DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EG97-83-000, et al.]
Corby Power Ltd., et al.; Electric Rate and Corporate Regulation
Filings
September 11, 1997.
Take notice that the following filings have been made with the
Commission:
1. Corby Power Ltd.
[Docket No. EG97-83-000]
On September 8, 1997, Corby Power Ltd. (Corby), filed with the
Federal Energy Regulatory Commission an application for determination
of exempt wholesale generator status pursuant to Part 365 of the
Commission's Regulations.
Corby owns and operates an generating facility with a net capacity
of approximately 350 MW consisting of two 119 MW gas turbines, three
generators, a 114 MW steam turbine and an air-cooled condenser. The
facility is located in Corby, Northampshire, England.
Comment date: October 2, 1997, in accordance with Standard
Paragraph E at the end of this notice.
2. Pennsylvania Power & Light Company
[Docket Nos. ER96-930-000, ER96-931-000, ER96-932-000, and ER96-933-
000]
Take notice that on July 23, 1997, Pennsylvania Power & Light
Company tendered for filing its compliance refund report in the above-
referenced dockets.
Comment date: September 24, 1997, in accordance with Standard
Paragraph E at the end of this notice.
3. New York State Electric & Gas Corporation
[Docket No. ER96-3139-000]
Take notice that on August 19, 1997, New York State Electric & Gas
Corporation tendered for filing a Notice of Withdrawal in the above-
referenced docket.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
[[Page 49004]]
4. Illinois Power Company
[Docket No. ER97-1827-001]
Take notice that on August 7, 1997, Illinois Power Company tendered
for filing a compliance filing in the above-referenced docket.
Comment date: September 24, 1997, in accordance with Standard
Paragraph E at the end of this notice.
5. Duke Power Division of Duke Energy Corp.
[Docket No. ER97-2398-000]
Take notice that on August 11, 1997, Duke Power Division of Duke
Energy Corp., tendered for filing an amendment in the above-referenced
docket.
Comment date: September 24, 1997, in accordance with Standard
Paragraph E at the end of this notice.
6. DPL Energy, Inc.
[Docket No. ER97-3040-000]
Take notice that on September 3, 1997, DPL Energy, Inc., tendered
for filing an amendment in the above-referenced docket.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
7. Dayton Power and Light Company
[Docket No. ER97-3041-000]
Take notice that on September 3, 1997, Dayton Power and Light
Company tendered for filing an amendment in the above-referenced
docket.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
8. R. Hadler and Company, Inc.
[Docket No. ER97-3056-000]
Take notice that on August 29, 1997, R. Hadler and Company tendered
for filing an amendment in the above-referenced docket.
Comment date: Septemer 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
9. Soyland Power Cooperative, Inc.
[Docket No. ER97-3090-001]
Take notice that on August 7, 1997, Soyland Power Cooperative, Inc.
tendered for filing a compliance filing in the above-referenced docket.
Comment date: September 24, 1997, in accordance with Standard
Paragraph E at the end of this notice.
10. Central Illinois Public Service Company
[Docket No. ER97-3393-000]
Take notice that on September 5, 1997, Central Illinois Public
Service Company (CIPS) filed an amendment to its June 20, 1997, filing
in this proceeding.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
11. Sierra Pacific Power Company
[Docket No. ER97-3593-000]
Take notice that on September 2, 1997, Sierra Pacific Power Company
tendered for filing an amendment in the above-referenced docket.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
12. Electrical Association Power Marketing, Inc.
[Docket No. ER97-4173-000]
Take notice that on August 12, 1997, Electrical Association Power
Marketing, Inc., tendered for filing a petition for acceptance of rate
schedule and waivers of blanket authority.
Comment date: September 24, 1997, in accordance with Standard
Paragraph E at the end of this notice.
13. El Paso Electric Company
[Docket No. ER97-4212-000]
Take notice that on August 15, 1997, El Paso Electric Company (El
Paso) tendered for filing an Index of Non-Firm Point-to-Point
Transmission Service Customers and an Index of Firm Point to Point
Transmission Service Customers under its open access transmission
service tariff. El Paso tendered for filing service agreements for non-
firm point-to-point transmission service under its open access
transmission tariff to the following customers:
Aquila Power Corporation
Arizona Public Service Company
Citizens Lehman Power Sales
Coral Power LLC
e prime, Inc.
El Paso Electric Company
Electric Clearinghouse, Inc.
Idaho Power Company
Minnesota Power & Light Company
PacifiCorp
PanEnergy Trading & Market Services LLC
Public Service Company of New Mexico
Salt River Project
Southern Energy Trading and Marketing, Inc.
Southwestern Public Service Company
Valero Power Services Company
Williams Energy Services Company
Comment date: September 24, 1997, in accordance with Standard
Paragraph E at the end of this notice.
14. Union Electric Company
[Docket No. ER97-4300-000]
Take notice that on August 22, 1997, Union Electric Company (UE),
tendered for filing Service Agreements for Firm Point-to-Point
Transmission Services between UE and Citizens Power Sales, Enron Power
Marketing, Inc., Entergy Operating Companies, Minnesota Power & Light
Company, NorAm Energy Services, Inc., PECO Energy Company--Power Team
and Wisconsin Electric Power Company. UE asserts that the purpose of
the Agreements is to permit UE to provide transmission service to the
parties pursuant to UE's Open Access Transmission Tariff filed in
Docket No. OA96-50.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
15. Union Electric Company
[Docket No. ER97-4301-000]
Take notice that on August 22, 1997, Union Electric Company (UE),
tendered for filing a Service Agreement for Non-Firm Point-to-Point
Transmission Service between NP Energy Inc. (NP) and UE. UE asserts
that the purpose of the Agreement is to permit UE to provide
transmission service to NP pursuant to UE's Open Access Transmission
Tariff filed in Docket No. OA96-50.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
16. Consolidated Edison Company
[Docket No. ER97-4303-000]
Take notice that on August 22, 1997, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing a service agreement to
provide non-firm transmission service pursuant to its Open Access
Transmission Tariff to ProMark Energy (ProMark).
Con Edison states that a copy of this filing has been served by
mail upon ProMark.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
17. Rochester Gas and Electric Corporation
[Docket No. ER97-4304-000]
Take notice that on August 22, 1997, Rochester Gas and Electric
Corporation (RG&E) filed a Service Agreement between RG&E and the
Virginia Power (Customer). This Service Agreement specifies that the
Customer has agreed to the rates, terms and conditions of the RG&E open
access transmission tariff filed on July 9, 1996 in Docket No. OA96-
141-000.
RG&E requests waiver of the Commission's sixty (60) day notice
requirements and an effective date of August 15, 1997 for the Virginia
Power Service Agreement. RG&E has served
[[Page 49005]]
copies of the filing on the New York State Public Service Commission
and on the Customer.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
18. Consolidated Edison Company of New York, Inc.
[Docket No. ER97-4305-000]
Take notice that on August 22, 1997, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing a service agreement to
provide non-firm transmission service pursuant to its Open Access
Transmission Tariff to Constellation Power Source, Inc. (CPS).
Con Edison states that a copy of this filing has been served by
mail upon CPS.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
19. Louisville Gas and Electric Company
[Docket No. ER97-4306-000]
Take notice that on August 22, 1997, Louisville Gas and Electric
Company (LG&E), tendered for filing an executed Non-Firm Point-to-Point
Transmission Service Agreement between LG&E and NESI Power Marketing,
Inc. under LG&E's Open Access Transmission Tariff.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
20. Central Hudson Gas and Electric Corporation
[Docket No. ER97-4307-000]
Take notice that on August 22, 1997, Central Hudson Gas and
Electric Corporation (CHG&E), tendered for filing pursuant to 35.12 of
the Federal Energy Regulatory Commission's (Commission) Regulations in
18 CFR a Service Agreement between CHG&E and Energy Transfer Group. The
terms and conditions of service under this Agreement are made pursuant
to CHG&E's FERC Electric Rate Schedule, Original Volume No. 1 (Power
Sales Tariff) accepted by the Commission in Docket No. ER97-890-000.
CHG&E also has requested waiver of the 60-day notice provision pursuant
to 18 CFR 35.11.
A copy of this filing has been served on the Public Service
Commission of the State of New York.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
21. Portland General Electric Company
[Docket No. ER97-4308-000]
Take notice that on August 22, 1997, Portland General Electric
Company (PGE), tendered for filing its Average System Cost (ASC) as
calculated by PGE and determined by the Bonneville Power Administration
under the revised ASC Methodology which became effective on October 1,
1984. This filing includes PGE's revised Appendix 1 of the Residential
Purchase and Sale Agreement.
PGE states that the revised Appendix 1 shows the ASC to be 35.32
mills/kWh effective December 1, 1996. The Bonneville Power
Administration determined the ASC rate for PGE to be 34.67 mills/kWh.
However, there is no effect on the residential exchange payments
because the amount for fiscal year 1997 was fixed by federal
legislation.
Copies of the filing have been served on the persons named in the
transmittal letter as included in the filing.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
22. Maine Electric Power Company
[Docket No. ER97-4309-000]
Take notice that on August 22, 1997, Maine Electric Power Company
(MEPCO), tendered for filing a service agreement for Firm Point-to-
Point Transmission service entered into with Enron Power Marketing,
Inc. Service will be provided pursuant to MEPCO's Open Access
Transmission Tariff, designated rate schedule MEPCO--FERC Electric
Tariff, Original Volume No. 1, as supplemented.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
23. Aroostook Valley Electric Company
[Docket No. ER97-4310-000]
Take notice that on August 22, 1997, Aroostook Valley Electric
Company (AVEC), submitted to the Federal Energy Regulatory Commission
and other interested persons a Second Amendment to Power Purchase
Agreement with Central Maine Power Company (CMP). Also submitted is the
Certificate of Concurrence of CMP to such Second Amendment to Power
Purchase Agreement.
The Second Amendment to Power Purchase Agreement extends the
expiring term of the existing Power Purchase Agreement from October 1,
1997 through October 31, 1999.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
24. Maine Public Service Company
[Docket No. ER97-4311-000]
Take notice that on August 22, 1997, Maine Public Service Company
(Maine Public), filed an executed Service Agreement for non-firm point-
to-point transmission service under Maine Public's open access
transmission tariff with NP Energy Inc.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
25. Maine Public Service Company
[Docket No. ER97-4312-000]
Take notice that on August 22, 1997, Maine Public Service Company
(Maine Public) filed an executed Service Agreement for non-firm point-
to-point transmission service under Maine Public's open access
transmission tariff with Williams Energy Services Company.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
26. Midwest Energy, Inc.
[Docket No. ER97-4313-000]
Take Notice that on August 22, 1997, Midwest Energy, Inc.
(Midwest), tendered for filing with the Federal Energy Regulatory
Commission the Service Agreement for Non-Firm Point-to-Point
Transmission Service entered into between Midwest and Constellation
Power Source, Inc.
Midwest states that it is serving copies of the instant filing to
its customers, State Commissions and other interested parties.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
27. Old Dominion Electric Cooperative
[Docket No. ER97-4314-000]
Take notice that on August 22, 1997, Old Dominion Electric
Cooperative (Old Dominion), filed a Petition for blanket authority to
sell power at market-based rates to non-affiliated entities and to its
distribution cooperative members. Old Dominion's Petition is filed
pursuant to 205 of the Federal Power Act and Rules 205 and 207 of the
Commission's Rules of Practice and Procedure, 18 CFR 385.205 and
385.207. Old Dominion also seeks waiver of the cost-of-service filing
requirements of 18 CFR 35.12 and 35.13, and the 60-day notice
requirement of 18 CFR 35.3 in order to permit Old Dominion to commence
sales of power at market-based rates as of the earlier of 60 days from
the date of the filing of its Petition or the date of an order
accepting its market-based rate schedule.
[[Page 49006]]
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
28. Maine Electric Power Company
[Docket No. ER97-4315-000]
Take notice that on August 22, 1997, Maine Electric Power Company
(MEPCO), tendered for filing a service agreement for Non-Firm Point-to-
Point transmission service entered into with Pro Mark Energy. Service
will be provided pursuant to MEPCO's Open Access Transmission Tariff,
designated rate schedule MEPCO--FERC Electric Tariff, Original Volume
No. 1, as supplemented.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
29. Maine Electric Power Company
[Docket No. ER97-4316-000]
Take notice that on August 22, 1997, Maine Electric Power Company
(MEPCO), tendered for filing a service agreement for Non-Firm Point-to-
Point transmission service entered into with Tractebel Energy
Marketing, Inc. Service will be provided pursuant to MEPCO's Open
Access Transmission Tariff, designated rate schedule MEPCO--FERC
Electric Tariff, Original Volume No. 1, as supplemented.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
30. Central Maine Power Company
[Docket No. ER97-4317-000]
Take notice that on August 22, 1997, Central Maine Power Company
(CMP), tendered for filing a service agreement for Non-Firm Point-to-
Point Transmission service entered into with NP Energy Inc. Service
will be provided pursuant to CMP's Open Access Transmission Tariff,
designated rate schedule CMP--FERC Electric Tariff, Original Volume No.
3, as supplemented.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
31. Maine Electric Power Company
[Docket No. ER97-4318-000]
Take notice that on August 22, 1997, Maine Electric Power Company
(MEPCO), tendered for filing a service agreement for Non-Firm Point-to-
Point transmission service entered into with PECO Energy Company.
Service will be provided pursuant to MEPCO's Open Access Transmission
Tariff, designated rate schedule MEPCO--FERC Electric Tariff, Original
Volume No. 1, as supplemented.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
32. Maine Electric Power Company
[Docket No. ER97-4319-000]
Take notice that on August 22, 1997, Maine Electric Power Company
(MEPCO), tendered for filing a service agreement for Non-Firm Point-to-
Point transmission service entered into with NP Energy Inc. Service
will be provided pursuant to MEPCO's Open Access Transmission Tariff,
designated rate schedule MEPCO--FERC Electric Tariff, Original Volume
No. 1, as supplemented.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
33. San Diego Gas & Electric Company
[Docket No. ER97-4320-000]
Take notice that on August 22, 1997, San Diego Gas & Electric
Company (SDG&E), tendered for filing a Notice of Cancellation for the
following:
1. Rate Schedule FERC No. 96--Coordination Agreement between San
Diego Gas & Electric Company and Eclipse Energy, Inc., executed June
20, 1994, to be terminated October 31, 1997;
2. Rate Schedule FERC No. 115--Coordination Agreement between San
Diego Gas & Electric Company and Utility-2000 Energy Corp. Executed May
5, 1995, to be terminated October 31, 1997; and
3. Service Agreement for Firm Point-to-Point Transmission Service
between San Diego Gas & Electric Company and San Diego Gas & Electric
Company--Energy Trading, dated June 30, 1997, to be terminated August
1, 1997.
Comment date: September 25, 1997, in accordance with Standard
Paragraph E at the end of this notice.
34. Vastar Resources, Inc.; Vastar Gas Marketing, Inc.; Vastar Power
Marketing, Inc.; Vastar Energy, Inc.; SEI Holdings, Inc.; Southern
Energy North America, Inc.; Southern Energy Trading and Marketing, SC
Ashwood Holdings, Inc.; SC Energy Ventures, Inc.; Southern Company
Energy Marketing L.P.; Southern Company Energy Marketing G.P., L.L.C.
[Docket No. EC97-49-000]
Take notice that on September 9, 1997, the above-captioned parties
(Applicants) filed an amendment to their application under Section 203
of the Federal Power Act.
Comment date: October 7, 1997, in accordance with Standard
Paragraph E at the end of this notice.
Standard Paragraph:
E. Any person desiring to be heard or to protest said filing should
file a motion to intervene or protest with the Federal Energy
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426,
in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such
motions or protests should be filed on or before the comment date.
Protests will be considered by the Commission in determining the
appropriate action to be taken, but will not serve to make protestants
parties to the proceeding. Any person wishing to become a party must
file a motion to intervene. Copies of this filing are on file with the
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 97-24818 Filed 9-17-97; 8:45 am]
BILLING CODE 6717-01-P
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.