DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EG99-181-000, et al.]

PanEnergy Lake Charles Generation, Inc., et al.; Electric Rate

and Corporate Regulation Filings

July 7, 1999.

Take notice that the following filings have been made with the

Commission:

1. PanEnergy Lake Charles Generation, Inc.

[Docket No. EG99-181-000]

Take notice that on June 29, 1999, PanEnergy Lakes Charles

Generation, Inc. (PanEnergy Lake Charles Generation) of 5444 Westheimer

Road, Houston, Texas 77056, filed with the Federal Energy Regulatory

Commission an application for determination of Exempt Wholesale

Generator (EWG) status pursuant to Part 365 of the Commission's

regulations.

PanEnergy Lake Charles Generation is in the exclusive business of

owning and operating a 16 MW electric generating facility located in

Lake Charles, Louisiana. The electric energy generated by this facility

will be sold at wholesale. Pan Energy Lake Charles Generation has been

previously certified as an EWG for the subject facility. A change in

ownership of the stock of Pan Energy Lake Charles Generation

necessitates the instant filing.

Comment date: July 28, 1999, in accordance with Standard Paragraph

E at the end of this notice. The Commission will limit its

consideration of comments to those that concern the adequacy or

accuracy of the application.

2. NRG Northeast Generating LLC, Dunkirk Power LLC, and Huntley

Power LLC

[Docket No. EG99-161-000, Docket No. EG99-162-000 and Docket No. EG99-

163-000]

Take notice that on June 18, 1999, NRG Northeast Generating LLC,

Dunkirk Power LLC and Huntly Power LLC (collectively, Applicants),

tendered for filing with the Federal Energy Regulatory Commission, a

clarification to their pending applications.

Comment date: July 28, 1999, in accordance with Standard Paragraph

E at the end of this notice. The Commission will limit its

consideration of comments to those that concern the adequacy or

accuracy of the application.

3. Broad River Energy LLC

[Docket No. EG99-182-000]

Take notice that on June 30, 1999, Broad River Energy LLC

(Applicant) with its principal office at c/o SkyGen Energy LLC, Edens

Corporate Center, 650 Dundee Road, Suite 350, Northbrook, Illinois

60062, filed with the Federal Energy Regulatory Commission (Commission)

an application for determination of exempt wholesale generator status

pursuant to Part 365 of the Commission's regulations.

Applicant states that it will be engaged in owning and operating

the Broad River Energy Center (the Facility) consisting of three

natural gas fueled simple cycle combustion turbines having a combined

electrical output totaling approximately 500 MW. The Facility will be

constructed outside of Gaffney in Cherokee County, South Carolina. The

Applicant also states that it will sell electric energy exclusively at

wholesale.

Comment date: July 28, 1999, in accordance with Standard Paragraph

E at the end of this notice. The Commission will limit its

consideration of comments to those that concern the adequacy or

accuracy of the application.

4. Mt. Poso Cogeneration Company, L.P.

[Docket No. EG99-183-000]

Take notice that on June 30, 1999, Mt. Poso Cogeneration Company,

L.P., 10000 Stockdale Highway, Suite 100, Bakersfield, CA 93311, filed

with the Federal Energy Regulatory Commission an application for

determination of exempt wholesale generator status pursuant to Part 365

of the Commission's regulations.

Mt. Poso owns and operates a nominal 49,500 kW, coal-fired,

enhanced oil recovery cogeneration power plant that uses a circulating

fluidized bed boiler (CFB) combustion system (the Facility). The

Facility is located about 15 miles east of Highway 99 and about 25

miles north of Bakersfield in California's San Joaquin Valley.

Comment date: July 28, 1999, in accordance with Standard Paragraph

E at the end of this notice. The Commission will limit its

consideration of comments to those that concern the adequacy or

accuracy of the application.

5. PP&L Colstrip III, LLC

[Docket No. EG99-184-000]

Take notice that on July 1, 1999, PP&L Colstrip III, LLC

(Applicant), 11350 Random Hills Road, Fairfax, Virginia 22030-6044,

filed with the Federal Energy Regulatory Commission an

[[Page 37961]]

Application for Determination of Exempt Wholesale Generator Status

pursuant to Part 365 of the Commission's Regulations and Section 32 of

the Public Utility Holding Company Act of 1935, as amended.

Applicant, a limited liability company organized under the laws of

the State of Delaware, is acquiring assets from The Montana Power

Company that will be used to make sales of electric energy exclusively

at wholesale.

Copies of the application have been served upon the Montana Public

Service Commission, the Pennsylvania Public Utility Commission, and the

Securities and Exchange Commission.

Comment date: July 28, 1999, in accordance with Standard Paragraph

E at the end of this notice. The Commission will limit its

consideration of comments to those that concern the adequacy or

accuracy of the application.

6. PP&L Montana, LLC

[Docket No. EG99-185-000]

Take notice that on July 1, 1999, PP&L Montana, LLC (Applicant),

11350 Random Hills Road, Fairfax, Virginia 22030-6044, filed with the

Federal Energy Regulatory Commission an Application for Determination

of Exempt Wholesale Generator Status pursuant to Part 365 of the

Commission's Regulations and Section 32 of the Public Utility Holding

Company Act of 1935, as amended.

Applicant, a limited liability company organized under the laws of

the State of Delaware, is acquiring assets from The Montana Power

Company that will be used to make sales of electric energy exclusively

at wholesale.

Copies of the application have been served upon the Montana Public

Service Commission, the Pennsylvania Public Utility Commission, and the

Securities and Exchange Commission.

Comment date: July 28, 1999, in accordance with Standard Paragraph

E at the end of this notice. The Commission will limit its

consideration of comments to those that concern the adequacy or

accuracy of the application.

7. Foote Creek II, LLC

[Docket No. EG99-186-000]

Take notice that on July 1, 1999, Foote Creek II, LLC, 1455 Frazee

Road, Suite 900, San Diego, California 92108 filed with the Federal

Energy Regulatory Commission an application for determination of exempt

wholesale generator status pursuant to part 365 of the Commission's

regulations.

Foote Creek II, LLC, is a Delaware limited liability company that

intends to construct, own and operate a 1.8 MW generation facility

consisting of three (3) Mitsubishi WT Model 450/600 wind turbine

generators in Carbon County, Wyoming. Foote Creek II, LLC, is engaged

directly and exclusively in the business of owning or operating, or

both owning and operating, all or part of one or more eligible

facilities and selling electric energy at wholesale.

Comment date: July 28, 1999, in accordance with Standard Paragraph

E at the end of this notice. The Commission will limit its

consideration of comments to those that concern the adequacy or

accuracy of the application.

8. Newport Electric Corporation

[Docket No. ER99-2469-000]

Take notice that on June 30, 1999, Newport Electric Corporation

(Newport), tendered for filing an amendment to its cost of service

formula to reduce the cost of common equity to 10.65%. Newport also

provided an explanation of the differences between the proposed cost of

service formula and the currently-effective formula.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

9. Central Power and Light Company, West Texas Utilities Company,

Public Service Company of Oklahoma and Southwestern Electric Power

Company

[Docket No. ER99-2779-000]

Take notice that on June 30, 1999, Central Power and Light Company

(CPL), West Texas Utilities Company (WTU), Public Service Company of

Oklahoma (PSO) and Southwestern Electric Power Company (SWEPCO)

(collectively, the CSW Operating Companies) tendered for filing an

amendment to its May 3, 1999, filing in this proceeding in response to

a Letter Order issued in this proceeding on May 26, 1999.

The CSW Operating Companies state that a copy of the filing has

been served on all parties to Docket No. ER99-2779-000.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

10. American Electric Power Service Corporation

[Docket No. ER99-3416-000]

Take notice that on June 30, 1999, the American Electric Power

Service Corporation (AEPSC), tendered for filing executed Firm and Non-

Firm Point-to-Point Transmission Service Agreements for DukeSolutions,

Inc., an amendment to a previously filed Network Integration

Transmission Service Agreement for Buckeye Power Inc., on behalf of

Ormet Primary Aluminum Corporation, and service specifications for a

number of Long-Term Firm Point-to-Point Transmission Service

reservations made on AEP's OASIS. All of these agreements are pursuant

to the AEP Companies' Open Access Transmission Service Tariff (OATT).

The OATT has been designated as FERC Electric Tariff Original Volume

No. 4, effective July 9, 1996.

AEPSC requests waiver of notice to permit the Service Agreements to

be made effective for service billed on and after June 1, 1999.

A copy of the filing was served upon the Parties and the state

utility regulatory commissions of Indiana, Kentucky, Michigan, Ohio,

Tennessee, Virginia and West Virginia.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

11. Wisconsin Public Service Corporation

[Docket No. ER99-3417-000]

Take notice that on June 30, 1999, Wisconsin Public Service

Corporation (WPSC), tendered for filing an executed Service Agreement

with Madison Gas and Electric Company, providing for transmission

service under FERC Electric Tariff, Volume No. 1.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

12. Kansas Gas and Electric Company

[Docket No. ER99-3418-000]

Take notice that on June 30, 1999, Western Resources, Inc. (Western

Resources), on behalf of its wholly-owned subsidiary, Kansas Gas and

Electric Company (KGE), tendered for filing a Ninth Revised Exhibit B

to the Electric Power, Transmission and Service Contract between KGE

and Kansas Electric Power Cooperative, Inc., (KEPCo). KGE states the

filing is to update Exhibit B to reflect the installation of the Sharpe

point of delivery.

This filing is proposed to become effective June 1, 1999.

A copy of this filing was served upon KEPCo and the Kansas

Corporation Commission.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

13. Central Power and Light Company, West Texas Utilities Company,

Public Service Company of Oklahoma and Southwestern Electric Power

Company

[Docket No. ER99-3419-000]

Take notice that on June 30, 1999, Central Power and Light Company,

West

[[Page 37962]]

Texas Utilities Company, Public Service Company of Oklahoma and

Southwestern Electric Power Company (collectively, the CSW Operating

Companies), tendered for filing service agreements under which the CSW

Operating Companies will provide transmission and ancillary services to

the City of Coffeyville, Kansas in accordance with the CSW Operating

Companies' open access transmission service tariff.

The CSW Operating Companies state that a copy of the filing has

been served on the City of Coffeyville, Kansas.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

14. Sunbury Generation, LLC

[Docket No. ER99-3420-000]

Take notice that on June 30, 1999, Sunbury Generation, LLC (Sunbury

Generation), tendered for filing its application for market-based rate

authority pursuant to Section 205 of the Federal Power Act. The

application included a tariff providing for sales of electric capacity

and/or energy at market-based rates, a code of conduct and a form of

service agreement. The tariff also provides for sales of ancillary

services at market-based rates into the PJM Power Exchange, the New

York ISO Market and the ISO New England market. Sunbury Generation also

filed a Transition Power Purchase Agreement with PP&L, Inc.

Sunbury Generation requested that its tariff and related materials,

and the Transition Power Purchase Agreement become effective on August

29, 1999, sixty days after the date of this filing.

Sunbury Generation states that it has served its filing on the

Pennsylvania Public Utility Commission because Sunbury Generation will

own a generating facility which in the past has been used to make power

sales within the Commonwealth of Pennsylvania.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

15. Public Service Company of Oklahoma

[Docket No. ER99-3421-000]

Take notice that on June 30, 1999, Public Service Company of

Oklahoma (PSO) filed an Interconnection Agreement between PSO and the

City of Coffeyville, Kansas (Coffeyville).

PSO requests an effective date for the Interconnection Agreement of

July 1, 1999. Accordingly, PSO requests waiver of the Commission's

notice requirements.

PSO states that a copy of the filing was served on Coffeyville and

the Oklahoma Corporation Commission.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

16. Duke Energy Corporation

[Docket No. ER99-3422-000]

Take notice that on June 30, 1999, Duke Power, a division of Duke

Energy Corporation (Duke), tendered a Service Agreement for Market Rate

Sales under Rate Schedule MR, FERC Electric Tariff First Revised Volume

No. 3 (the MRSAs), between Duke and the United States of America,

Department of Energy acting by and through the Southeastern Power

Administration.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

17. SCC-L1, L.L.C.

[Docket No. ER99-3423-000]

Take notice that on June 30, 1999, SCC-L1, L.L.C. (SCC-L1),

tendered for filing a service agreement establishing Enron Power

Marketing, Inc. (EPMI), as a customer under SCC-L1's Rate Schedule No.

1.

SCC-L1 requests an effective date of June 1, 1999.

SCC-L1 states that a copy of the filing was served on EPMI.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

18. SCC-L3, L.L.C.

[Docket No. ER99-3424-000]

Take notice that on June 30, 1999, SCC-L3, L.L.C. (SCC-L3),

tendered for filing a service agreement establishing Enron Power

Marketing, Inc. (EPMI) as a customer under SCC-L3's Rate Schedule No.

1.

SCC-L3 requests an effective date of June 1, 1999.

SCC-L3 states that a copy of the filing was served on EPMI.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

19. SCC-L2, L.L.C.

[Docket No. ER99-3425-000]

Take notice that on June 30, 1999, SCC-L2, L.L.C. (SCC-L2),

tendered for filing a service agreement establishing Enron Power

Marketing, Inc. (EPMI) as a customer under SCC-L2's Rate Schedule No.

1.

SCC-L2 requests an effective date of June 1, 1999.

SCC-L2 states that a copy of the filing was served on EPMI.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

20. San Diego Gas & Electric Company

[Docket No. ER99-3426-000]

Take notice that on June 30, 1999, San Diego Gas & Electric Company

(SDG&E) tendered for filing pursuant to Section 205 of the Federal

Power Act, 16 U.S.C. 824d, Original Sheet No. 3 to Vol. No. 7 of

SDG&E's FERC Electric Tariff, providing for the sale of electric energy

at market-based rates.

SDG&E states that it was authorized by prior Commission orders in

Docket No. ER96-1663-000 to make sales of energy at market based rates

through the California Power Exchange (the PX). SDG&E now proposes to

remove the conditions that such sales be made only through the PX.

In support of its proposal, SDG&E submits a market power analysis

reflecting the divestiture of its fossil-fuel generation. SDG&E also

tenders the analysis to meet the requirement adopted in Docket No.

ER96-1663-000 that it file such an analysis prior to the termination of

the ``transition period'' during which, under state law, its retail

rates are fixed at specified levels.

SDG&E states that it has served a copy of its filing on the

California Public Utilities Commission.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

21. SOWEGA Power LLC

[Docket No. ER99-3427-000]

Take notice that on June 30, 1999, SOWEGA Power LLC, tendered for

filing, pursuant to Section 205 of the Federal Power Act, a request for

blanket approval to make sales at market-based rates from its two

generators located in southwestern Georgia.

SOWEGA also requests waiver of the Commission's open access

transmission tariff and OASIS requirements to the extent required and

requests the waivers traditionally granted to parties authorized to

sell power at market-based rates. SOWEGA seeks a waiver of the

Commission's 60 day prior notice and filing requirements and an

effective date from the Commission of July 2, 1999.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

22. Indianapolis Power & Light Company

[Docket No. ER99-3428-000]

Take notice that on June 29, 1999, Indianapolis Power & Light

Company (IPL), tendered for filing a letter

[[Page 37963]]

agreement extending by one year to August 31, 2000, the service IPL

currently provides to PSI Energy, a public utility subsidiary of

Cinergy, under an existing interconnection agreement.

Copies of this filing were sent to the Indiana Utility Regulatory

Commission and Cinergy.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

23. Puget Sound Energy, Inc.

[Docket No. ER99-3429-000]

Take notice that on June 30, 1999, Puget Sound Energy, Inc. (PSE),

tendered for filing a Service Agreement under the provisions of PSE's

market-based rates tariff, FERC Electric Tariff, First Revised Volume

No. 8, with Cinergy Capital & Trading, Inc. (Cinergy).

A copy of the filing was served upon Cinergy.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

24. Puget Sound Energy, Inc.

[Docket No. ER99-3430-000]

Take notice that on June 30, 1999, Puget Sound Energy, Inc. (PSE),

tendered for filing a Service Agreement under the provisions of PSE's

market-based rates tariff, FERC Electric Tariff, First Revised Volume

No. 8, with Calpine Power Services Company (Calpine).

A copy of the filing was served upon Calpine.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

25. Puget Sound Energy, Inc.

[Docket No. ER99-3431-000]

Take notice that on June 30, 1999, Puget Sound Energy, Inc. (PSE),

tendered for filing a Service Agreement under the provisions of PSE's

market-based rates tariff, FERC Electric Tariff, First Revised Volume

No. 8, with Citizens Power Sales (CP Sales).

A copy of the filing was served upon CP Sales.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

26. Puget Sound Energy, Inc.

[Docket No. ER99-3432-000]

Take notice that on June 30, 1999, Puget Sound Energy, Inc. (PSE),

tendered for filing a Service Agreement under the provisions of PSE's

market-based rates tariff, FERC Electric Tariff, First Revised Volume

No. 8, with City of Anaheim, Public Utilities Department (Anaheim).

A copy of the filing was served upon Anaheim.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

27. Puget Sound Energy, Inc.

[Docket No. ER99-3433-000]

Take notice that on June 30, 1999, Puget Sound Energy, Inc. (PSE),

tendered for filing a Service Agreement under the provisions of PSE's

market-based rates tariff, FERC Electric Tariff, First Revised Volume

No. 8, with California Department of Water Resources (DWR).

A copy of the filing was served upon DWR.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

28. Puget Sound Energy, Inc.

[Docket No. ER99-3434-000]

Take notice that on June 30, 1999, Puget Sound Energy, Inc. (PSE),

tendered for filing a Service Agreement under the provisions of PSE's

market-based rates tariff, FERC Electric Tariff, First Revised Volume

No. 8, with City of Burbank (Burbank).

A copy of the filing was served upon Burbank.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

29. Arizona Public Service Company

[Docket No. ER99-3435-000]

Take notice that on June 30, 1999, Arizona Public Service Company

(APS), tendered for filing a Service Agreement to provide Network

Integration Transmission Service under APS' Open Access Transmission

Tariff to the Navajo Tribal Utility Authority (NTUA).

A copy of this filing has been served on NTUA, the Arizona

Corporation Commission, and Walter Wolf, Esq.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

30. Illinois Power Company

[Docket No. ER99-3436-000]

Take notice that on June 30, 1999, Illinois Power Company (Illinois

Power), 500 South 27th Street, Decatur, Illinois 62526, tendered for

filing updated specification pages to the existing Network Service

Agreement under which Corn Belt Energy Company will take transmission

service pursuant to its open access transmission tariff. The agreements

are based on the Form of Service Agreement in Illinois Power's tariff.

Illinois Power has requested an effective date of June 1, 1999.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

31. Illinois Power Company

[Docket No. ER99-3437-000]

Take notice that on June 30, 1999, Illinois Power Company (Illinois

Power), 500 South 27th Street, Decatur, Illinois 62526, tendered for

filing updated specification pages to the existing Network Service

Agreement under which Soyland Power Cooperative will take transmission

service pursuant to its open access transmission tariff. The agreements

are based on the Form of Service Agreement in Illinois Power's tariff.

Illinois Power has requested an effective date of June 1, 1999.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

32. New York State Electric & Gas Corporation

[Docket No. ER99-3438-000]

Take notice that on June 30, 1999, New York State Electric & Gas

Corporation (NYSEG), tendered for filing pursuant to Section 205 of the

Federal Power Act and Section 35.13 of the Federal Energy Regulatory

Commission's (FERC or Commission) Regulations, an amendment to Rate

Schedule 87 filed with FERC corresponding to an Agreement with

Consolidated Edison Company of New York, Inc., (Con Ed). The proposed

amendment would decrease revenues by $7,901 based on the twelve month

period ending August 31, 2000.

This rate filing is made pursuant to Article 3, Sections 1(e) and

(f), and Sections 2 (e through g) of the August 23, 1983 Facilities

Agreement between NYSEG and Con Ed, filed with FERC. The annual charges

for routine operation, maintenance, general expenses, and revenue and

property taxes are revised based on data taken from NYSEG's Annual

Report to the Federal Energy Regulatory Commission (FERC Form 1) for

the twelve month period ended December 31, 1998. The revised facilities

charge is levied on the cost of Con Ed's use of NYSEG's substation,

transmission and distribution facilities required for the supply of Con

Ed's distribution feeders to serve its customers in the vicinity of

NYSEG's Mohansic Substation.

NYSEG requests an effective date of September 1, 1999.

Copies of the filing were served upon Consolidated Edison Company

of New

[[Page 37964]]

York, Inc. and the Public Service Commission of the State of New York.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

33. New York State Electric & Gas Corporation

[Docket No. ER99-3439-000]

Take notice that on June 30, 1999, New York State Electric & Gas

Corporation (NYSEG), tendered for filing pursuant to Section 205 of the

Federal Power Act and Section 35.13 of the Federal Energy Regulatory

Commission's (FERC or Commission) Regulations, an amendment to Rate

Schedule 191 filed with FERC corresponding to an Agreement with the

Delaware County Electric Cooperative (Delaware). The proposed amendment

would increase revenues by $484.92 based on the twelve month period

ending June 30, 2000.

This rate filing is made pursuant to Paragraph 3 of the May 8, 1998

Facilities Agreement between NYSEG and Delaware, filed with FERC. The

annual charges for routine operation and maintenance and general

expenses, as well as revenue and property taxes are revised based on

data taken from NYSEG's Annual Report to the Federal Energy Regulatory

Commission (FERC Form 1) for the twelve month period ended December 31,

1998. The revised facilities charge is levied on the cost of Delaware's

tap of NYSEG's 46 kV transmission line which extends from NYSEG's River

Road Substation to NYSEG's Delhi Substation. The tap terminates at

Delaware's Delhi Substation and is owned and operated by NYSEG for

Delaware's sole use.

NYSEG requests an effective date of July 1, 1999.

Copies of the filing were served upon the Delaware County Electric

Cooperative, Inc., and the Public Service Commission of the State of

New York.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

34. New York State Electric & Gas Corporation

[Docket No. ER99-3440-000]

Take notice that on June 30, 1999, New York State Electric & Gas

Corporation (NYSEG), tendered for filing pursuant to Section 205 of the

Federal Power Act and Section 35.13 of the Federal Energy Regulatory

Commission's (FERC or Commission) Regulations, an amendment to Rate

Schedule 180 filed with FERC corresponding to an Agreement with the

Oneida Madison Electric Cooperative (Oneida). The proposed amendment

would increase revenues by $203.10 based on the twelve month period

ending June 30, 2000.

This rate filing is made pursuant to Paragraph 3 of the December

16, 1996 Facilities Agreement between NYSEG and Oneida, filed with

FERC. The annual charges for routine operation and maintenance and

general expenses, as well as revenue and property taxes are revised

based on data taken from NYSEG's Annual Report to the Federal Energy

Regulatory Commission (FERC Form 1) for the twelve month ended December

31, 1998. The revised facilities charge is levied on the cost of

Oneida's tap of NYSEG's 46 kV transmission line which extends from

NYSEG's existing Eaton Tap to NYSEG's Eaton Substation. The new tap

terminates at Oneida's Eaton Substation and is owned and operated by

NYSEG for Oneida's sole use.

NYSEG requests an effective date of July 1, 1999.

Copies of the filing were served upon the Oneida Madison Electric

Cooperative , Inc. and the Public Service Commission of the State of

New York.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice

35. South Carolina Electric & Gas Company

[Docket No. ER99-3441-000]

Take notice that on June 30, 1999, South Carolina Electric & Gas

Company (SCE&G), tendered for filing service agreements establishing

Snapping Shoals Electric Membership Corporation, Washington Electric

Membership Corporation, and Cobb Electric Membership Corporation as

customers under the terms of SCE&G's Negotiated Market Sales Tariff.

SCE&G requests an effective date of one day subsequent to the date

of filing. Accordingly, SCE&G requests waiver of the Commission's

notice requirements.

Copies of this filing were served upon Snapping Shoals Electric

Membership Corporation, Washington Electric Membership Corporation, and

Cobb Electric Membership Corporation and the South Carolina Public

Service Commission.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

36. Duquesne Light Company

[Docket No. ER99-3442-000]

Take notice that June 30, 1999, Duquesne Light Company (DLC),

tendered for filing a Service Agreement dated June 29, 1999 with

Merrill Lynch Capital Services, Inc., under DLC's Open Access

Transmission Tariff (Tariff). The Service Agreement adds Merrill Lynch

Capital Services, Inc., as a customer under the Tariff.

DLC requests an effective date of June 29, 1999, for the Service

Agreement.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

37. Carolina Power & Light Company

[Docket No. ER99-3443-000]

Take notice that on June 30, 1999, Carolina Power & Light Company

(CP&L), tendered for filing an executed Service Agreement with Cleco

Corporation under the provisions of CP&L's Market-Based Rates Tariff,

FERC Electric Tariff No. 4.

CP&L is requesting an effective date of June 17, 1999 for this

Agreement.

Copies of the filing were served upon the North Carolina Utilities

Commission and the South Carolina Public Service Commission.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

38. Carolina Power & Light Company

[Docket No. ER99-3444-000]

Take notice that on June 30, 1999, Carolina Power & Light Company

(CP&L), tendered for filing Service Agreements for Short-Term Firm

Point-to-Point Transmission Service and Non-Firm Point-to-Point

Transmission Service with FPL Energy Power Marketing, Inc. Service to

this Eligible Customer will be in accordance with the terms and

conditions of Carolina Power & Light Company's Open Access Transmission

Tariff.

CP&L is requesting an effective date of June 15, 1999 for each

Agreement.

Copies of the filing were served upon the North Carolina Utilities

Commission and the South Carolina Public Service Commission.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

39. Carolina Power & Light Company

[Docket No. ER99-3445-000]

Take notice that on June 30, 1999, Carolina Power & Light Company

(CP&L), tendered for filing executed Service Agreements with Seminole

Electric Cooperative, Inc., and Southern Minnesota Municipal Power

Agency under the provisions of CP&L's Market-Based Rates Tariff, FERC

Electric Tariff No. 4. These Service Agreements supersede the un-

executed Agreements originally filed in Docket No. ER98-3385-000 and

approved effective May 18, 1998.

[[Page 37965]]

Copies of the filing were served upon the North Carolina Utilities

Commission and the South Carolina Public Service Commission.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

40. Pacific Gas and Electric Company

[Docket No. ER99-3447-000]

Take notice that on June 30, 1999, Pacific Gas and Electric Company

(PG&E), tendered for filing certain recorded cost information for the

period ending December 31, 1998, concerning generating units at five

power plants under reliability must-run (RMR) contracts with the

California Independent System Operator Corporation (CAISO).

Copies of this filing have been served upon the CAISO, the

California Public Utilities Commission, and all other participants in

the RMR proceedings.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

41. Duquesne Light Company

[Docket No. ER99-3462-000]

Take notice that on June 30, 1999, Duquesne Light Company (DLC),

tendered for filing under DLC's pending Market-Based Rate Tariff,

(Docket No. ER98-4159-000) executed Service Agreement at Market-Based

Rates with Central Illinois Light Company (Customer).

DLC has requested the Commission waive its notice requirements to

allow the Service Agreement to become effective as of June 29, 1999.

Copies of this filing were served upon Customer.

Comment date: July 20, 1999, in accordance with Standard Paragraph

E at the end of this notice.

42. PECO Energy Company

[Docket No. ES99-44-000]

Take notice that on June 30, 1999, PECO Energy Company filed an

application under Section 203 of the Federal Power Act seeking

authority to issue and reissue from time to time through September 30,

2001 up to $1.5 billion of promissory notes and other evidences of

secured and unsecured indebtedness maturing in less than one year from

the date of issuance.

Comment date: July 28, 1999, in accordance with Standard Paragraph

E at the end of this notice.

43. New England Power Pool

[Docket Nos. OA97-237-008., et al.]

Take notice that on July 1, 1999, Boston Edison Company filed a

report of refunds in compliance with the Commission's April 20, 1998

order in this proceeding.

Comment date: August 2, 1999, in accordance with Standard Paragraph

E at the end of this notice.

Standard Paragraphs

E. Any person desiring to be heard or to protest such filing should

file a motion to intervene or protest with the Federal Energy

Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in

accordance with Rules 211 and 214 of the Commission's Rules of Practice

and Procedure (18 CFR 385.211 and 385.214). All such motions or

protests should be filed on or before the comment date. Protests will

be considered by the Commission in determining the appropriate action

to be taken, but will not serve to make protestants parties to the

proceeding. Any person wishing to become a party must file a motion to

intervene. Copies of these filings are on file with the Commission and

are available for public inspection. This filing may also be viewed on

the Internet at http://www.ferc.fed.us/online/rims.htm (call 202-208-

2222 for assistance).

David P. Boergers,

Secretary.

[FR Doc. 99-17908 Filed 7-13-99; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.