
with gasketed seams or units that are otherwise sealed by the manufacturer to
prevent leakage are exempted from this requirement
ential Code for One- and Two-Family Dwellings (copyrighted 2011 by the
International Code Council, Inc.; incorporated by reference in accordance with
Section 422.15).
7) Air-handling
units shall be sealed to prevent air from being drawn into the unit. Units
with gasketed seams or units that are otherwise sealed by the manufacturer to
prevent leakage are exempted from this requirement.
8) Underground
and crawlspace duct systems shall be sealed in accordance with Section M1601.4.1
of the 2012 International Residential Code for One- and Two-Family Dwellings
(copyrighted 2011 by the International Code Council, Inc.; incorporated by
reference in accordance with Section 422.15).
9) Openings
around all penetrations through floors above crawlspaces shall be caulked or
otherwise filled to prevent air leakage.
10) Access
doors and other openings or penetrations into crawlspaces shall be closed,
gasketed or otherwise sealed to prevent air leakage.
e) Passive
Sub-membrane Depressurization (SMD) System. In buildings with crawlspace
foundations or earthen floors, the following components of a passive SMD system
shall be installed during construction.
1) Crawlspaces
shall be provided with vents to the exterior of the building in accordance with
Section R408 of the 2012 International Residential Code for One- and Two‑Family
Dwellings.
2) The
soil in crawlspaces shall be covered with a continuous layer of minimum 6-mil
(0.15 mm) polyethylene soil gas retarder. The ground cover shall be lapped a
minimum of 12 inches (305 mm) at joints and shall extend to all foundation
walls enclosing the crawlspace area.
3) Any
seams in soil gas retarder membranes shall be overlapped at least 12 inches and
sealed in a permanent air tight manner using compatible glues
covered with a continuous layer of minimum 6-mil
(0.15 mm) polyethylene soil gas retarder. The ground cover shall be lapped a
minimum of 12 inches (305 mm) at joints and shall extend to all foundation
walls enclosing the crawlspace area.
3) Any
seams in soil gas retarder membranes shall be overlapped at least 12 inches and
sealed in a permanent air tight manner using compatible glues. The membrane
shall also be sealed around interior piers and to the inside of exterior walls
with furring strips and compatible glues or in accordance with specific
procedures submitted by radon contractors as part of their license application
and approved by the Agency.
4) A
plumbing tee or other approved connection fitted with not less than 5 feet (105
m) of perforated pipe extending from each horizontal opening of the tee shall
be inserted horizontally beneath the sheeting and connected to a 3- or 4-inch
diameter (76 mm or 102 mm) fitting with a vertical vent pipe installed through
the sheeting. The vent pipe shall be extended up through the building floors,
terminate at least 12 inches (305 mm) above the penetration in the highest roof
in a location at least 2 feet (609.6 mm) above any window or other opening into
the conditioned spaces of the building and 10 feet (3048 mm) from any window or
other opening in adjoining or adjacent buildings.
f) Passive
Sub-slab Depressurization (SSD) System. Buildings with a basement, crawlspace
or slab-on grade concrete floor in contact with the earth or grade shall have
the following components of a passive SSD system that shall be installed during
construction.
1) A
minimum 3-inch diameter (76 mm) Schedule 40 PVC shall be embedded vertically
into the sub-slab aggregate or other permeable material before the slab is cased
(SSD) System. Buildings with a basement, crawlspace
or slab-on grade concrete floor in contact with the earth or grade shall have
the following components of a passive SSD system that shall be installed during
construction.
1) A
minimum 3-inch diameter (76 mm) Schedule 40 PVC shall be embedded vertically
into the sub-slab aggregate or other permeable material before the slab is cased.
A) A
plumbing tee or other approved connection fitted with not less than 5 feet (105
m) of perforated pipe extending from each horizontal opening of the tee shall
be inserted horizontally within the sub-slab permeable material to ensure that
the pipe opening remains within the sub-slab. Alternatively, the 3-inch (76
mm) pipe shall be inserted directly into an interior perimeter drain tile
loop. The vent pipe shall be extended up through the building floors,
terminate at least 12 inches (305 mm) above the highest roof in a location of
at least 2 feet (609.6 mm) above any window or other opening into the
conditioned spaces of the building and 10 feet (3048 mm) from any window or
other opening in adjoining or adjacent buildings; or
B) A
penetration into the sub-slab permeable material may be cored through sub-slab
after the slab is cased. A minimum 3-inch diameter (76 mm) Schedule 40 PVD
shall be embedded vertically into the sub-slab aggregate or other permeable
material and extended up through the building floors, terminate at least 12
inches (305 mm) above the penetration in the highest roof in a location at
least 2 feet (609.6 mm) above any window or other opening into the conditioned
spaces of the building and 10 feet (3048 mm) from any window or other opening
in adjoining or adjacent buildings.
2) In
buildings where interior footings or other barriers separate the sub-slab
aggregate or other gas-permeable material, each area shall be fitted with an
individual vent pipe
n a location at
least 2 feet (609.6 mm) above any window or other opening into the conditioned
spaces of the building and 10 feet (3048 mm) from any window or other opening
in adjoining or adjacent buildings.
2) In
buildings where interior footings or other barriers separate the sub-slab
aggregate or other gas-permeable material, each area shall be fitted with an
individual vent pipe. Vent pipes shall connect to a single vent that shall
terminate at least 12 inches (305 mm) above the penetration in the highest roof
in a location at least 2 feet (609.6 mm) above any window or other opening into
the conditioned spaces of the building and 10 feet (3048 mm) from any window or
other opening in adjoining or adjacent buildings.
g) All
components of the radon vent pipe system shall be installed to provide positive
drainage to the ground beneath the slab or soil gas retarder.
h) Radon
vent pipes shall be accessible for fan installation through an attic or other
area outside and above the habitable space. The radon vent pipe need not be
accessible in an attic space when an approved roof-top electrical supply is
provided for future use.
i) All
exposed and visible interior radon vent pipes shall be conspicuously identified
with at least one label on each floor and in accessible attics. The label
shall read "Radon Reduction System".
j) Combination
basement/crawlspace or slab-on-grade/crawlspace foundations shall have separate
radon vent pipes installed in each type of foundation area or be connected with
a continuous drain tile loop. Vent pipes shall connect to a single vent that
shall terminate at least 12 inches (305 mm) above the highest roof in a
location at least 2 feet (609.6 mm) above any window or other opening into the
conditioned spaces of the building and 10 feet (3048 mm) from any window or
other opening in adjoining or adjacent buildings
e of foundation area or be connected with
a continuous drain tile loop. Vent pipes shall connect to a single vent that
shall terminate at least 12 inches (305 mm) above the highest roof in a
location at least 2 feet (609.6 mm) above any window or other opening into the
conditioned spaces of the building and 10 feet (3048 mm) from any window or
other opening in adjoining or adjacent buildings.
k) Joints
in air ducts and plenum spaces shall meet the requirements of Section M1601 of
the 2012 International Residential Code for One- and Two-Family Dwellings
(copyrighted 2011 by the International Code Council, Inc.; incorporated by
reference pursuant to Section 422.15). Thermal envelope air infiltration
requirements shall comply with the energy conservation provisions in Chapter 11
of the 2012 International Residential Code for One- and Two-Family Dwellings
(copyrighted 2011 by the International Code Council, Inc.; incorporated by
reference pursuant to Section 422.15). Firestopping shall be in conformance
with the most recent general building code enacted by the appropriate local
government or meet the requirements contained in Section R302.11 of the 2012
International Residential Code for One- and Two-Family Dwellings (copyrighted
2011 by the International Code Council, Inc.; incorporated by reference pursuant
to Section 422.15).
l) To
provide for future installation of an active SMD or SSD system, an electrical
circuit terminated to a single outlet in an accessible approved box shall be
installed during construction in the attic in the anticipated location of vent
pipe fans.
m) To
provide for future installation of an active SSD, the piping length in the
attic of the building shall have a minimum height of 3 feet to allow for the
anticipated installation of a radon mitigation fan in the vent pipe.
n) The
juncture of each radon vent pipe with the roof line shall be made water tight
by an approved flashing
e anticipated location of vent
pipe fans.
m) To
provide for future installation of an active SSD, the piping length in the
attic of the building shall have a minimum height of 3 feet to allow for the
anticipated installation of a radon mitigation fan in the vent pipe.
n) The
juncture of each radon vent pipe with the roof line shall be made water tight
by an approved flashing. Lead vent flashings or any other flashing or cap that
would impede the exhaust from the radon vent are prohibited from use.