Enfield Operations, L.L.C., et al.; Electric Rate and Corporate Regulation Filings

Federal RegisterNov 24, 1997

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EG98-7-000, et al.]

Enfield Operations, L.L.C., et al.; Electric Rate and Corporate

Regulation Filings

November 17, 1997.

Take notice that the following filings have been made with the

Commission:

1. Enfield Operations, L.L.C.

[Docket No. EG98-7-000]

Take notice that on November 10, 1997, Enfield Operations, L.L.C.,

a limited liability company incorporated and existing under the laws of

the State of Delaware, having its registered office at Corporation

Trust Center, 1209 Orange Street, City of Wilmington, County of New

Castle, State of Delaware (the Applicant), filed with the Federal

Energy Regulatory Commission an application for determination of exempt

wholesale generator (EWG) status pursuant to Part 365 of the

Commission's Regulations.

Applicant states that it will be engaged directly in operating an

eligible facility located near the Plant. The Plant will consist of a

396 MW combined cycle power plant, fueled by natural gas and located in

the Borough of Enfield, North London, England.

Comment date: December 5, 1997, in accordance with Standard

Paragraph E at the end of this notice. The Commission will limit its

consideration of comments to those that concern the adequacy or

accuracy of the application.

2. Wisconsin Public Service Corporation v. Wisconsin Power & Light

Company and Wisconsin Public Power Incorporated SYSTEM

[Docket No. EL98-7-000]

Take notice that on November 6, 1997, Wisconsin Public Service

Corporation tendered for filing a complaint against Wisconsin Power &

Light Company and Wisconsin Public Power Incorporated SYSTEM alleging

that Wisconsin Power and Light Company refuses to file the bypass

amendment in violation of the Federal Power Act and that Wisconsin

Public Power Incorporated SYSTEM is guilty of hoarding scarce

transmission capacity.

Comment date: December 17, 1997, in accordance with Standard

Paragraph E at the end of this notice. Answers to the complaint shall

be due on or before December 17, 1997.

3. Maine Electric Power Company

[Docket No. ER97-4517-000]

Take notice that on November 6, 1997, Maine Electric Power Company

tendered for filing an amendment in the above-referenced docket.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

4. Union Electric Company

[Docket No. ER98-285-000]

Take notice that on October 27, 1997, Union Electric Company

tendered for filing a Notice of Cancellation of Rate Schedule FERC No.

155.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

5. New England Power Company

[Docket No. ER98-366-000]

Take notice that on October 29, 1997, New England Power Company

filed a Service Agreement and Certificates of Concurrence with Wheeled

Electric Power Company, under NEP's FERC Electric Tariff, Original

Volume No. 5.

[[Page 62583]]

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

6. Delmarva Power & Light Company

[Docket No. ER98-367-000]

Take notice that on October 29, 1997, Delmarva Power & Light

Company (Delmarva), tendered for filing a summary of short-term

transactions made during the third quarter of calendar year 1997, under

Delmarva's market rate sales tariff, FERC Electric Tariff, Original

Volume No. 14, filed by Delmarva in Docket No. ER96-2571-000.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

7. Southern Company Services, Inc.

[Docket No. ER98-368-000]

Take notice that on October 29, 1997, Southern Company Services,

Inc. (SCS), acting on behalf of Alabama Power Company, Georgia Power

Company, Gulf Power Company, Mississippi Power Company, and Savannah

Electric and Power Company (collectively referred to as Southern

Company) filed one (1) umbrella service agreement for short-term firm

point-to-point transmission service between SCS, as agent for Southern

Company, and Williams Energy Services Company, under Part II of the

Open Access Transmission Tariff (Tariff) of Southern Company. Southern

Company also filed three (3) umbrella non-firm point-to-point

transmission service agreements under the Tariff between SCS, as agent

for Southern Company, and (i) Oglethorpe Power Corporation, (ii)

Williams Energy Services Company, and (iii) NP Energy, Inc.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

8. Northeast Utilities Service Company

[Docket No. ER98-369-000]

Take notice that on October 29, 1997, Northeast Utilities Service

Company (NUSCO), tendered for filing, a Service Agreement with DPL

Energy, Inc., under the NU System Companies' Sale for Resale, Tariff

No. 7.

NUSCO states that a copy of this filing has been mailed to the DPL

Energy, Inc.

NUSCO requests that the Service Agreement become effective October

23, 1997.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

9. Central Illinois Public Service Company

[Docket No. ER98-371-000]

Take notice that on October 29, 1997, Central Illinois Public

Service Company (CIPS), submitted an executed non-firm point-to-point

service agreement, dated October 17, 1997, establishing Entergy Power

Marketing Corp., as a customer under the terms of CIPS' Open Access

Transmission Tariff.

CIPS requests an effective date of October 17, 1997, for the

service agreement. Accordingly, CIPS requests waiver of the

Commission's notice requirements. Copies of this filing were served on

Entergy Power Marketing Corp., and the Illinois Commerce Commission.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

10. Lowell Cogeneration Company Limited Partnership

[Docket No. ER98-372-000]

Take notice that on October 29, 1997, Lowell Cogeneration Company

Limited Partnership (Lowell), tendered for filing a service agreement

between the New England Power Pool and Lowell for service under

Lowell's FERC Electric Tariff, Original Volume No. 1 (Tariff). This

Tariff was accepted for filing by the Commission on July 17, 1997, in

Docket No. ER97-2414-000.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

11. Yadkin, Inc.

[Docket No. ER98-373-000]

Take notice that on October 29, 1997, Yadkin, Inc., tendered for

filing a summary of activity for the quarter ending September 30, 1997.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

12. Florida Power Corporation

[Docket No. ER98-374-000]

Take notice that on October 29, 1997, Florida Power Corporation

(Florida Power), filed a Cost-Based Wholesale Power Sales Tariff (CR-1)

(Tariff) to permit Florida Power to engage in transactions for capacity

and energy at negotiated rates, subject to a cost-based cap. Florida

Power requests that the Tariff be made effective as of the date it was

filed.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

13. Louisville Gas and Electric Company

[Docket No. ER98-375-000]

Take notice that on October 30, 1997, Louisville Gas and Electric

Company, tendered for filing copies of a service agreement between

Louisville Gas and Electric Company and CMS Marketing, Services and

Trading under Rate GSS.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

14. New England Power Pool

[Docket No. ER98-376-000]

Take notice that on October 30, 1997, the New England Power Pool

Executive Committee filed for acceptance a signature page to the New

England Power Pool (NEPOOL) Agreement dated September 1, 1971, as

amended, signed by Constellation Power Source, Inc., (Constellation).

The NEPOOL Agreement has been designated NEPOOL FPC No. 2.

The Executive Committee states that the Commission's acceptance of

Constellation's signature page would permit NEPOOL to expand its

membership to include Constellation. NEPOOL further states that the

filed signature page does not change the NEPOOL Agreement in any

manner, other than to make Constellation a member in NEPOOL. NEPOOL

requests an effective date of November 1, 1997, for commencement of

participation in NEPOOL by Constellation.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

15. PECO Energy Company

[Docket No. ER98-377-000]

Take notice that on October 30, 1997, PECO Energy Company (PECO),

filed the following documents as part of its amendment to the Code of

Conduct adopted by PECO in connection with the Commission's grant of

market-based rates authorization to PECO in FERC Docket Nos. ER96-640-

000, ER96-641-000 and ER97-316-000:

1. Letter of Transmittal.

2. Clean and redlined copies of the amended Code of Conduct.

Copies of the filing are being sent to the Pennsylvania Public

Utility Commission and all customers with executed agreements under

PECO's FERC Electric Service Tariff--Volume I.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

[[Page 62584]]

16. Duquesne Light Company

[Docket No. ER98-378-000]

Take notice that on October 30, 1997, Duquesne Light Company (DLC),

filed a Service Agreement dated October 28, 1997, with New Energy

Ventures, L.L.C., under DLC's FERC Coordination Sales Tariff (Tariff).

The Service Agreement adds New Energy Ventures, L.L.C., as a customer

under the Tariff. DLC requests an effective date of October 28, 1997,

for the Service Agreement.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

17. Duquesne Light Company

[Docket No. ER98-379-000]

Take notice that on October 30, 1997, Duquesne Light Company (DLC),

filed a Service Agreement dated October 28, 1997, with New Energy

Ventures, L.L.C., under DLC's Open Access Transmission Tariff. The

Service Agreement adds New Energy Ventures, L.L.C., as a customer under

the Tariff. DLC requests an effective date of October 28, 1997, for the

Service Agreement.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

18. Long Island Lighting Company

[Docket No. ER98-381-000]

Take notice that on October 30, 1997, Long Island Lighting Company

(LILCO), filed Electric Power Service Agreements entered into as of the

following dates by LILCO and the following parties:

------------------------------------------------------------------------

Purchaser Service agreement date

------------------------------------------------------------------------

Niagara Mohawk Power Corporation..... July 3, 1996.

Incorporated Village of Freeport..... April 23, 1997.

------------------------------------------------------------------------

The Electric Power Service Agreements listed above were entered

into under LILCO's Power Sales Umbrella Tariff.

LILCO requests that the Commission accept the Electric Power

Service Agreement between LILCO and Niagara Mohawk Power Corporation

with an effective date of October 16, 1996, and the Electric Power

Service Agreement between LILCO and the Incorporated Village of

Freeport with an effective date of May 31, 1997. LILCO has served

copies of this filing on the customers which are a party to each of the

Electric Power Service Agreements and on the New York State Public

Service Commission.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

19. PECO Energy Company

[Docket No. ER98-382-000]

Take notice that on October 30, 1997, PECO Energy Company (PECO)

filed an executed Installed Capacity Obligation Allocation Agreement

between PECO and MC\2\ Inc., (hereinafter Supplier). The terms and

conditions contained within this agreement are identical to the terms

and conditions contained with the Form of Installed Capacity Allocation

Agreement filed by PECO with the Commission on October 3, 1997, at

Docket No. ER98-28-000. This filing merely submits an individual

executed copy of the Installed Capacity Obligation Allocation Agreement

between PECO and an alternate supplier participating in PECO's Pilot.

Copies of the filing were served on the Supplier and the

Pennsylvania Public Utility Commission.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

20. PECO Energy Company

[Docket No. ER98-383-000]

Take notice that on October 27, 1997, PECO Energy Company (PECO),

filed an executed Installed Capacity Obligation Allocation Agreement

between PECO and Delmarva Power & Light d/b/a Connectiv Energy

(hereinafter Supplier). The terms and conditions contained within this

Agreement are identical to the terms and conditions contained with the

Form of Installed Capacity Allocation Agreement filed by PECO with the

Commission on October 3, 1997, at Docket No. ER98-28-000. This filing

merely submits an individual executed copy of the Installed Capacity

Obligation Allocation Agreement between PECO and an alternate supplier

participating in PECO's Pilot.

Copies of the filing were served on the Supplier and the

Pennsylvania Public Utility Commission.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

21. Northern/AES Energy LLC

[Docket No. ER98-445-000]

Take notice that on October 31, 1997, Northern/AES Energy LLC

(Northern/AES), petitioned the Commission for acceptance of Northern/

AES Rate Schedule FERC No. 1; the granting of certain blanket

approvals, including the authority to sell electricity at market-based

rates; and the waiver of certain Commission Regulations.

Northern/AES intends to engage in wholesale electric power and

energy purchases and sales as a marketer. Northern/AES is not in the

business of generating or transmitting electric power. AES Power, Inc.

(AES Power), United Power Association (UPA), and J Power, Inc. (J

Power), own member interests in Northern/AES. AES Power is a marketer

of wholesale electric power and energy. The AES Corporation, the parent

of AES Power, is a developer and owner of independent power projects.

UPA is a generation and transmission cooperative that is regulated by

the Rural Utility Service. J Power is a marketer of wholesale electric

power and energy.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

22. COM/Energy Marketing, Inc.

[Docket No. ER98-449-000]

Take notice that on October 31, 1997, COM/Energy Marketing, Inc.

(CE), tendered for filing pursuant to Rules 205 and 207, a petition for

waivers and blanket approvals under various regulations of the

Commission and for an order accepting its FERC Electric Rate Schedule

No. 1 to be effective December 30, 1997.

CE intends to engage in electric power and energy transactions as a

marketer and a broker. In transactions where CE sells electric energy

it proposes to make such sales on rates, terms and conditions to be

mutually agreed to with the purchasing party.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

23. Bangor Energy Resale, Inc.

[Docket No. ER98-459-000]

Take notice that Bangor Energy Resale, Inc. (Bangor Energy), a

wholly-owned subsidiary of Bangor Hydro-Electric Company, submitted for

filing on October 31, 1997, pursuant to Rule 205 of the Commission's

Rules of Practice and Procedure, 18 CFR 385.205, an application for

waivers and blanket approvals under various regulations of the

Commission and for an order accepting its Electric Rate Schedule FERC

No. 1, a market-based rate schedule.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

24. Bangor Hydro-Electric Company

[Docket No. ER98-463-000]

Take notice that on October 31, 1997, Bangor Hydro Electric Company

(Bangor Hydro) tendered for filing a rate schedule providing for the

sale of energy and capacity to Bangor Energy Resale, Inc., a wholly-

owned subsidiary of Bangor Hydro.

[[Page 62585]]

Copies of this filing were served on the affected state public

utility commissions and UNITIL Power Corporation.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

25. New England Power Company

[Docket No. ER98-466-000]

Take notice that on October 31, 1997, New England Power Company

(NEP), submitted for filing, pursuant to Section 205 of the Federal

Power Act, and Part 35 of the Commission's Regulations, an Amendment to

Service Agreement that would terminate the obligation of the Water and

Light Department of the Town of Littleton, New Hampshire (Littleton) to

purchase from NEP, and the obligation of NEP to supply Littleton,

requirements service pursuant to NEP's FERC Tariff, Original Volume No.

1, and would obligate Littleton to compensate NEP by the payment of

Contract Termination Charges. NEP also filed a Service Agreement for

the provision to Littleton of Network Integration Transmission Service

and a Network Operating Agreement under NEP's open access transmission

tariff. Copies of the filing have been served on the customer, the New

Hampshire Public Utilities Commission and other Tariff 1 customers.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

26. Puget Sound Energy, Inc.

[Docket No. ER98-486-000]

Take notice that on October 31, 1997, Puget Sound Energy, Inc.,

tendered for filing a Service Agreement for Network Integration

Transmission Service pursuant to which Puget Sound Energy will

implement a retail electric direct access pilot program. The pilot

program was approved by the Washington Utilities and Transportation

Commission to allow retail electricity sales by alternate suppliers in

designated portions of Puget Sound Energy's service territory for a

period of limited duration. A copy of the filing was served on the

Washington Utilities and Transportation Commission.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

27. Orange and Rockland Utilities, Inc.

[Docket No. ER98-487-000]

Take notice that on October 30, 1997, Orange and Rockland

Utilities, Inc. (O&R), tendered for filing an amendment to its

agreement with the New York Power Authority (NYPA) dated June 28, 1985.

O&R has served a copy of this filing on the New York State Public

Service Commission and NYPA.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

28. Oklahoma Gas and Electric Company

[Docket No. ER98-511-000]

Take notice that on November 3, 1997, Oklahoma Gas and Electric

Company (OG&E), tendered for filing an initial rate schedule (Power

Sales Tariff) providing for sales of capacity and/or energy at market-

based rates and for the resale of transmission rights that OG&E has

reserved for its own use on its own transmission system or on the

transmission systems of other transmission providers.

Copies of this filing have been sent to the Oklahoma Corporation

Commission and the Arkansas Public Service Commission.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

29. Boston Edison Company

[Docket No. ER98-522-000]

Take notice that on November 3, 1997, Boston Edison Company of

Boston, Massachusetts, tendered for filing a (1) tariff providing for

sales of electric capacity and/or energy at market-based rates and for

the resale of transmission rights, (2) Standards of conduct as to

inter-affiliate transactions, and (3) a form of service agreement and

service specifications. Boston Edison asks that its tariff and related

documents be allowed to become effective January 2, 1998.

Boston Edison states that it has served a copy of the instant

filing upon the Massachusetts Department of Public Utilities and the

Massachusetts Attorney General.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

30. Wolverine Power Supply Cooperative Inc.

[Docket No. ER98-539-000]

Take notice that Wolverine Power Supply Cooperative, Inc.

(Wolverine), on October 30, 1997, tendered for filing an Open Access

Transmission Tariff in compliance with Order No. 888, Order No. 888-A.

Copies of the filing were served on Wolverine's six wholesale power

customers, two existing unbundled transmission customers, and the

Michigan Public Service Commission.

Comment date: December 1, 1997, in accordance with Standard

Paragraph E at the end of this notice.

Standard Paragraph

E. Any person desiring to be heard or to protest said filing should

file a motion to intervene or protest with the Federal Energy

Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426,

in accordance with Rules 211 and 214 of the Commission's Rules of

Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such

motions or protests should be filed on or before the comment date.

Protests will be considered by the Commission in determining the

appropriate action to be taken, but will not serve to make protestants

parties to the proceeding. Any person wishing to become a party must

file a motion to intervene. Copies of this filing are on file with the

Commission and are available for public inspection.

Lois D. Cashell,

Secretary.

[FR Doc. 97-30824 Filed 11-21-97; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.