Title 18 CFR: Conservation of Power and Water Resources › Chapter I: FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY › Part 157: APPLICATIONS FOR CERTIFICATES OF PUBLIC CONVENIENCE AND NECESSITY AND FOR ORDERS PERMITTING AND APPROVING ABANDONMENT UNDER SECTION 7 OF THE NATURAL GAS ACT › Subpart B: Open Seasons for Alaska Natural Gas Transportation Projects › § 157.38: § 157.38 Pre-approval procedures.

This text was captured on Aug 14, 2026. It is a snapshot, not a live feed, so check the official code before relying on it.

Text

No later than 90 days prior to providing the notice of open season required by § 157.34(a), a prospective applicant must file, for Commission approval, a detailed plan for conducting an open season in conformance with this subpart. The prospective applicant's plan shall include the proposed notice of open season. Upon receipt of a request for such a determination, the Secretary of the Commission shall issue a notice of the request, which will then be published in the

Federal Register.

The notice shall establish a date on which comments from interested persons are due and a date, which shall be within 60 days of receipt of the prospective applicant's request unless otherwise directed by the Commission, by which the Commission will act on the proposed plan.

[Order 2005-A, 70 FR 35026, June 16, 2005]

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

§ 157.38 Pre-approval procedures. · 18 C.F.R. § 157.38 (2026) | Frix