Revision Of Existing Regulations Under the Natural Gas Act

Federal RegisterOct 7, 1999

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

18 CFR Parts 2, 157, 284, 380, and 385

[Docket No. RM98-9-001; Order No. 603-A]

Revision Of Existing Regulations Under the Natural Gas Act

Issued September 29, 1999.

AGENCY: Federal Energy Regulatory Commission.

ACTION: Final rule; order on rehearing.

-----------------------------------------------------------------------

SUMMARY: On rehearing, the Federal Energy Regulation Commission

reaffirms its basic determinations in Order No. 603 and modifies and

clarifies certain aspects of the Final Rule based on the requests for

rehearing. Order No. 603 updated the Commission's regulations governing

the filing of applications for the construction and operation of

facilities to provide service or to abandon facilities or service under

section 7 of the Natural Gas Act. The changes were necessary to conform

the Commission's regulations to the Commission's current policies.

DATES: The revision to the regulations in this order on rehearing

become effective November 8, 1999.

ADDRESSES: Federal Energy Regulatory Commission 888 First Street, N.E.

Washington DC, 20426.

FOR FURTHER INFORMATION CONTACT:

Michael J. McGehee, Office of Pipeline Regulation, Federal Energy

Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426,

(202) 208-2257

Carolyn Van Der Jagt, Office of the General Counsel, Federal Energy

Regulatory Commission 888 First Street, N.E., Washington, DC 20426

(202)208-2246.

SUPPLEMENTARY INFORMATION: In addition to publishing the full text of

this document in the Federal Register, the Commission also provides all

interested persons an opportunity to inspect or copy the contents of

this document during normal business hours in the Public Reference Room

at 888 First Street, NE., Room 2A, Washington, DC 20426.

The Commission Issuance Posting System (CIPS) provides access to

the texts of formal documents issued by the Commission from November

14, 1994, to the present. CIPS can be accessed via Internet through

FERC's Home Page (http://www.ferc.fed.us) using the CIPS Link or the

Energy Information Online icon. Documents will be available on CIPS in

ASCII and WordPerfect 8.0. User assistance is available at 202-208-2474

or by E-mail to [email protected].

This document is also available through the Commission's Records

and Information Management System (RIMS), an electronic storage and

retrieval system of documents submitted to and issued by the Commission

after November 16, 1981. Documents from November 1995 to the present

can be viewed and printed. RIMS is available in the Public Reference

Room or remotely via Internet through FERC's Home Page using the RIMS

link or the Energy Information Online icon. User assistance is

available at 202-208-2222, or by E-mail to [email protected].

Finally, the complete text on diskette in WordPerfect format may be

purchased from the Commission's copy contractor, RVJ International,

Inc. RVJ International, Inc. is located in the Public Reference Room at

888 First Street, NE, Washington, DC 20426.

[[Page 54523]]

I. Introduction

In this order the Federal Energy Regulatory Commission (Commission)

is modifying and clarifying certain aspects of the Final Rule issued in

Order No. 603.1 Specifically, this order (1) clarifies

certain aspects of section 2.55, including the 30-day notification

requirement, the construction area requirements, and the phrase

``designed delivery capacity'' as it pertains to a storage reservoir;

(2) clarifies how a pipeline should apply the construction area

guidelines in Appendix A to Part 2; (3) explains the modifications to

the existing electronic filing requirements in section 157.6; (4)

clarifies that under section 157.8 the Director of the Office of

Pipeline Regulation (OPR) may reject an application subsequent to

noticing it if the applicant fails to provide necessary information;

(5) clarifies certain aspects of section 157.10 that requires that the

pipeline make available copies of its application and voluminous or

difficult to reproduce material at various locations along the proposed

pipeline route; (6) explains aspects of section 157.202(b), including

the application of the terms ``closest available size'' and ``sound

engineering reasons,'' and clarifies what minor changes to storage

operations would encompass; (7) changes the definition of

``interconnecting point'' in section 157.202(b)(2)(ii) to include the

related pipeline segment; (8) explains the implications of the

dismissal of protests under section 157.205(g); (9) explains the

compressor station noise requirements in section 157.206(b)(5); (10)

removes the phrase ``due to construction delays'' from section

157.206(c); (11) explains certain environmental requirements in section

157.208(c)(9); (12) clarifies the applicability of the prior notice

procedures to increases to the Maximum Allowable Operating Pressures;

(13) denies requests that the Commission review its bypass and contract

demand (CD) reduction policies in this proceeding; (14) clarifies the

automatic and prior notice abandonment authorization in section

157.216; (15) clarifies the application of certain requirements under

the National Historic Preservation Act of 1966 in Appendix II to

Subpart F and section 380.14; (16) explains the requirements concerning

nonjurisdictional facilities in section 380.12(c)(2); (17) clarifies

the requirements concerning the cultural resource reports required in

section 380.12(f)(2); (18) modifies the minimum filing requirements in

section 380.12(k)(4) for information concerning compressor facilities;

(19) clarifies the minimum filing requirements applying to the Coastal

Zone Management Act in Appendix A to Part 380, Resource Report 8; and

(20) explains the siting and maintenance requirements in section

380.15.

---------------------------------------------------------------------------

\1\ Revisions of Existing Regulations Under Part 157 and Related

Sections of the Commission's Regulations Under the Natural Gas Act,

Order No. 603, 64 FR 26571 (May 14, 1999), FERC Stats. and Regs.

para. 31,073 (Apr. 29, 1999).

---------------------------------------------------------------------------

II. Background

On April 29, 1999, the Commission issued a Final Rule in Order No.

603 amending its regulations governing the filing of applications for

certificates of public convenience and necessity authorizing the

construction and operation of facilities to provide service or to

abandon facilities or service under section 7 of the Natural Gas Act

(NGA),2 and amending the blanket certificate regulations

under Subpart F of Part 157. The Final Rule: (1) Conformed the existing

regulations with current practices and policies; (2) eliminated

ambiguities and obsolete language; (3) made the regulations more

germane and less cumbersome; and (4) reduced the existing reporting

burden by a total of 8,284 hours. Additionally, the Final Rule

consolidated and clarified the Commission's current practices

concerning the filing and reporting requirements associated with its

environmental review of pipeline construction projects under the

National Environmental Policy Act of 1969.3

---------------------------------------------------------------------------

\2\ 15 USC 717b.

\3\ 42 USC 4321-4370a.

---------------------------------------------------------------------------

The Commission received rehearing/clarification requests from 10

parties including the American Public Gas Association (APGA), CNG

Transmission Corporation (CNG), Columbia Gas Transmission Corporation

and Columbia Gulf Transmission Company (Columbia), El Paso Energy

Corporation (El Paso), Enron Interstate Pipelines (Enron), Great Lakes

Gas Transmission (Great Lakes), Indicated Shippers, Interstate Natural

Gas Association of America (INGAA), Process Gas Consumers Group, the

American Iron and Steel Institute, and the Georgia Industrial Group

(Process Gas), and Williston Gas Interstate Pipeline Company (Williston

Basin).

Indicated Shippers filed a motion to file an answer and an answer

to requests for rehearing. While our rules do not permit answers to

rehearing requests,4 we may, for good cause, waive a

rule.5 We find good cause to do so in this instance. To

achieve a complete and accurate record, we will accept Indicated

Shippers' answer.

---------------------------------------------------------------------------

\4\ See 18 CFR 385.213(a)(2).

\5\ 18 CFR 385.101(e).

---------------------------------------------------------------------------

III. Discussion

A. Section 2.55(a)--Auxiliary Facilities Constructed With Newly

Proposed Jurisdictional Facilities

Under section 2.55 of the regulations, the Commission exempts

auxiliary facilities, such as valves, drips, yard and station piping,

and cathodic protection equipment, from NGA section 7(c) authority.

Traditionally, section 2.55 limited the installation of auxiliary

facilities to facilities installed on an existing transmission system.

In the Final Rule, the Commission stated that it would include in the

exemption auxiliary facilities constructed in conjunction with new

transmission facilities. However, for auxiliary facilities on newly

authorized transmission facilities not yet in service, the Final Rule

stated that the Commission would require that the pipeline notify it 30

days prior to installing the auxiliary facilities.

Comments. On rehearing, El Paso and INGAA request that the

Commission clarify that the 30-day advance notice requirement is

satisfied if the auxiliary facilities are identified in a pipeline's

certificate or prior notice application. El Paso states that the

pipeline should not be required to make a separate filing to identify

such auxiliary facilities.

El Paso and INGAA also request that the Commission clarify that the

30-day advance notification requirement does not apply when such

facilities are being constructed on, or at the same time, as facilities

which are being constructed automatically under the Subpart F blanket

construction certificate. They contend that such notification would

essentially nullify the automatic authorization provision and delay

construction of such facilities.

Columbia questions what follows once the pipeline notifies the

Commission of the impending section 2.55(a) construction. It contends

that if the Commission intends to conduct a substantive review of the

facilities, it should have the necessary resources to conduct any

inquiry in a timely manner.

Commission Response. The Commission intends to review the filings

under section 2.55(a)(2) for compliance with the Commission's

environmental regulations. The Commission intended that the 30-day

notification requirement in section

[[Page 54524]]

2.55(a)(2)(ii) apply to case-specific projects which include an

Environmental Report as specified in section 380.12 of the Commission's

regulations or to prior notice projects under section 157.208. It does

not apply to projects constructed under the Part 157 automatic

authorization procedures. To clarify this in the regulations, we will

add the phrase ``except those authorized under the automatic

authorization procedures of Subpart F of Part 157 of this chapter'' to

section 2.55(a)(2)(ii).

We will also clarify that the 30-day notification requirement does

not apply if the auxiliary facilities are identified in the certificate

application. We believe that the use of the word ``or'' between

paragraphs (ii) and (iii) of paragraph 2.55(a)(2) precludes the

application of both to a given project and its related auxiliary

facilities. However, we will also modify the introductory paragraph to

paragraph 2.55(a)(2) to read, ``[o]ne of the following requirements

will apply to any specified auxiliary installation.''

B. Section 2.55(b)--Construction Area for Replacement Facilities in

Existing Right-of-Way

1. Existing, Unrelated Rights-of-Way

In the Final Rule, the Commission codified its current policy that

limits the construction area for replacement facilities to the

temporary work space used to construct the original facilities.

Comments. On rehearing, Great Lakes contends that the Commission

did not respond to its comments requesting authority to use its entire

existing right-of-way, including Commission-approved rights-of-way

unrelated to the construction of facilities being replaced. It claims

that any existing right-of-way that has already been disturbed for

pipeline construction, has been reviewed for archaeological concerns,

and for which the pipeline has obtained appropriate land rights should

be available for use. Great Lakes notes that the pipeline would be

required to obtain updated clearances for cultural resources and

threatened or endangered species prior to using such replacement

construction areas. It asserts that the Commission's concerns regarding

environmental assessments are not present when the pipeline uses an

existing right-of-way. It requests that the Commission explain why use

of unrelated, existing right-of-way is not appropriate when use of the

existing right-of-way approved for the facilities being replaced is

less safe, environmentally disadvantaged, or impractical.

Commission Response. The types of construction activities being

conducted under section 2.55 are replacements that should only involve

basic maintenance or repair to relatively minor facilities where the

Commission has determined that no significant impact to the environment

will occur. The Commission believes that the existing right-of-way that

was used to construct the original facilities should be sufficient for

these types of activities. Pipelines may use their blanket certificate

authority to perform projects involving more extensive work that would

need additional workspace, including the use of other unrelated rights-

of-way. This would allow for the required additional environmental

scrutiny. Therefore, those projects should be done under the pipeline's

blanket certificate.

As Great Lakes points out, there may be a need for updated

clearances. The Commission believes that use of the blanket process is

more appropriate in these situations since the replacement regulations

do not contain any such requirement. Accordingly, Great Lakes' request

that the Commission allow the use of any existing rights-of-way for

activities conducted under section 2.55 is denied.

2. Equivalent Designed Delivery Capacity

The Final Rule clarified that the phrase ``equivalent designed

delivery capacity'' used in the context of replacement storage wells

refers to both the daily deliverability and seasonal cyclic capacity.

Comments. CNG seeks further clarification that ``designed delivery

capacity'' refers to the capacity of the entire storage pool, not that

of each individual well. CNG states that operators manage the pool on

the basis of overall deliverability and that it is the deliverability

of the entire storage pool that is certificated, not each individual

well in the pool. According to CNG, the deliverability from individual

wells will fluctuate over time, and increasing the deliverability of an

individual well will not increase the certificated capacity of the

entire storage pool.

Commission Response. We agree with CNG that it is the

deliverability and capacity of a storage reservoir that is

certificated, not the capability of individual wells. We recognize that

the deliverability of an individual replacement well may differ from

the original well being replaced. However, as long as the replacement

well does not alter the underlying parameters of the storage field,

i.e., the certificated capacity, deliverability, or storage boundary,

and functions in a manner similar to the well it replaced, we will view

such a replacement well as having a substantially equivalent designed

delivery capacity as the facility it replaced.

C. Appendix A to Part 2--Guidance for Determining the Acceptable

Construction Area for Replacements

In the Final Rule, the Commission codified its current policy that

requires that replacement facilities must be placed in the existing

right-of-way. Appendix A to Part 2 delineates guidelines for the

pipeline to use to determine the acceptable construction area for

replacement facilities. Subpart (b) of the Appendix requires that the

temporary right-of-way (working side) be on the same side as the

original construction work area.

Comments. Williston Basin requests that the Commission clarify how

subpart (b) applies when there is no documentation as to which side was

used in constructing the original pipeline. It contends that it may not

always be possible for the pipeline to tell by visual inspection which

side was the original working side. Williston Basin suggests that it

would be appropriate for the Commission to state that, when the

original working side is unknown, the pipeline should make the working

side of any replacement activity the side that will have the lowest

impact on the environment.

Commission Response. The purpose of Appendix A is to provide

guidance for determining the appropriate workspace for replacement

facilities constructed under section 2.55 when the original

documentation is not available. In Appendix A, the Commission is

attempting to maximize the probability that the pipeline construction

footprint of the replacement activities will coincide with the

footprint of the original construction and that the nature of the

environmental impact will be the same.

As stated, the guidelines in paragraph (a) are to be used in the

absence of contradictory physical evidence. Any reasonable physical

evidence pointing to the likely location of the working side during the

initial construction can be used to estimate the size and location of

the original work space. For example, if the line to be replaced is a

loop adjacent (within about 25 feet) to another line, it may be assumed

that the working side was on the opposite side of the line to be

replaced. If there are trees or structures close to one side of the

pipeline to be replaced, and they predate the pipeline, then it is

unlikely that side was the working side.

[[Page 54525]]

However, we note that when visual inspection fails, i.e., if there

are no reasonable hints to the location of the working side, the

facilities cannot be constructed under section 2.55. They must be

constructed under the Subpart F of Part 157 blanket program to ensure

protection of the resources. The Part 157 regulations include criteria

for minimizing environmental impacts without relying on the company's

guess as to where the facilities should be constructed to have the

lowest impact on the environment.

D. Section 157.6--Applications; General Requirements

1. Electronic Filing Requirements

The Final Rule modified the existing electronic filing requirements

for certificate applications.

Comments. On rehearing, Enron states that section 157.6(a)(2) has

been revised to require that all applications and exhibits are to be

``submitted in electronic format as prescribed by the Commission.''

Enron is unsure as to whether the Commission is proposing substantive

changes to the current electronic reporting requirement or is placing a

general reference to electronic formats in the regulations in

anticipation of new or modified electronic formats that may be a result

of the proceeding in Docket No. PL98-1-000.6 Enron seeks

clarification that the Commission is not imposing new electronic filing

requirements as part of the Final Rule. INGAA raises similar concerns.

---------------------------------------------------------------------------

\6\ 63 FR 27532 (May 13, 1998).

---------------------------------------------------------------------------

Commission Response. The Final Rule does not impose any new

electronic filing requirements. The documents listed in section

157.6(a)(2) simply delineated the specific documents that previously

were included in the all encompassing phrase: ``[a]pplications,

amendments thereto, and all exhibits and other submissions required * *

* under this subpart'' in section 157.6(a)(1).

Additionally, on November 30, 1998, a Notice to Provide Additional

Guidance about the Revised Electronic Filing Requirements for

Certificate Applications was issued that explained the specific

electronic format requirements and reduced the electronic filing

requirements.7 These reduced electronic filing requirements

will be in effect pending the outcome of the proceeding in Docket No.

PL98-1-000.

---------------------------------------------------------------------------

\7\ Notice to Provide Additional Guidance About the Revised

Electronic Filing Requirements for Certificated Application, 80 FERC

para. 62,139 (1998).

---------------------------------------------------------------------------

2. Pricing Policy Statement

In the Final Rule in section 157.6 (b)(8) the Commission codified

certain filing requirements in accordance with the Pricing Policy

Statement For New and Existing Facilities Constructed By Interstate

Natural Gas Pipeline.8 On September 15, 1999, the Commission

issued a new statement of policy to provide the industry with guidance

as to how the Commission will evaluate proposals for certificating new

construction.9 On rehearing, we will make conforming

modifications to section 157.6(b)(8) to reflect the new policy

statement.

---------------------------------------------------------------------------

\8\ 71 FERC para. 61,241 (1995).

\9\ Certification of New Interstate Natural Gas Pipeline

Facilities, 88 FERC para. 61,227 (1999).

---------------------------------------------------------------------------

E. Section 157.8--Acceptance for Filing or Rejection of Applications

In the Final Rule, the Commission revised section 157.8 to provide

that the Director of OPR may reject an application within ten days of

filing if the application ``patently fails to comply with applicable

statutory requirements or with applicable Commission rules,

regulations, and orders.'' The ten day time frame is intended to

provide the Director the opportunity to make an initial finding that

the application contains the minimum information necessary for

providing public notice of the application and to begin preliminary

processing. As stated in the Final Rule, the Commission recognizes that

not all information, for example, certain environmental data, may be

available at the time of filing. However, we note that once the

application has been noticed, the applicants are required to file any

and all information necessary to complete their application. We wish to

clarify that this section does not limit the Director's ability to

subsequently reject the application after it has been noticed if the

applicant fails to provide any information needed to fully process that

application. Therefore, we will modify section 157.8 to state that the

Director may also reject an application after it has been noticed if it

does not conform to the requirements of Part 157.

F. Section 157.10--Interventions and Protests

1. Availability of Application

Section 157.10 of the Final Rule requires that complete copies of

the application must be available in each county in the project area

within three days of the filing of the application.

Comments. CNG contends that the application should not be made

available until three business days from the time the application is

issued a docket number and after a Commission notice is issued.

According to CNG, if the Commission were to reject the application

later than three days after it were filed, the entire project would

already be in the public domain, even though no project was then on

file with the Commission. CNG argues that the pipeline should not be

subjected to this risk of disclosure. Further, it could cause

substantial confusion and complication to have a copy of an application

available to the public before a docket number has been assigned and

the application has been accepted by the Commission. CNG contends that

if the application were rejected or modified to respond to Commission

comments, there could be multiple versions of a project in circulation.

In that event, CNG states that the benefit of providing a copy to the

public early to give time for a more thorough review would be

outweighed by the burden of reviewing a later, conflicting document.

Commission Response. We will modify Section 157.10 to require that

pipelines have complete copies of their applications available within

three business days of the date a filing is issued a docket number. We

will not, however, extend the time the application needs to be made

available to after the application is noticed. The Final Rule put

pipelines on notice that they must file substantially complete

applications or face the risk of rejection. It is incumbent upon the

pipeline to ensure that each application is complete and ready to be

noticed when it is filed to avoid the potential for rejection, the risk

of disclosure, and the possibility of multiple versions.

Further, we note that in the Final Rule in Docket No. RM98-17-000,

the Commission is requiring that pipelines notify all affected

landowners within three business days of receiving the docket number

for a filed application. The Commission believes that the application

should be available for those landowners to review when they receive

the notice that the application has been filed.

2. Voluminous/Difficult To Reproduce Material

In section 157.10, the Final Rule also provides that pipelines do

not have to serve voluminous or difficult to reproduce material, such

as copies of environmental information, on all parties in the

proceeding. However, the Final Rule does require that the pipelines

have copies of the material available for inspection in each county in

the project area within three business

[[Page 54526]]

days of filing the material with the Commission. It also requires that

the pipelines make copies of the material available to any party that

requests it within five business days of receiving a request for the

material.

Comments. Enron and INGAA seek rehearing of the requirement to

serve complete copies of applications, including voluminous or

difficult-to-reproduce materials, on individual parties that request

the information. Enron contends that the requirement to establish

public reference sites to provide access to complete copies of

applications is not an insignificant effort. According to Enron, this

effort is worthwhile only to the extent that it offsets the requirement

to produce voluminous or difficult-to-reproduce materials. However,

Enron questions the cost/benefit of this effort if parties may

nevertheless request individual copies. Enron requests that pipelines

only be required to serve a copy of the application, excluding

voluminous or difficult-to-reproduce materials. Enron suggests that

pipelines make the voluminous or difficult-to-reproduce materials

available on an Internet web site rather than be required to produce

hard copies of such material. Enron states that such materials will

also be available at the designated public locations. INGAA agrees.

Great Lakes also seeks clarification concerning the meaning of the

requirement to make electronic copies available in each county. It

requests that the Commission accept placement of the complete

application on the pipeline's Internet website as complying with the

requirement to keep electronic copies in each county.

Additionally, Great Lakes is concerned with the Commission's

requirement that voluminous materials be made available in each county

in the project area. Great Lakes contends that libraries and public

buildings may not be available in every county, may not have evening

and weekend hours, and that such places may not consent to or be able

to accommodate the public in this way. Great Lakes seeks clarification

as to whether any non-public buildings are acceptable as a central

location. It also seeks rehearing and a determination that flexible

hours of operation are not a requirement but a goal, because one

alternative, the County Clerk's office, would not offer evening and

weekend hours.

Commission Response. Upon reconsideration, we will modify section

157.10 and not require that the applicant serve a copy of the entire

voluminous or difficult-to-reproduce material when requested by a party

to the proceeding. However, we will require that if an individual party

requests information concerning that party's particular piece of

property that may be included in the voluminous and difficult to

reproduce material, the applicant should provide that particular

information to that party within 5 business days from the request. For

example, if a landowner requests a copy of the map that shows where the

pipeline will be going through that landowner's property, the applicant

should provide the landowner with a copy of the portion of the map that

includes that particular piece of property.

The Commission intends that pipeline applications be readily

accessible and available to all interested parties along the pipeline

route. We will not change our requirement that complete copies of

applications, including voluminous or difficult-to-reproduce materials

must be placed in publicly available places in each county along the

pipeline route. However, in light of the rehearing requests, we will

modify and further clarify that requirement.

First, the application can either be in paper or electronic format.

A pipeline does not have to provide both paper and electronic copies,

unless it desires to do so. However, it must provide a complete copy in

either one of the two formats. If the copy is in electronic format, any

party accessing such copy should be able to obtain a hard copy version

from the electronic format.

Second, we also believe that it is reasonable to allow pipelines to

establish an Internet web site on which to post its voluminous and

difficult-to-reproduce material, in addition to having such material

available at public sites along the project route. However, because not

everyone has access to the Internet, we will still require pipelines to

have complete copies available in each county along the pipeline route.

Finally, we will modify section 157.10 to allow the applicant more

flexibility in determining where the applications will be placed for

public viewing. The applicant should place copies of the complete

application, including the voluminous and difficult-to-reproduce

material, in central locations in each county with public access and

flexible hours. We expect the applicant will use its best judgement in

determining the best location to put the materials.

G. Section 157.202(b)(2)(i)--Eligible Facilities

1. Replacement of Mainline and Lateral Facilities

The Final Rule stated that replacing pipeline and compression

facilities must be done for sound engineering reasons and not for the

primary purpose of creating additional mainline capacity. The order

emphasized that such replacement facilities must be the closest

available size and horsepower rating to the facilities being replaced.

Comments. Columbia states that the requirement that the replacement

be the ``closest available size'' may be overly restrictive and go

beyond the Commission's intended goal. Columbia states that on older

portions of its system, it has inconsistently sized pipe in the same

area. For example, in storage fields, Columbia may have a several mile

pipeline comprised of 4-,

6-, 8- and 10-inch pipeline in alternating segments. Columbia states

that when one of those segments need to be replaced, sound engineering

practice dictates that a single size pipe be selected for all

replacements on that line. It claims that this would permit more

efficient pipeline maintenance by use of smart pig technology through

longer segments. Columbia also asserts that it would also reduce the

need for installing multiple pig launchers and receivers. To that end,

Columbia states that it might choose to replace a 4-inch segment with

8-inch line, solely for the purpose of achieving maintenance related

uniformity, even though 4- and/or 6-inch pipe is available. Columbia is

concerned that such a replacement might not qualify under the blanket

certificate regulations. Columbia requests that the Commission refine

the expansion of eligible facilities so that replacements may be done

for sound engineering reasons without the restriction that the

replacement must be the closest available size to the facility being

replaced.

Conversely, Indicated Shippers request that the Commission modify

the Final Rule to eliminate automatic authorization of replacement

facilities that can increase mainline capacity. Indicated Shippers

contend that pipelines will use this authority to circumvent the

spending caps on blanket authorization. Indicated Shippers claim that

the Commission's statement in the Final Rule that pipelines should not

segment a project to circumvent the automatic or prior notice spending

limits, acknowledges that pipelines will have an incentive to do so but

fails to impose adequate safeguards. They claim that any

[[Page 54527]]

challenge to whether facilities were constructed for sound engineering

purposes would result in a battle of expert engineers and professional

judgements that may differ substantially. Further, they argue that a

shipper's ability to file a complaint against a pipeline for an

apparent attempt to circumvent the spending caps would be inherently

limited because the shipper is burdened with assembling the necessary

facts to support the complaint and that the pipeline will have

exclusive possession of the relevant information.

Finally, Indicated Shippers assert that the Commission's suggestion

that the parties could challenge an improper mainline expansion in a

future rate case ignores the elimination of the three-year rate filing

requirement in Order No. 636. As such, the pipelines have no legal

requirement to file a rate case by any date certain.

Commission Response. We underscore our policy that the blanket

certificate regulations cannot be used in a manner that will alter

mainline capacity in any substantive manner. Thus, we require that

replacements be done for sound engineering reasons and not for the

primary purpose of creating additional mainline capacity. We intend

that virtually the same criteria applicable under section 2.55(b) apply

to replacements under the blanket certificate. Namely, the existing

facilities are or will soon become physically deteriorated or obsolete,

and the replacement will not result in a reduction or abandonment of

service through the facilities. While replacements under section

2.55(b) must also have a substantially equivalent designed delivery

capacity as the facilities being replaced, we recognize that

replacements done under the blanket certificate may result in an

incidental increase in mainline capacity because the replacement

facilities do not exactly match the original. However, pipelines are

still required to design the replacements so that they have a

substantially equivalent designed delivery capacity and are prohibited

from using the blanket certificate to create new point to point

mainline capacity via the replacement procedure. Thus, there must be a

physical need to replace facilities.

We emphasized in the Final Order that replacements must be the

closest available size and horsepower rating to the facilities being

replaced. The situation described by Columbia, to the extent it is

required for sound engineering reasons, i.e., to allow continuous

pigging and minimize the number of launchers and receivers, could

qualify for blanket treatment. However, we envision limited

applicability for such replacements. As described by Columbia, these

type replacements may pertain to older, inconsistently sized sections,

such as in storage fields or producing areas. We do not intend for

pipelines to use this rationale to replace long sections of mainline

pipeline under the blanket certificate under the guise of ``efficient

pipeline maintenance.'' We reiterate that the pipeline must be able to

support its prudent decision to use any replacement facility that is

not the closest available size and/or horsepower rating to the facility

being replaced.

Indicated Shippers reiterate its opposition to automatic

authorization of facilities that could increase mainline capacity. As

stated in the Final Rule, replacement facilities must not create new,

usable capacity that a pipeline would otherwise need to certificate in

a separate section 7(c) proceeding. Pipelines are reminded that the

procedures for constructing replacement facilities under the blanket

certificate do not allow pipelines to circumvent the section 7(c)

authority needed to construct projects for new mainline capacity.

Additionally, section 157.208 specifically prohibits pipelines from

segmenting projects to circumvent the cost limits under the blanket

certificate.

The Commission intends to monitor the effect the newly granted

automatic authorizations have on the workings of the industry and may

consider whether further changes are necessary. In the interim, if

Indicated Shippers believe that a pipeline is violating or deliberately

circumventing the Commission's regulations, it should bring the alleged

violation to the Commission's attention by filing a complaint. Finally,

although the three-year filing requirement was eliminated by Order No.

636, whenever a rate case is filed, the pipeline must include the costs

of new plant. At that point, any such costs associated with the alleged

improper mainline expansion would be open to challenge.

2. Minor Storage Operations

In the Final Rule the Commission modified section

157.202(b)(2)(ii)(D) to allow minor changes to storage field

operations, but did not allow the drilling of storage wells as eligible

facilities.

Comments. CNG contends that in the NOPR the Commission proposed to

exclude any facility required to test, develop, or utilize an

underground storage field as an eligible facility under the blanket

certificate. According to CNG, the Commission intended to allow minor

changes to field operations and facilities, such as rerouting or

changing storage field lines. CNG argues, however, that the practical

result of the change in the Final Rule was to prevent minor

modifications of facilities under the blanket certificate.

CNG also contends that while the Final Rule states that wells must

still be drilled under section 157.215, it is not clear that this

section applies to existing storage pools, rather than just new storage

pools. CNG questions whether drilling a new storage well in an existing

pool is permitted under this section.

CNG seeks rehearing of this issue and requests that the Commission

implement its intent to provide for minor changes to field operations

and facilities, by changing the ``or'' back to an ``and,'' and clarify

that new wells can be drilled in existing storage pools under section

157.215.

Commission Response. Under the Commission's regulations, pipelines

currently can use their blanket certificate to construct and operate

facilities to test and develop underground storage reservoirs for the

possible storage of gas. However, such facilities are excluded from the

definition of eligible facilities and must be constructed separately

under section 157.215. Once such a reservoir is tested and developed,

pipelines must obtain separate authority under section 7(c) in order to

utilize a storage reservoir to render service. We are not altering that

authority here.

In modifying section 157.202(b)(2)(ii)(D), the Commission intended

to continue to exclude facilities required to test and develop storage

fields from the definition of eligible facilities. We also intend to

exclude wells needed to utilize an underground storage field. However,

the regulation will allow pipelines to make minor changes to field

operations and facilities, such as rerouting, changing, or adding

storage field lines. We intend to allow pipelines to make modifications

that will improve the operation and/or flexibility of a storage field,

without altering the parameters of the underlying certificate

authority.

As stated in the Final Rule, we do not intend for the change in

this section to allow pipelines to drill additional injection/

withdrawal wells under the blanket certificate because such wells may

inherently alter the deliverability, capacity, or boundary of a

reservoir. Drilling new injection/withdrawal wells in existing storage

pools requires separate section 7(c) authorization. We will revise

section 157.202(b)(2)(ii)(D) to clarify that it applies only to the

testing

[[Page 54528]]

or developing of underground storage fields.

H. Section 157.202(b)(12)--Interconnecting Point

In the Final Rule, the Commission limited interconnecting points to

the tap, metering, metering and regulating (M&R) facilities, and minor

related piping. The Commission found that any related pipeline

connecting two interstate pipelines would function as a mainline

facility and thus, not qualify as an eligible facility.

Comments. El Paso states that the practical effect of the

Commission's decision prevents ``long'' segments of interconnecting

pipeline between two transporters of natural gas from being constructed

under the blanket certificate. El Paso, Enron, Great Lakes, INGAA, and

Williston Basin all believe that interconnecting segments should be

included along with the tap and meter as eligible facilities.

El Paso argues that there is no functional difference between an

``interconnecting point'' that requires ten feet of interconnecting

pipeline and a point that requires five miles of pipeline. According to

El Paso, however, the Commission will allow the ten foot segment to be

constructed as an eligible facility (as minor piping) but not the five

mile segment. El Paso contends that both short and long interconnecting

segments are capable of receiving/delivering the same level of volumes,

provide the same flexibility to permit backhaul arrangements, could be

capable of accommodating bi-directional gas flows, and would have the

same effect on gas flows on the two interconnecting pipelines. Under

these circumstances, there is no legitimate ``operational'' reason to

differentiate between a short and long interconnecting segment. Enron

and INGAA agree that interconnecting pipeline of various lengths share

these operating characteristics.

Enron and INGAA contend that interconnecting pipeline segments will

facilitate interconnection of the pipeline grid. El Paso, however,

argues that the Commission's goal of fostering development of a

national pipeline grid is hampered without including long

interconnecting segments as eligible facilities.

El Paso and INGAA state that the spending limits for blanket

certificate construction will effectively limit the length of any

interconnecting pipeline. Thus, they argue, constructing long

interconnecting pipeline cannot impact ratepayers to a greater extent

than construction of any other eligible facility.

El Paso further argues that the Commission does not support its

conclusion that a ``long'' interconnecting pipeline between two

transporters constitutes mainline, not supply or delivery lateral.

INGAA contends that interconnecting pipeline does not function

differently than a lateral line; both facilities are designed to

receive and/or deliver gas supplies. El Paso states that the only

difference between a lateral and an interconnecting pipeline is that a

lateral generally connects a pipeline to a production field, gathering

system or customer delivery point, whereas interconnecting pipeline

connects a pipeline to another pipeline. According to El Paso, that

difference cannot serve as a basis to find that ``long''

interconnecting pipeline performs a mainline function, while

interconnecting points, including minor related pipeline, are eligible

facilities.

Commission Response. In KN Interstate Gas Transmission Company (KN

Interstate),10 we found that a 2-mile pipeline was not an

interconnecting point. The order clarified that ``interconnecting

point'' under section 157.208(a) specifically refers to taps, meters,

M&R facilities and minor piping. We adopted that definition in the

Final Rule. However, upon reconsideration, we will grant rehearing on

this issue. We will allow interconnecting pipelines between Part 284

transporters to be constructed as eligible facilities, subject to the

cost limits under the blanket certificate. We agree that such

facilities do not operate as mainline facilities or extensions of

mainline facilities, because they do not alter the mainline

capacity.11 We will view interconnecting pipeline segments

in the same manner that we view lateral lines--both serve to receive

and/or deliver gas supplies, and both can be constructed automatically,

subject to the cost limits under section 157.208. While we stated in KN

Interstate that a 2-mile pipeline was not an interconnecting point, we

now believe that interconnecting pipelines between Part 284

transporters should be covered under the blanket certificate because

they display more characteristics in common with lateral lines than

with mainlines. Thus, we will change the definition in section

157.202(b)(2)(ii) to reference interconnecting facilities, instead of

interconnecting points. We will also change the definition in section

157.202(b)(12) to encompass both the interconnecting point facilities

and the related pipeline segment necessary to interconnect two Part 284

transporters. Since the length of such segments will be governed by the

cost limits of the blanket certificate, these facilities will have a

minimal impact on a certificate holder's system. Upon reconsideration,

we believe that allowing interconnecting pipeline segments is

consistent with the intent of the blanket certificate, which authorizes

pipelines to construct routine facilities that have relatively little

impact on ratepayers or pipeline operations.

---------------------------------------------------------------------------

\10\ 83 FERC para. 61,305 (1998).

\11\ However, to the extent that any interconnecting facility

will alter mainline capacity of either Part 284 transporter, such

facility will not be covered under the blanket certificate.

---------------------------------------------------------------------------

I. Section 157.205(g)--Withdrawal or Dismissal of Protest

The Final Rule authorized the Director of OPR to dismiss any

protest to a prior notice filing which does not raise a substantive

issue and fails to provide any specific reason or rationale for the

objection.

Comments. APGA states that the Commission has not documented the

number of ``no issue'' protests that are the basis for the change in

the regulation. APGA surmises that there are no protests to bypasses

that fail to raise substantive issues. However, APGA contends that it

is the Commission's practice to refuse requests for discovery when a

protested prior notice is converted to a section 7(c) application.

According to APGA, the Commission concluded in a recent order that the

bypassed distributor that protested the application had ``not proffered

any evidence indicating that unfair competition or undue discrimination

has occurred,'' while simultaneously denying the Local Distribution

Company (LDC) the opportunity to seek information from the pipeline

that might prove such undue discrimination.12 APGA argues

that if an LDC cannot obtain details of the bypass ``deal,'' then it

stands to reason that it will not prove its case to the satisfaction of

the Commission. APGA fears that in such a situation the Director of OPR

could conclude that distributors that do not prove their case will also

fail to ``raise a substantive issue and fail to provide any specific

detailed reason or rationale for its objection.'' Thus, LDCs would be

denied not only due process rights to obtain information to make a

case, but they would be denied due process completely by the summary

rejection of a protest to a bypass application ten days after it is

filed. APGA argues that the absence of process will rob the Commission

of its opportunity to detect

[[Page 54529]]

unfair competition because industry participants, particularly LDCs,

will not be able to bring facts to its attention.

---------------------------------------------------------------------------

\12\ See Transcontinental Gas Pipe Line Corp., 87 FERC para.

61,136 (1999).

---------------------------------------------------------------------------

Alternatively, APGA requests that the Commission clarify the

relationship among any dismissal by the Director of OPR, conversion to

a section 7 proceeding, and the 30-day reconciliation period. APGA

contends that the Commission would enforce a reconciliation or

settlement period, yet this period would appear to come after the

dismissal of the protest. Therefore, APGA contends that it is unlikely

that there can be any settlement on a non-existent protest. APGA states

that the purpose of the reconciliation period is to obtain the

withdrawal of the protest; the end-user and the pipeline that seek to

bypass the LDC need not talk to the LDC if the LDC's protest has been

dismissed.

El Paso and INGAA state that section 157.205(g) provides that when

a protest is dismissed by the Director of OPR, the notice requirements

will not be fulfilled until the earlier of: (1) 30 days after the

deadline for filing protests and interventions (referred to as the

``waiting period''); or (2) the dismissed protesting party notifies the

Commission that its concerns have been resolved.

Both El Paso and INGAA believe that imposing a ``waiting period''

after a protest is dismissed unfairly penalizes pipelines and rewards

protesting parties which fail to raise substantive issues or provide

adequate support for their claims. They argue that if a protest is

dismissed, a pipeline should not have to wait the additional 30 days

before it can commence construction. They further argue that this

section rewards protestors that file frivolous protests, which is

inconsistent with the intent of the section. They also claim that this

treatment is inconsistent with the Commission's treatment of withdrawn

protests under the blanket certificate. El Paso states that prior

notice authorization becomes effective on the day after all protests

are withdrawn. El Paso believes that there is no reason to treat a

dismissed protest differently than a withdrawn protest.

El Paso, INGAA, and Williston Basin contend that if the Director of

OPR dismisses a protest within the 45-day notice period, and there are

no other protests, the proposed construction should be deemed

authorized consistent with the prior notice procedures, i.e., on the

day after the 45-day protest/intervention period. If the Director of

OPR dismisses a protest after the 45-day protest/intervention period

has passed, and there are no other protests, El Paso and INGAA contend

that the proposed construction should be deemed authorized on the day

after the protest is rejected.

Indicated Shippers disagree with El Paso's position that the

Commission should not require a pipeline to wait up to 30 days beyond

the protest deadline if the Director of OPR dismisses a protest for

failure to raise a substantive issue. Indicated Shippers state that a

protestor may appeal the dismissal of its protest to the Commission.

Thus, the additional 30 days that the Commission would add to the end

of the 45-day protest period does not constitute ``undue delay.''

Commission Response. First, we find the APGA's concerns that it

will be denied due process unfounded. As we stated in the Final Rule, a

protesting party must substantiate its allegation, not necessarily

prove that the allegation is true. As long as the protesting party

provides some substantiating evidence, the protest will not be

dismissed. Further, the party still has its right to request rehearing

and have the dismissal reviewed by the Commission, and subsequently by

the court of appeals.

Second, we disagree that there is no reason to treat a dismissed

protest differently than a withdrawn protest. The 30-day period is to

allow appeal of the Director of OPR's action to the Commission, which

is required under sections 375.301 and 385.1902 (Rule 1902) of the

regulations.13 While a frivolous protest may delay

construction beyond the 45-day prior notice protest period to allow for

the required right to file for rehearing, the application does not roll

over to a section 7(c), which potentially could result in substantial

delays for the applicant. Thus, while construction may be delayed in

such a case, it only will be delayed for a minimal period.

---------------------------------------------------------------------------

\13\ Section 375.301 states that ``[A]ny action by a staff

official under the authority of this subpart may be appealed to the

Commission in accordance with Section 385.1902 of this chapter.''

---------------------------------------------------------------------------

Finally, we believe the pipeline still has an incentive to

reconcile or settle with the party with the dismissed protest. For

example, the Commission may grant the request for rehearing, thereby

reinstating the protest and possibly converting the prior notice

proceeding to a section 7(c). Thus, the pipeline may want to resolve

the protesting party's concerns before the rehearing period has run in

order to commence construction sooner.

J. Section 157.206(b)(5)--Compressor Station Noise

In the Final Rule, the Commission updated section 157.206(b)(5) to

bring it into line with current usage concerning limitations on

compressor station noise levels. Specifically, it requires that the

noise attributable to any new compressor stations, compression added to

an existing station, or any modification, upgrade or update of an

existing station, must not exceed a day-night level (Ldn) of 55 dBA at

any pre-existing noise-sensitive area (such as schools, hospitals, or

residences).

Comments. On rehearing, Columbia contends that the modification

would inappropriately include potential noise effects of any change to

an existing compressor station, not just from compressor unit

modifications. It claims that nothing has been presented in this

proceeding to suggest that there is a noise concern for other aspects

of compressor station operations beyond the compressor units

themselves.

Commission Response. In fact, it was the Commission's intent to

include any potential new noise source or any change in the existing

station that might have an effect on the noise generated by the station

and be heard at nearby noise-sensitive areas. There are many potential

modifications that could do this, including: additions or changes to

the cooling fans; modification to suction or discharge piping; addition

or modification of the gas scrubbers; changes to metering facilities

(including purely operational changes); and removal of structures or

other screening. Likewise, there is a wide range of modifications that

cannot reasonably be expected to have any effect on noise (e.g.,

utility, administration, or maintenance structures or their contents,

and communications equipment). In these cases, surveys would rarely be

required. The companies should be able to distinguish between the

different types of modifications. However, there may be occasions where

a company would want to do a noise survey even if experience indicates

there is little probability for an effect. For example, there may be

instances where a complaint or an inspection results in a need for such

surveys. In these instances, which we believe will be rare, the surveys

would be done after the change was made.

While this same wording is used in section 380.12(k), as long as

the application specifies that the modification (not new or changed

compressor units) would have no noise impact, it will be up to the

Commission's staff to determine if a noise analysis is needed. We

emphasize, however, that noise analyses are always needed for new or

changed compressor units.

[[Page 54530]]

K. Section 157.206(c)--Commencement

The Final Rule amended the regulations to allow for facilities to

be completed ``and made available for service'' instead of ``in actual

operation'' within one year of authorization. The Final Rule also

provides that a certificate holder may apply to the Director of OPR for

an extension of the one year deadline ``due to construction delays.''

Comments. El Paso and INGAA argue that the Commission should delete

the phrase ``due to construction delays'' and return to its practice of

permitting pipelines to seek an extension of the deadline for any

reason. They state that extensions may be necessary and appropriate for

reasons other than construction delays. El Paso offers, for example, a

situation where a pipeline proposes to construct a delivery lateral to

serve a new power plant which is not expected to be placed into service

for a couple of years. There, a plant owner may need to ensure that all

regulatory authorizations are in place before it can obtain the

financing and contracts necessary to commence construction of the

plant. In such a situation, it contends that a pipeline may need to

seek prior notice approval more than a year in advance, while not

actually constructing facilities until the plant is ready to go on

line. Thus, it argues the pipeline would need to request an extension

of the one year deadline. El Paso states that if the Commission does

not revise section 157.206(c), pipelines face two undesirable

alternatives in the future: (1) Construct facilities far in advance of

the end-user's projected service date; or (2) file section 7(c)

applications for facilities which otherwise could be constructed under

the blanket certificate.

Commission Response. The phrase ``construction delays'' was used to

differentiate between pipeline delays and delays attributable to a

shipper/end-user. We intend for this section to encompass situations

such as that described by El Paso. However, in order to clarify this

intent, we will remove the phrase ``due to construction delays.''

Further, the next to last sentence in section 157.206(c) is modified to

read: ``The certificate holder may apply to the Director of the Office

of Pipeline Regulation for an extension of this deadline.''

L. Section 157.208(c)(9)--Prior Notice

In the Final Rule, the Commission required that a copy of

consultations for the Endangered Species Act, the National Historic

Preservation Act, and the Coastal Zone Management Act be included in

all prior notice filings.

Comments. On rehearing, INGAA, Columbia and Williston Basin state

that the Commission should allow the pipeline to submit the clearances

during the 45-day notice period. INGAA asserts that it is current

industry practice for pipelines to file a prior notice application

prior to receipt of final clearances but with a statement that the

pipeline anticipates the clearance to be submitted in the near future.

It contends that the Commission did not cite any ongoing industry-wide

abuse of the process or environmental harm which has resulted from the

current practice that would justify a change. INGAA claims that there

are significant efficiencies in beginning the prior notice process

while the pipeline is waiting to hear back from the agencies for their

final agreements.

INGAA proposes that the Commission revise section 157.208(c)(9) to

permit a pipeline to file with its prior notice filing: (1) The

requests for clearances that have been sent to the various agencies;

and (2) a commitment that the final agreements will be in place prior

to the end of the 45-day notice period. It also suggests that the

application should automatically be deemed protested on the forty-fifth

day if the clearances are not filed within 30-days of the prior notice

being filed.

Similarly, Columbia claims that ``the benefit of permitting the

filing of a prior notice application when clearances are not in hand

but soon anticipated is obvious.'' 14 It contends that

although a portion of the time required to obtain the clearances will

run concurrently, it should not impede the Commission's ability to

review the application, nor does it create any risk that the

construction might begin without necessary clearance.

---------------------------------------------------------------------------

\14\ See Columbia's request for rehearing, at 5.

---------------------------------------------------------------------------

Commission Response. We will deny rehearing on this issue. One of

the purposes of the Final Rule is to make changes in the Commission's

regulations that would streamline the certificate process. Incomplete

information at the time applications are filed only fosters

inefficiencies and additional expenditures of Commission resources.

INGAA's claim that it is current industry practice to file the

prior notice prior to receipt of the agency agreements is overly broad

`` a substantial number of pipelines file this information with the

prior notice. When clearances are not filed with the application, it

requires that the Commission's staff expend effort in keeping track of

the status of the filing and then file a protest if the material is not

forthcoming. INGAA's proposed compromise, as well as the baseline

suggestion, introduces an unnecessary level of complexity and

bookkeeping. In addition, in the case of the compromise solution, the

company is setting itself up for an automatic protest, more paperwork,

and delay that would not be necessary if the prior notice filing is

complete when initially filed.

M. Section 157.208(f)(2)--Maximum Allowable Pressure

The Final Rule modified section 157.208(f)(2) to permit pipelines

to follow prior notice procedures in order to increase the Maximum

Allowable Operating Pressure (MAOP) of laterals constructed under

individual section 7(c) authority.

Comments. Indicated Shippers state that the Commission appears to

have adopted this proposal based on considerations pertinent to

delivery laterals. However, Indicated Shippers contend that MAOP

increases have been a basis for concern in recent certificate cases

involving supply area facilities, in which producers of ``older''

reserves faced the prospect of shut-in of lower-pressure production as

``new'' higher-pressure production is attached to a pipeline's system.

Indicated Shippers state that the Commission must modify the Final Rule

to prohibit pipelines from increasing the MAOP of supply area laterals

under the blanket certificate procedures. Instead, they argue that all

MAOP increases involving supply area laterals should be authorized

under Subpart A of Part 157, to provide potentially adversely affected

parties a meaningful opportunity to present their concerns in advance

of authorization.

Commission Response. In the Final Rule, the Commission intended for

supply area facilities to be treated in the same manner as delivery

area facilities. In order to clarify this, we will modify section

157.208(f)(2) to recognize that changes in the MAOP of both supply and

delivery area laterals are subject to the prior notice procedures under

section 157.205. In the Final Rule, we also recognized that there could

be potentially detrimental effects on receipt area facilities.

Therefore, we subjected this type of construction to the prior notice

procedures and denied a request to allow MAOP increases to be

implemented automatically. Under the prior notice procedures, all

affected parties will have a meaningful opportunity to present their

concerns and/or protest any proposed change in the MAOP of any lateral

facilities.

[[Page 54531]]

N. Section 157.211--Delivery Points

The Final Rule revised section 157.211 to provide for automatic and

prior notice authorization to acquire, replace, modify, or construct

delivery points. In the Final Rule, the Commission required that all

delivery points constructed to provide service for an end-user

currently being served by an LDC were subject to the Commission's prior

notice procedures.

1. CD Reduction

Comments. APGA contends that the Commission erred by failing to

change its policy on contract demand reduction relief in the event of

bypass. APGA argues that the Commission should reform its bypass

practices and policies. According to APGA, the Commission had not

provided CD reduction relief because it demands that an LDC present

evidence of a written service contract between the LDC and the bypassed

customer. AGPA argues that a contract is not the only way in which to

demonstrate that a nexus exists between the LDC's contract demand on

the bypassing pipeline and the LDC's service to the end-user. According

to APGA, evidence of a history of service rendered to the end-user by

the LDC is equally valid.

Commission Response. As stated in the Final Rule, the Commission

determines if CD reductions are appropriate on a case-by-case basis

depending on the particular facts and circumstances in each

case.15 The Commission does not believe it is necessary to

codify its bypass and CD reduction policies in its regulations. Nor

does it believe it is appropriate to make any changes to that policy in

the context of this rulemaking proceeding. Any challenges to the

Commission's existing policies should be made in proceedings where the

issues are raised.

---------------------------------------------------------------------------

\15\ See, e.g., Transcontinental Gas Pipe Line Corporation, 84

FERC para. 61,160 (1998), order on reh'g, 87 FERC para. 61,136

(1999).

---------------------------------------------------------------------------

2. Prior Notice for Bypass Facilities

Comments. Process Gas contends that the Commission's ruling that

the contract must expire before the new delivery point is constructed

in order not to constitute bypass creates practical problems with

respect to timing of a service change and the strong possibility the

gas transportation service to the end user could be interrupted during

the transition to the new supply arrangement. Process Gas requests

rehearing in order to prevent such interruptions. It contends that the

Commission should allow construction of the delivery point as long as

deliveries through the new delivery point await expiration of the

user's previous contract with its LDC.

Similarly, Great Lakes contends that the Commission's definition of

bypass fails to recognize that the pipeline generally can time the

construction of its facilities to be in-service contemporaneously with

the termination date of the LDC's service. It claims that the gap in

service provides a disincentive for customers of LDCs to look for the

most economical supply/transportation.

Great Lakes contends that under the Commission's bypass policy, it

is engaging in speculation as to the LDC's market by protecting the LDC

from the forces of competition and creating a gap in service for any

LDC customer desiring to use a more cost-effective combination of

supply and transportation. Great Lakes recommends that the Commission

not require a prior notice filing unless both: (1) the pipeline's

service to the current LDC customer will take the place of the service

provided by the LDC; and (2) the effective date of the pipeline's

service is prior to the termination date of the LDC's contract with the

same end-user. It states that, if both of the prongs are not met, the

Commission should only require that the pipeline provide advance notice

to the LDC of its intent to construct facilities.

Additionally, Great Lakes and Process Gas contend that the

Commission should allow automatic authorization for the construction of

delivery points when an end user served by an LDC is constructing a new

facility or plant. Process Gas argues that the automatic authorization

should apply to new facilities at least as long as those facilities are

not expressly covered by an existing contract between the end user and

the LDC serving the area. It states that an end user should not be

subject to the expense and delays of protests and prior notice

procedures simply because it currently receives LDC service for other

existing facilities in the LDC's service territory.

Commission Response. As stated in the Final Rule, the Commission

believes that an LDC should have notice before facilities that could

potentially create a bypass of its service area are constructed. This

gives the LDC an opportunity to negotiate and compete with the pipeline

for the end user's business. We do not believe that this necessarily

protects the LDC from competition or creates a problem with a gap in

service. The end user knows the expiration date of the existing

contract well in advance. Similarly, the planning and construction of a

new plant or facilities is not an isolated incident that is decided on

the spur of the moment. The end users and the pipeline have sufficient

notice to plan accordingly for the possibility that there may be a

delay because of the prior notice procedures. The pipeline need not

wait until the expiration of the existing contract before filing a

prior notice proceeding. Therefore, being subject to the prior notice

procedures need not necessarily delay the ultimate construction of the

new delivery point.

O. Section 157.216--Automatic Abandonment

1. Automatic Authorization

The Final Rule allowed a pipeline to automatically abandon a

receipt point which had not been used within a twelve-month period if

the point is no longer covered under a firm contract.

Comments. Enron requests that the Commission clarify that the

availability of a point as an alternate delivery point does not

preclude automatic abandonment under the new requirements, provided the

point has not been used for a period of one year prior to the effective

date of the proposed abandonment. INGAA requests clarification that a

pipeline should be able to automatically abandon a receipt or delivery

point so long as the point is no longer covered under a firm contract

as a primary point--even if the point is listed or has been available

as an alternative point. INGAA contends that this is consistent with

the Commission's intent since many pipeline shippers designate all or

many points as alternatives to their primary points. INGAA argues that

if this clarification is not granted, pipelines will be unable to

abandon a point if a shipper has designated all points as alternatives

to their primary points on their contract. Williston Basin raises a

similar concern.

Indicated Shippers argue that the amendments adopted by the

Commission provide pipelines with considerable discretion to abuse

market power and limit competition. Indicated Shippers contend that the

Commission erred in permitting automatic abandonment of any supply area

facility. Additionally, they claim that the Commission erred in

refusing to require that pipelines obtain consent of upstream supply

parties in order to abandon supply area facilities.

According to Indicated Shippers, the Commission must support pre-

granted abandonment approvals with appropriate findings that existing

market conditions and regulatory structures protect customers from

[[Page 54532]]

pipeline market power. Indicated Shippers contend that pipelines will

strand supply if it is in their economic interest to do so, regardless

of what would be best for supply area competition. Indicated Shippers

point out that contrary to the Commission's statement that upstream

suppliers have contract agreements with shippers and that they should

seek the appropriate remedy from the shipper, suppliers have

Operational Balancing Agreement (OBA) and pooling agreements with the

pipelines. They contend that allowing abandonment of pipeline supply

facilities based solely on the non-opposition from shippers may not

adequately protect against premature abandonment of those facilities.

Indicated Shippers contend that the Commission's abandonment rules must

provide adequate procedures to ensure that upstream suppliers and other

parties have a meaningful opportunity to present their views and

supporting information before a pipeline abandons a supply area

facility. They also claim that the Commission has failed to justify the

elimination of the supplier's right to protest in a prior notice filing

to show that the facility will provide a meaningful level of service in

the foreseeable future. The Commission must provide sufficient

procedural safeguards to ensure that before a pipeline may abandon

jurisdictional facilities or services, the public interest is protected

through adequate safeguards against the pipeline's exercise of market

power.

Commission Response. The Commission sees no reason to differentiate

between primary and alternate firm receipt points. We do not intend to

allow automatic abandonment for primary and/or alternate points used

for firm service under effective contracts, because parties paying

demand charges should retain the availability of those points. However,

if firm primary or alternate receipt points are no longer under a firm

contract and have not been used in the prior year, such points would be

covered by the automatic authority under section 157.216(a)(1). If firm

primary or alternate receipt points were in use during the last 12

months, a pipeline can obtain consent of its customers and use the

automatic provision under section 157.216(a)(2) to abandon such

facilities. If a pipeline cannot obtain consent, it must use the prior

notice procedures to abandon such facilities.

As to Indicated Shippers' argument, pipelines cannot unilaterally

abandon a receipt point which is under a firm contract or that was used

for firm or interruptible service during the past 12 months. While

there may be many reasons a receipt point goes unused for some period

of time, pipelines should not be required to keep that point available

indefinitely in the event a supplier and/or their customers determine

they may need it at some later date. Suppliers must rely on their

underlying contractual arrangements for remedies. We agree that supply

area parties do enter into OBAs and pooling agreements with the

pipeline and not the shipper, but these are balancing agreements only.

The supply area parties enter into contracts for the sale of gas to

shippers who contract with the pipeline for transportation. Thus,

shippers such as LDCs and end-users are contractually committed to the

suppliers for their required gas supply and to the pipeline for the

necessary transportation capacity.

It is to the supply contract with pipeline shippers that these

parties must look for a remedy if a supply area receipt point is

proposed to be abandoned by a pipeline. These agreements may cover

multiple receipt points and a shipper may ultimately decide that it no

longer needs service from a particular supply area facility because its

needs have changed, alternative transportation options exist, or its

supply contract expires or terminates. The point is, supply area

parties should be aware of the market area situation affecting both the

shippers purchasing their gas and themselves. If a facility is in use

by firm or interruptible shippers, pipelines cannot abandon the

facility without shipper consent. If the shippers consent, the question

revolves around the status of the shipper-supplier contract. If a

shipper agrees to the abandonment of a receipt facility while it is

still contractually committed to a supplier, the supplier would seek

remedy under its contract with the shipper.

In the Final Rule, we required pipelines to make a prior notice

filing in order to abandon delivery facilities which were in use during

the preceding 12 months. The order stated that delivery points are not

eligible facilities because of potential bypass situations and are not

covered by section 157.216(b)(2). We continue to believe that prior

notice is necessary for the construction of delivery points that

involve bypass. However, once such delivery facilities are constructed,

bypass is no longer relevant. Thus, it should not be a factor when the

time comes to abandon the delivery facilities.

We believe that delivery facilities which have been in use during

the preceding 12 months should be eligible for automatic abandonment

under section 157.216(a)(2), subject to the pipeline's obtaining the

written consent of the customers served through such facilities.

Therefore, we will modify section 157.216(a)(2) accordingly.

2. Prior Notice Authorization

Comments. INGAA states that section 157.216(b)(1) provides that a

pipeline can abandon any receipt or delivery point if the existing

customers consent. INGAA contends that the Commission should strike the

reference to receipt point here because it has already clarified that

receipt points are eligible for automatic authorization under section

157.216(a)(2) where customer consent has been received.

Indicated Shippers request that the Commission clarify that

pipelines must use the prior notice procedures to abandon receipt

points and related facilities that exceed the automatic project cost

limit. Indicated Shippers take issue with INGAA's request that the

Commission delete reference to receipt points in section 157.216(b)(1)

because receipt points are eligible for automatic abandonment under

section 157.216(a)(2).

According to Indicated Shippers, INGAA assumes that all receipt

points qualify under section 157.216(a)(2), which requires that the

facility must have been installed under the automatic construction

authority of, and met the cost limitations under, section 157.208(a),

or must qualify at the time of abandonment. Indicated Shippers state

that pipelines, however, may seek to abandon a receipt point (or

perhaps multiple receipt points) and other appurtenant supply area

facilities as part of a single comprehensive abandonment. Indicated

Shippers aver that those facilities taken as a whole may exceed the

cost caps in section 157.208, and thus would not qualify for automatic

abandonment under section 157.216(a).

Commission Response. The only facilities that can be abandoned

under the automatic authority of section 157.216(a) are those

facilities that both meet the eligibility requirements and do not

exceed the section 157.208 cost limitations. Receipt facilities that

were constructed under the prior notice requirements or whose original

cost exceed the level for automatic construction are not eligible for

automatic abandonment under section 157.216(a). Pipelines must use the

prior notice authority under section 157.216(b) to abandon such

facilities. However, since the cost limit for automatic construction

under the blanket certificate is currently $7.2 million, we do not

expect that many

[[Page 54533]]

supply area abandonments will exceed this limitation.

3. Abandonment by Sale

In addition, we clarify that using either the automatic or prior

notice authority of this section to abandon facilities by sale to a

third party does not address the jurisdictional status of the

facilities after the effective date of abandonment. The acquiring party

is still responsible for seeking a determination, if one is desired, on

the jurisdictional status of the facilities.

P. Section 157.217--Changes in Rate Schedules

The Final Rule allowed pipelines to change rate schedules, at

customer request, for the purpose of converting Part 157 transportation

or storage service to a complementary Part 284 service. The order also

provided automatic abandonment authorization for the Part 157

transportation service and noted that pipelines will need to make a

filing to reflect removal of the Part 157 rate schedule from their

tariff. Consistent with this discussion, we will add a new section

157.217(a)(4) that requires pipelines to remove any Part 157 rate

schedule under which service has been totally converted to Part 284

service.

Q. Appendix II to Subpart F--Procedures for Compliance With the

National Historic Preservation Act of 1966 Under Section

157.206(d)(3)(ii)

In the Final Rule, the Commission defined the Tribal Historic

Preservation Officer (THPO) and added references to the THPO where

State Historic Preservation Officer (SHPO) is cited in section

157.202(d)(3)(ii).

Comments. Enron requests that the Commission clarify that, to the

extent a THPO declines to comment in writing or a SHPO gives

conditional clearance subject to the approval of the THPO, a project

will not automatically convert to a case-specific certificate

proceeding. El Paso states that the definition of THPO should be

consistent with the definition in Section 106 of National Historic

Preservation Act (NHPA) and the implementing regulations of the

Advisory Council on Historic Preservation (Advisory Council).

El Paso requests that the Commission clarify who will constitute an

``alternative consultant'' and how the consultant will be designated by

the Commission. El Paso also requests that the Commission clarify that

if the pipeline files a request for clearance, and the SHPO/THPO does

not respond to the request within 30 days, the lack of response means

that the SHPO/THPO has declined to consult with the certificate holder.

Additionally, it contends that the Commission should revise its

procedures to provide that if the SHPO/THPO does not respond within 30

days, the pipeline either may proceed With the next step Under the

Advisory Council's process or should consult with the alternative

consultant designated by the Commission. Finally, it requests that the

Commission clarify that if it designates an alternative consultant,

that consultant must act within 30 days of the pipeline's request for

clearance.

Commission Response. Under section 106 of the NHPA, the Commission

is obligated to ensure that the Advisory Council's process is properly

carried out. Under the Commission's blanket certificate construction

program, the pipeline's construction must be subject to the SHPO/THPO

review and it can have no impact to covered cultural resources. If

these two requirements are met, the Commission has determined that it

has met its obligation under the Advisory Council's regulations.

If the SHPO/THPO have not responded to a company's request within

30 days, it does not mean that they have declined to consult with the

certificate holder. Section 106 of the NHPA pertains to responding to

the Federal agency official, not the applicant. The Commission views

the SHPO/THPO's failure to respond and declining to consult as two

different things.

If the SHPO/THPO respond to the certificate holder that they will

not consult with the certificate holder, then Appendix II provides that

the certificate holder should contact the Commission for a

determination of how to proceed. Depending on the circumstances of the

project, and the reason given for declining to consult, the Commission

staff will designate an alternative entity, to be determined by the

Director of the OPR, or it might take over the consultation

responsibility. This provision allows the blanket process to continue

where it might otherwise be stymied. Projects do not convert to the

case-specific authorization procedures because either the SHPO or the

THPO decline to consult.

If the SHPO/THPO fail to respond to the certificate holder, it is

up to the certificate holder to decide how long it will wait before it

requests assistance from the Commission or determines that it can not

use the blanket process for a given project. In any event, it may not

proceed with the blanket project unless it gets a response from the

SHPO/THPO or until it contacts the Commission, which will then

determine how to proceed under the particular circumstances.

Finally, we will revise paragraph (d) of Appendix II consistent

with the Advisory Council regulation to state that THPO means the

Tribal Historic Preservation Officer, as at Title 36 section

800.2(c)(2) of the Code of Federal Regulations (CFR).

R. Section 380.12(c)(2)--Nonjurisdictional Facilities

In the Final Rule, the Commission listed the information it needed

to consider the environmental impact of related nonjurisdictional

facilities that would be constructed upstream or downstream of the

jurisdictional facilities for the purpose of delivering, receiving, or

using the proposed gas volumes.

Comments. Generally, INGAA and Enron contend that the Commission is

requesting too much information under the filing requirements relative

to the four-factor test, 16 and that the information may not

be available at the time the pipeline files the application. Further,

they contend that the requirements should not be part of the minimum

checklist and that the application should not be rejected if the

pipeline fails to provide all the information.

---------------------------------------------------------------------------

\16\ See Algonquin Gas Transmission Co., 59 FERC para. 61,255,

at 61,934 (1992).

---------------------------------------------------------------------------

Commission Response. The four-factor test cannot be applied without

a knowledge of what the facilities are and where they are to be

located. Without a description of the facilities, it is difficult to

apply the first factor and determine whether the ``regulated activity

comprises `merely a link' in a corridor type project.'' Without

location information and a reasonable description of the facilities

involved, it isn't possible to apply factors two or three to determine

whether there ``are aspects of the nonjurisdictional facility in the

immediate vicinity of the regulated activity which uniquely determine

the location and configuration of the regulated activity'' or the

``extent to which the entire project will be within the Commission's

jurisdiction.'' Locational information, as well as the status of

permits needed for the nonjurisdictional facility, are required to

determine factor four, ``the extent of cumulative Federal control and

responsibility.'' Consequently, the Final Rule requires in sections

380.12(c)(2)(i)(A-C) that the filing provide a brief description,

locational information, and status of permits for the nonjurisdictional

facilities.

[[Page 54534]]

The Final Rule also requires consultation with the appropriate

agencies for endangered species, cultural resources, and coastal zone

management in sections 380.12(c)(2)(i)(D-F). While this information is

not needed for the four-factor test, it is usually needed for a

complete analysis of the project under the legislation covering these

resources. Further, if it hasn't already been done by the

nonjurisdictional sponsor, it can usually be done with very little

effort at the same time as similar analysis is done for the

jurisdictional facilities.

Finally, section 380.12(c)(2)(ii) asks the jurisdictional company

to give the Commission its view of the results of applying the four-

factor test. This allows the company direct input into the analysis and

can help the staff more fully understand the circumstances of the

project so it can make an appropriate recommendation to the Commission.

The four-factor test must be applied as early in the environmental

review process as possible to avoid substantial delays. Without it, it

is difficult for the Commission to determine whether an environmental

assessment may suffice or whether an environmental impact statement

would be appropriate. It is difficult to identify the scope of whatever

environmental document will be prepared without this information, and,

in fact, if it is filed after the initial scoping, it is entirely

possible that a second scoping process, including additional public

meetings, would be required. This would be wasteful of Commission's

time and resources, as well as having the potential to delay the

environmental review and the Commission's ultimate disposition of the

application. Therefore, we believe it is necessary that this

information be filed with the application.

S. Section 380.12(f)(2)--Cultural Resources

The Final Rule requires that the documentation of the applicant's

initial cultural resources consultation and Overview and Survey Reports

must be filed with the initial application. Further, it requires that

the comments of the SHPO and land management agency, if appropriate, be

filed with the initial application if they are available.

1. Survey Reports

Comments. INGAA requests that the Commission clarify that the

intent of the language in section 380.12(f)(2) is not to require that a

survey report is necessary in every case. It states that the general

practice of the industry is to file an Overview Report with the

application. It explains that the Overview Report canvasses existing

literature to identify significant sites in the vicinity of the

proposed project, and allows the sponsor either to avoid the site or to

set forth proposed mitigation measures. It argues that a survey report

takes much longer to complete and is significantly more costly since it

involves using an archeologist to examine the actual route to determine

whether there are additional sites not currently identified in existing

literature. It contends that the determination of whether a survey is

required is made in consultation with the appropriate SHPO.

Commission Response. As clearly stated in section 380.12(f)(2), it

is our intent to require that the survey report is filed with the

application in all cases where the report is deemed necessary during

the cultural resources consultations. As stated, one of the

Commission's goals in the Final Rule is to facilitate expediting the

certificate process. The current practice of the industry that INGAA

alludes to is a significant contributing factor to the time required

for Commission review. Applications which do not have the survey

reports included are invariably delayed while the applicant and the

Commission's staff attempt to satisfy the requirements of the law

before a certificate is issued or construction begins. Therefore, the

survey report should be filed with the application when it is deemed

necessary as a result of the consultations.

2. Issuing Certificates

Comments. Enron and INGAA request that the Commission clarify the

timing for providing SHPO/THPO clearances in conjunction with the

issuance of a case-specific certificate. They contend that currently

certificates are issued contingent on receiving clearances before

construction begins on the affected area because the pipeline may not

have been able to secure the land rights necessary to perform cultural

resource work prior to the issuance of the certificate.

Commission Response. The Commission prefers that the SHPO/THPO

comments on the Overview and Survey Reports and the Evaluation Report

and Treatment Plan, if required, for the entire project be filed before

a certificate is issued. However, we understand that if access to the

property is denied by the landowner, comments for the areas to which

access has been denied would be filed after the certificate is issued.

The Commission will determine on a case-by-case basis if it is

necessary to issue a certificate contingent on the pipeline receiving

clearances before construction begins.

T. Section 380.12(k)(4)--Compressor Facilities

In the Final Rule, the Commission required that the pipeline

provide certain specific information concerning the compression

facilities proposed in an application and the noise impact of proposed

compression and LNG facilities.

Comments. On rehearing, INGAA contends that much of the information

concerning the compression facilities is not available at the time the

application is filed because the pipeline has not made its final

selection of compressor units. It requests that the minimum checklist

be clarified so as to require data that is reasonably available at the

time the application is filed. Williston Basin makes a similar request.

Commission Response. The Commission agrees that some of the items

listed in the minimum checklist may not be available at the time of

filing, especially for large projects with long lead times. This

information includes the manufacturer's name and the model number of

the compressor units. Therefore, we will modify section

380.12(k)(4)(ii) and paragraph 4 of the Resource Report 9 section of

the Appendix A to Part 380 and limit the information the pipeline must

provide for new compressors at the time the application is filed to the

proposed horsepower of compression, the type of compressor that is

needed (turbine, reciprocating), and the energy source (natural gas or

electricity). These are basic pieces of information that are needed to

formulate a project. If the additional required information listed in

the resource report is not available at the time the application is

filed, the applicants should justify the absence of such information,

especially for smaller projects where there may not be a long lead

time. Additionally, the application should specify when the listed

information will be available and when it will be filed.

U. Section 380.14(a)(3)--Cultural Resources Procedure for Case-specific

Projects

The Final Rule adds a new section 380.14 to the Commission's

regulations to address concerns regarding the Commission's compliance

with the National Historic Preservation Act.

Comment. INGAA requests that the Commission clarify that if a

pipeline files a request for clearance and the SHPO/THPO does not

respond to the pipeline within 30 days, the SHPO/THPO has declined to

consult with the

[[Page 54535]]

certificate holder for the purpose of complying with section 380.14(a).

Commission Response. As explained above, under section 106 of the

NHPA, the Commission is obligated to ensure that the Advisory Council's

process is properly carried out. If the SHPO/THPO has not responded

within 30 days, it does not mean that they have declined to consult

with the certificate holder. If the SHPO/THPO does not respond, the

applicant should contact the Commission's staff for further guidance.

V. Section 380.15--Siting and Maintenance Requirements

In section 380.15 of the Final Rule, the Commission moved the

siting guidelines from section 2.69 in the General Policy and

Interpretations section to the environmental regulations in Part 380.

Comments. INGAA requests that the Commission clarify that this

section should be titled ``guidelines'' and not requirements since

section 380.15(d) lists suggestions to avoid or minimize effects on

scenic, historic, wildlife, and recreational values that may or may not

be applicable to every project.

Commission Response. In section 380.15 the Commission is requiring

that the pipeline consider the areas listed when it is planning a

construction activity. If the requirements of the section are ``not

applicable'' to a project, then they are not relevant to that project

and there is no potential for conflict. For projects where they are

applicable, the wording is such that a good faith effort to comply

should be adequate. In all cases, the applicant should be able to

justify the level of compliance.

W. Miscellaneous

Minor modifications have been made to certain sections in the

regulations to correct references to other sections that have been

changed and to update the Commission's address and phone number.

Additionally, the Commission intends to modify the minimum filing

requirement in Resource Report 8 for facilities in a designated coastal

zone management area as specified in number nine in Resource Report 8

in Appendix A to Part 380. In addition to requiring that the pipeline

identify all facilities located within a designated coastal zone

management area, it will also require that the applicant provide a

consistency determination or evidence that it has requested a

consistency determination consistent with the existing requirements in

section 380.12(j)(7).

The Commission will also clarify the minimum filing requirement in

Resource Report 3 for threatened or endangered species surveys as

specified in number six in Resource Report 3 in Appendix A to Part 380.

The text of this resource report clearly and explicitly indicates that

the surveys for the species or, in the case where timing problems

exist, habitat surveys must be done and reported upon as part of the

initial application. This requirement was implicit in the wording of

Appendix A. We clarify the intent by making it explicit.

In the Final Rule, the existing paragraph (a)(2), Maps and

diagrams, in section 157.6 was inadvertently removed. We will correct

this error by reinserting this paragraph.

Finally, in the Final Rule the existing paragraph (g), Reports, in

section 157.206 was inadvertently removed and paragraph (h), Treatment

of Revenues, was redesignated as paragraph (d). Paragraph (g), Reports,

should have been redesignated as paragraph (d) and the Treatment of

Revenues paragraphs should have been removed. We will correct this

error in this rehearing order.

List of Subjects

18 CFR Part 2

Administrative practice and procedure, Electric power, Natural gas,

Pipelines, Reporting and record keeping requirements.

18 CFR Part 157

Administrative practice and procedure, Natural gas, Reporting and

record keeping requirements.

18 CFR Part 284

Continental shelf, Natural gas, Reporting and record keeping

requirements.

18 CFR Part 380

Environmental impact statements, Reporting and record keeping

requirements.

18 CFR Part 385

Administrative practice and procedure, Electric power, Penalties,

Pipelines, Reporting and record keeping.

By the Commission.

David P. Boergers,

Secretary.

In consideration of the foregoing, the Commission amends parts 2,

157, 284, 380, and 385, Chapter I, Title 18, Code of Federal

Regulations, as follows .

PART 2--GENERAL POLICY AND INTERPRETATIONS

1. The authority citation for Part 2 continues to read as follows:

Authority: 5 U.S.C. 601; 15 U.S.C. 717-717w, 3301-3432; 16

U.S.C. 792-825y, 2601-2645; 42 U.S.C. 4321-4361, 7101-7352.

2. In Sec. 2.55, paragraphs (a)(2) introductory text and (a)(2)(ii)

are revised to read as follows:

Sec. 2.55 Definition of terms used in section 7(c).

* * * * *

(a) * * *

(2) Advance notification. One of the following requirements will

apply to any specified auxiliary installation. If auxiliary facilities

are to be installed:

* * * * *

(ii) On, or at the same time as, certificated facilities which are

not yet in service (except those authorized under the automatic

procedures of part 157 of subpart F of this chapter), then a

description of the auxiliary facilities and their locations must be

provided to the Commission at least 30 days in advance of their

installation; or

* * * * *

PART 157--APPLICATIONS FOR CERTIFICATES OF PUBLIC CONVENIENCE AND

NECESSITY AND FOR ORDERS PERMITTING AND APPROVING ABANDONMENT UNDER

SECTION 7 OF THE NATURAL GAS ACT

3. The authority citation for part 157 continues to read as

follows:

Authority: 15 U.S.C. 717-717W, 3301-3432; 42 U.S.C. 7101-7352.

4. In Sec. 157.6:

A. Paragraphs (a)(2) through (a)(5) are redesignated as (a)(3)

through (a)(6).

B. A new paragraph (a)(2) is added.

C. Paragraph (b)(8) is revised.

The addition and revision read as follows:

Sec. 157.6 Applications; general requirements.

(a) * * *

(2) Maps and diagrams. An applicant required to submit a map or

diagram under this subpart must submit one paper copy of the map or

diagram.

* * * * *

(b) * * *

(8) For applications to construct new facilities, detailed cost-of-

service data supporting the cost of the expansion project, a detailed

study showing the revenue responsibility for each firm rate schedule

under the pipeline's currently effective rate design and under the

pipeline's proposed rates, a detailed rate impact analysis by rate

schedule (including by zone, if applicable), and an analysis reflecting

the impact of the fuel usage resulting from the proposed

[[Page 54536]]

expansion project (including by zone, if applicable).

* * * * *

5. Section 157.8 is revised to read as follows:

Sec. 157.8 Acceptance for filing or rejection of applications.

Applications will be docketed when received and the applicant so

advised.

(a) If an application patently fails to comply with applicable

statutory requirements or with applicable Commission rules,

regulations, and orders for which a waiver has not been granted, the

Director of the Office of Pipeline Regulation may reject the

application within 10 days of filing as provided by Sec. 385.2001(b) of

this chapter. This rejection is without prejudice to an applicant's

refiling a complete application. However, an application will not be

rejected solely on the basis of:

(1) Environmental reports that are incomplete because the company

has not been granted access by the affected landowner(s) to perform

required surveys; or,

(2) Environmental reports that are incomplete, but where the

minimum checklist requirements of Part 380, Appendix A of this chapter

have been met.

(b) An application which relates to an operation, sale, service,

construction, extension, acquisition, or abandonment concerning which a

prior application has been filed and rejected, shall be docketed as a

new application. Such new application shall state the docket number of

the prior rejected application.

(c) The Director of the Office of Pipeline Regulation may also

reject an application after it has been noticed, at any time, if it is

determined that such application does not conform to the requirements

of this part.

6. Section 157.10 is revised to read as follows:

Sec. 157.10 Interventions and protests.

(a) Notices of applications, as provided by Sec. 157.9, will fix

the time within which any person desiring to participate in the

proceeding may file a petition to intervene, and within which any

interested regulatory agency, as provided by Sec. 385.214 of this

chapter, desiring to intervene may file its notice of intervention.

(1) Any person filing a petition to intervene or notice of

intervention shall state specifically whether he seeks formal hearing

on the application.

(2) Any person may file to intervene on environmental grounds based

on the draft environmental impact statement as stated at

Sec. 380.10(a)(1)(i) of this chapter. In accordance with that section,

such intervention will be deemed timely as long as it is filed within

the comment period for the draft environmental impact statement.

(3) Failure to make timely filing will constitute grounds for

denial of participation in the absence of extraordinary circumstances

or good cause shown.

(4) Protests may be filed in accordance with Sec. 385.211 of this

chapter within the time permitted by any person who does not seek to

participate in the proceeding.

(b) A copy of each application, supplement and amendment thereto,

including exhibits required by Secs. 157.14, 157.16, and 157.18, shall

upon request be promptly supplied by the applicant to anyone who has

filed a petition for leave to intervene or given notice of

intervention.

(1) An applicant is not required to serve voluminous or difficult

to reproduce material, such as copies of certain environmental

information, to all parties, as long as such material is publically

available in an accessible central location in each county throughout

the project area.

(2) An applicant shall make a good faith effort to place the

materials in a public location that provides maximum accessibility to

the public.

(c) Complete copies of the application must be available in

accessible central locations in each county throughout the project

area, either in paper or electronic format, within three business days

of the date a filing is issued a docket number. Within five business

days of receiving a request for a complete copy from any party, the

applicant must serve a full copy of any filing on the requesting party.

Such copy may exclude voluminous or difficult to reproduce material

that is publically available. Pipelines must keep all voluminous

material on file with the Commission and make such information

available for inspection at buildings with public access preferably

with evening and weekend business hours, such as libraries located in

central locations in each county throughout the project area.

Sec. 157.103 [Amended]

7. In Sec. 157.103, in paragraph (i) the reference to

``157.206(d)'' is removed and a reference to ``157.206(b)'' is added in

its place.

8. In Sec. 157.202, the second sentence in paragraph (b)(2)(i), and

paragraphs (b)(2)(ii)(D) and (b)(12) are revised to read as follows:

Sec. 157.202 Definitions.

* * * * *

(b) * * *

(2)(i) * * * Eligible facility also includes any gas supply

facility or any facility, including receipt points, needed by the

certificate holder to receive gas into its system for further transport

or storage, and interconnecting facilities between transporters that

transport natural gas under part 284 of this chapter. * * *

(ii) * * *

(D) A facility required to test or develop an underground storage

field or that alters the certificated capacity, deliverability, or

storage boundary, or a facility required to store gas above ground in

either a gaseous or liquified state, or a facility used to receive gas

from plants manufacturing synthetic gas or from plants gasifying

liquefied natural gas, or wells needed to utilize an underground

storage field.

* * * * *

(12) Interconnection facilities means the interconnecting point,

which includes the tap, metering, and M&R facilities and the related

interconnecting pipeline.

* * * * *

9. In Sec. 157.206, in the second sentence in paragraph (c) the

words ``due to construction delays'' are removed, and paragraph (d) is

revised to read as follows:

Sec. 157.206 Standard conditions.

* * * * *

(d) Reports. The certificate holder shall file reports as required

by this subpart.

* * * * *

10. In Sec. 157.208, the second sentence in paragraph (f)(2) is

revised to read as follows:

Sec. 157.208 Construction, acquisition, operation, replacement, and

miscellaneous rearrangement of facilities.

* * * * *

(f) * * *

(2) * * * In the event that the certificate holder thereafter

wishes to change the maximum operating pressure of supply or delivery

lateral facilities constructed under section 7(c) of the Natural Gas

Act or facilities constructed under this section, it shall file an

appropriate request pursuant to the procedures set forth in

Sec. 157.205(b). * * *

* * * * *

11. In Sec. 157.216, paragraph (a)(2) is revised to read as

follows:

Sec. 157.216 Abandonment.

(a) * * *

[[Page 54537]]

(2) An eligible facility that was installed pursuant to automatic

authority under Sec. 157.208(a), or that now qualifies for automatic

authority under Sec. 157.208(a), or a facility constructed under

Sec. 157.211, provided the certificate holder obtains the written

consent of the customers that have received service through the

facilities during the past 12 months.

* * * * *

12. In Sec. 157.217, paragraph (a)(4) is added to read as follows:

Sec. 157.217 Changes in rate schedules.

(a) * * *

(4) The certificate holder shall make a filing to reflect removal

of the Part 157 rate schedule from its tariff.

* * * * *

13. In Appendix I to Subpart F of Part 157, the reference to

``157.206(b)(2)(vii)'' in the second paragraph of the introductory text

and the introductory text in paragraph 2, and paragraph 3, is removed

and a reference to ``157.206(b)(2)(vi)'' is added in its place.

14. In Appendix II to Subpart F of Part 157, in paragraph (7) the

phrase ``, or THPO, as appropriate,'' is added after the reference to

``the SHPO'' wherever it appears, and paragraph (d) is revised to read

as follows:

Appendix II to Subpart F--Procedures for Compliance With the

National Historic Preservation Act of 1966 Under

Sec. 157.206(b)(3)(ii)

* * * * *

(d) ``THPO'' means the Tribal Historic Preservation Officer, as

defined at 36 CFR 800.2(c)(2).

* * * * *

PART 284--CERTAIN SALES AND TRANSPORTATION OF NATURAL GAS UNDER THE

NATURAL GAS ACT, THE NATURAL GAS POLICY ACT OF 1978 AND RELATED

AUTHORITIES

15. The authority citation for part 284 continues to read as

follows:

Authority: 15 U.S.C. 717-717w, 3301-3432; 42 U.S.C. 7101-7352;

43 U.S.C. 1331-1356.

16. In Sec. 284.11, in paragraphs (a) and (c)(2) the references to

``157.206(d)'' are removed and references to ``157.206(b)'' are added

in their place.

PART 380--REGULATIONS IMPLEMENTING THE NATIONAL ENVIRONMENTAL

POLICY ACT

17. The authority citation for part 380 is revised to read as

follows:

Authority: 42 U.S.C. 4321-4370a, 7101-7352; E.O. 12009, 3 CFR

1978 Comp., p. 142.

Sec. 380.8 [Amended]

18. In Sec. 380.8:

A. The references to ``400 First Street NW.,'' and ``825 North

Capitol Street NW.,'' are removed and references to ``888 First Street

NE.,'' are added in their place.

B. The reference to ``and Producer'' in the second sentence is

removed.

C. The telephone number ``376-9171'' is removed and the telephone

number ``219-2700'' is added in its place.

D. The telephone number ``357-8500'' is removed and the telephone

number ``208-0700'' is added in its place.

Sec. 380.9 [Amended]

19. In Sec. 380.9, in paragraph (b) the reference to ``825 North

Capitol Street NW., room 1000'' is removed and a reference to ``888

First Street NE., Room 2A'' is added in its place.

20. In Sec. 380.12, a heading is added to paragraph (f)(2); and the

last sentence in paragraph (f)(2) introductory text and paragraph

(k)(4)(ii) are revised to read as follows:

Sec. 380.12 Environmental Reports for Natural Gas Act Applications.

* * * * *

(f) * * *

(2) Initial filing requirements. * * * If surveys are deemed

necessary by the consultation with the SHPO/THPO, the survey report

must be filed with the application.

* * * * *

(k) * * *

(4) * * *

(ii) Include sound pressure levels for unmuffled engine inlets and

exhausts, engine casings, and cooling equipment; dynamic insertion loss

for all mufflers; sound transmission loss for all compressor building

components, including walls, roof, doors, windows and ventilation

openings; sound attenuation from the station to nearby noise-sensitive

areas; the manufacturer's name, the model number, the performance

rating; and a description of each noise source and noise control

component to be employed at the proposed compressor station. For

proposed compressors the initial filing must include at least the

proposed horsepower, type of compression, and energy source for the

compressor.

* * * * *

21. In Appendix A to Part 380, paragraph 6 of Resource Report 3,

paragraph 9 of Resource Report 8, and paragraph 4 of Resource Report 9

are revised to read as follows:

Appendix A to Part 380--Minimum Filing Requirements for

Environmental Reports Under the Natural Gas Act

* * * * *

Resource Report 3--Vegetation and Wildlife

* * * * *

6. Identify all federally listed or proposed endangered or

threatened species that potentially occur in the vicinity of the

project and discuss the results of the consultations with other

agencies. Include survey reports as specified in Sec. 380.12(e)(5).

* * * * *

Resource Report 8--Land Use, Recreation and Aesthetics

* * * * *

9. Identify all facilities that would be within designated coastal

zone management areas. Provide a consistency determination or evidence

that a request for a consistency determination has been filed with the

appropriate state agency. ((Sec. 380.12(j)(4 & 7))

* * * * *

Resource Report 9--Air and Noise Quality

* * * * *

4. Describe the existing compressor units at each station where

new, additional, or modified compressor units are proposed, including

the manufacturer, model number, and horsepower of the compressor units.

For proposed new, additional, or modified compressor units include the

horsepower, type, and energy source. (Sec. 380.12(k)(4)).

* * * * *

PART 385--RULES OF PRACTICE AND PROCEDURE

22. The authority citation for part 385 continues to read as

follows:

Authority: 5 U.S.C. 551-557; 15 U.S.C. 717-717z, 3301-3432; 16

U.S.C. 791a-825r, 2601-2645; 31 U.S.C. 9701; 42 U.S.C. 7101-7352; 49

U.S.C. 60502; 49 App. U.S.C. 1-85.

Sec. 835.2001 [Amended]

23. In Sec. 385.2001, the reference in paragraph (a)(1)(i) to ``825

North Capitol Street'' is removed and a reference to ``888 First Street

N.E.'' is added in its place.

[FR Doc. 99-25783 Filed 10-6-99; 8:45 am]

BILLING CODE 6717-01-P