DEPARTMENT OF ENERGY
Final Environmental Impact Statement (EIS) for the Hanford Site
Tank Waste Remediation System, Richland, WA
AGENCY: Department of Energy and Washington State Department of
Ecology.
ACTION: Notice of availability.
-----------------------------------------------------------------------
SUMMARY: The U.S. Department of Energy (DOE) and the Washington State
Department of Ecology (Ecology) announce the availability of a Final
EIS entitled ``Tank Waste Remediation System at the Hanford Site,
Richland, Washington'' (DOE/EIS-0189). DOE and Ecology co-prepared the
EIS. DOE and Ecology revised the information in the Draft EIS in
response to public comments and to reflect new environmental
information that became available after the Draft EIS was issued in
April 1996.
The EIS evaluates the potential environmental impacts of DOE's
proposed action as well as reasonable alternatives for management and
disposal of mixed, radioactive, and hazardous waste currently or
projected to be stored in 177 underground storage tanks and in
approximately 60 active and inactive miscellaneous underground storage
tanks that were associated with Hanford's tank farm operations. In
addition, the EIS evaluates the management and potential disposal of
approximately 1,930 cesium and strontium capsules currently on loan or
stored at the Hanford Site.
ADDRESSES: Requests for copies of the Final EIS and for further
information on the Final EIS should be directed to Ms. Carolyn Haass,
DOE TWRS EIS NEPA Document Manager, U.S. Department of Energy, Richland
Operations Office, P.O. Box 1249, Richland, WA 99352. Requests for
copies of the Draft EIS also can be made via the Internet at
[email protected] or by calling Ecology's Hanford Information
Line at 1-800-321-2008. Addresses of locations where the Final EIS will
be available for public review are listed in this notice under ``DOE
Reading Rooms and Information Repositories.'' The Final EIS is also
available for review on the Internet at www.hanford.gov.
General information on the DOE National Environmental Policy Act
(NEPA) process may be requested from Ms. Carol Borgstrom, Director,
Office of NEPA Policy and Assistance (EH-42), U.S. Department of
Energy, 1000 Independence Avenue, SW., Washington, DC 20585. Ms.
Borgstrom may be contacted by telephone at (202) 586-4600 or by leaving
a message at 1-800-472-2756.
SUPPLEMENTARY INFORMATION:
Background
DOE and Ecology issued a Draft EIS for public comment and published
a Notice of Availability in the Federal Register on April 15, 1996 (61
FR 16471). EPA published a Notice of Availability in the Federal
Register on April 12, 1996 (61 FR 16248). Public hearings on the Draft
EIS were held in Pasco, Washington on May 2, 1996; Portland, Oregon on
May 9, 1996; Arlington, Virginia on May 7, 1996; Spokane, Washington on
May 15, 1996; and Seattle, Washington on May 22, 1996. All written and
oral comments on the Draft EIS received during the 45 day public
comment period were assessed and considered by DOE and Ecology both
individually and collectively. Comment letters, transcripts of oral
comments, and transcripts of public hearings and meetings are available
for review at locations listed in this notice under ``DOE Reading Rooms
and Information Repositories.''
DOE requested the National Academy of Science to review and comment
on the TWRS Draft EIS. DOE will carefully consider all comments
provided by the National Academy of Science and the public in the
Record of Decision.
DOE and Ecology revised the information in the Draft EIS in
response to public comments and to reflect new environmental
information that became available after the Draft EIS was issued.
Appendix L contains oral and written comments and DOE and Ecology's
responses to the comments. Responses to comments included appropriate
revisions of the EIS, answers to questions, explanations of technical
issues, references to information in other DOE environmental impact
statements, references to information provided in the Draft EIS,
explanations of the relationship of this EIS to other related DOE NEPA
documents, statements of government policy, or indications that the
comment was outside the scope of this EIS.
The Final EIS has been filed with the Environmental Protection
Agency (EPA) and has also been distributed to Federal, State, and local
officials, Tribal Nations, as well as agencies, organizations, and
individuals who may be interested or affected. The Final EIS and
supporting technical reports also are available for public review in
DOE reading rooms and designated information repository locations
identified in this notice. DOE plans to issue a Record of Decision on
the EIS no sooner than 30 days after publication of EPA's notice of
availability of the Final EIS in the Federal Register (i.e., no sooner
than September 30, 1996).
Alternatives Considered
The Final EIS evaluates ten tank waste alternatives in detail:
No Action--perform minimum activities required for safe
and secure management of Hanford's tank wastes with the current tank
farm configuration;
Long-Term Management--perform minimum activities required
for safe and secure management of Hanford's tank waste including
upgrades to tank farms with the current single-shell tank farm
configuration and the replacement of the double-shell tanks twice
during a 100-year period;
In Situ Fill and Cap--retrieve and evaporate liquid waste
from the double-shell tanks, then fill all tanks with gravel and cover
the tank farms with an earthen surface barrier, disposing of all tank
waste onsite;
In Situ Vitrification--retrieve and evaporate liquid waste
from the double-shell tanks, then vitrify all of the tank
[[Page 45950]]
farms and cover the tank farms with an earthen surface barrier,
disposing of all tank waste onsite;
Ex Situ No Separations--retrieve all tank farm waste
practicable (assumed to be 99 percent), then either vitrify or calcine
the waste and package the treated waste form for onsite storage and
eventual offsite disposal at a geologic repository;
Ex Situ Intermediate Separations--retrieve all tank farm
waste (99 percent) and separate the high-level and low-activity waste
streams using sludge washing and ion exchange, then vitrify the waste
streams in separate facilities and package the treated waste form for
onsite disposal of immobilized low-activity waste and offsite disposal
of the immobilized high-level waste at a geologic repository;
Ex Situ Extensive Separations--retrieve all tank farm
waste (99 percent) and separate into high-level and low-activity waste
streams using sludge wash, ion exchange, caustic leach and acid
dissolution, then vitrify the waste streams in separate facilities and
package the treated waste form for onsite disposal of the immobilized
low-activity waste and onsite storage and eventual offsite disposal of
the immobilized high-level waste at a geologic repository;
Ex Situ/In Situ Combination 1--retrieve waste from 70
tanks based on the potential long-term risks to human health or the
environment, separate the retrieved waste into high-level and low-
activity waste streams using sludge washing and ion exchange, then
vitrify the waste streams in separate facilities and package the
treated waste form for onsite disposal of the immobilized low-activity
waste and onsite storage and eventual offsite disposal of the
immobilized high-level waste at a geologic repository. Fill all tanks,
including those with waste that had not been retrieved, with gravel,
and cover the tanks with a barrier, permanently disposing of the waste
in-place;
Ex Situ/In Situ Combination 2--retrieve waste from 25
tanks based on the potential long-term risks to human health or the
environment, separate the retrieved waste into high-level and low-
activity waste streams using sludge washing and ion exchange, then
vitrify the waste streams in separate facilities and package the
treated waste form for onsite disposal of the immobilized low-activity
waste and onsite storage and eventual offsite disposal of the
immobilized high-level waste at a geologic repository. Fill all tanks,
including those with waste that had not been retrieved, with gravel,
and cover the tanks with a barrier, permanently disposing of the waste
in-place; and
Phased Implementation--for Phase 1, construct commercial
demonstration-scale facilities that would include one low-activity
waste separations and vitrification demonstration plant and one low-
activity and high-level waste vitrification demonstration plant to
operate for up to 10 years. These facilities could treat up to 30
percent of the tank waste by volume during the 10-year operating
period. For Phase 2, construct larger capacity separations and
vitrification plants, retrieve the remaining waste, separate the waste
into low-activity and high-level waste streams, vitrify the waste in
separate facilities, package the waste, and dispose of the low-activity
waste onsite in near-surface vaults and the high-level waste offsite at
a geologic repository.
The cesium and strontium capsules are currently classified as waste
by-product and are therefore available for beneficial uses. If
beneficial uses cannot be found, the capsules would be subject to
management and disposal actions as high-level waste. As in the Draft
EIS, cesium and strontium capsule alternatives analyzed in the Final
EIS are:
No Action--Continue existing operations and maintenance in
the Hanford Site Waste Encapsulation and Storage Facility for 10 years;
Onsite Disposal--overpack the cesium and strontium in
canisters and store onsite indefinitely in a newly constructed dry-well
storage facility;
Overpack and Ship--overpack the cesium and strontium into
canisters, which would then be overpacked into Multi-Purpose Canisters,
and dispose of offsite at the proposed national high-level waste
repository; and
Vitrify with Tank Waste--remove capsule contents and
vitrify with the high-level tank waste, place in Multi-Purpose
Canisters, and dispose of offsite at a geologic repository.
Preferred Alternatives
DOE and Ecology's preferred tank waste alternative in the EIS is
the Phased Implementation alternative. DOE and Ecology's preferred
alternative for the Hanford Site's cesium and strontium capsules is the
No Action alternative.
Availability of Copies of the Final EIS
Copies of the Final EIS are being distributed to Federal, State,
and local officials and agencies; to organizations and individuals
known to be interested in the EIS; and to persons and agencies that
commented on the Draft EIS. Additional copies may be obtained by
contacting Ms. Carolyn Haass, DOE TWRS EIS NEPA Document Manager, U.S.
Department of Energy, Richland Operations Office, P.O. Box 1249,
Richland, Washington 99352. Requests for copies also can be made via
the Internet at:
[email protected] or by calling Ecology's Hanford
Information Line at 1-800- 321-2008. Addresses of DOE Public Reading
Rooms and Information Repositories where the EIS and reference
documents will be available for public review are listed below:
Summary of the EIS
Summary:
Summary of the alternatives and analysis presented in the EIS
Volume One:
Main Text of the Tank Waste Remediation System EIS
Volume Two:
Appendices Supporting Volume One
Appendix A. Waste Inventory
Appendix B. Description of Alternatives
Appendix C. Alternatives Rejected from Analysis
Volume Three:
Appendix Supporting Volume One
Appendix D. Anticipated Health and Ecological Risks
Volume Four:
Appendices Supporting Volume One
Appendix E. Accident Risks
Appendix F. Groundwater Modeling
Volume Five:
Appendices Supporting Volume One
Appendix G. Air Quality Modeling
Appendix H. Socioeconomic Impact Modeling
Appendix I. Affected Environment
Appendix J. Consultation Letters
Appendix K. Uncertainties Analysis
Volume Six:
Appendix Containing Comments and DOE and Ecology Responses and
Supporting Changes to the Summary and Volumes One through Six made in
Response to Comments
Appendix L. Comments and Agency Responses
The Summary of the EIS is available for those who do not wish to
receive the entire Final EIS. When requesting copies of the Final EIS,
please indicate whether you wish to receive only the Summary (50
pages), the Summary and Volume One (620 pages), or the entire EIS,
including the appendices (3,100 pages).
DOE Public Reading Rooms and Information Repositories
University of Washington, Suzzallo Library, Government Publications
[[Page 45951]]
Room, Seattle, WA 98185. (206) 685-9855, Monday-Thursday 9:00 a.m. to
8:00 p.m., Friday and Saturday 9:00 a.m. to 5:00 p.m.
Gonzaga University, Foley Center, E. 502 Boone, Spokane, WA 99258.
(509) 328-4220 ext. 3829, Monday-Thursday 8:00 a.m. to midnight, Friday
8:00 a.m. to 9:00 p.m., Saturday 9:00 a.m. to 9:00 p.m., Sunday 11:00
a.m. to midnight.
U.S. Department of Energy Reading Room, Washington State University,
Tri-Cities Campus, 100 Sprout Road, Room 130W, Richland, WA 99352,
(509) 376-8583, Monday-Friday 10:00 a.m. to 4:00 p.m.
Portland State University, Bradford Price Millar Library, Science and
Engineering Floor, S.W. Harrison and Park, Portland, OR 97207, (503)
725-3690, Monday-Friday 8:00 a.m. to 10:00 p.m., Saturday 10:00 a.m. to
10:00 p.m., Sunday 11:00 a.m. to 10:00 p.m.
U.S. Department of Energy, Headquarters, Freedom of Information Public
Reading Room, 1E-190 Forrestal Building, 1000 Independence Avenue, SW,
Washington, D.C. 20585, (202) 586-6020, Monday-Friday 9:00 a.m. to 4:00
p.m.
Issued in Washington, D.C., this day August 26, 1996.
Stephen P. Cowan,
Deputy Assistant Secretary for Waste Management.
[FR Doc. 96-22186 Filed 8-29-96; 8:45 am]
BILLING CODE 6450-01-P