ENVIRONMENTAL PROTECTION AGENCY
40 CFR Part 52
[CA 78-2-6824; FRL-5162-4]
Approval and Promulgation of Implementation Plans; California
Implementation Plan Revision; South Coast Air Quality Management
District
AGENCY: Environmental Protection Agency (EPA).
ACTION: Notice of proposed rulemaking.
-----------------------------------------------------------------------
SUMMARY: EPA is proposing to conditionally approve revisions to the
California State Implementation Plan (SIP) which concern the control of
oxides of nitrogen (NOX) and oxides of sulfur (SOX) emissions
using an emissions-limiting economic incentives program, the NOX
and SOX Regional Clean Air Incentives Market (NOX and
SOX RECLAIM). This program, which consists of twelve rules and
associated appendices known as Regulation XX, applies to facilities in
the South Coast Air Quality Management District (SCAQMD) with four or
more tons of NOX or SOX emissions per year from permitted
equipment. The subject facilities, in order to meet annual emission
reduction requirements, will participate in an economic incentive
program (EIP) in order to reduce emissions at a significantly lower
cost.
The intended effect of proposing approval of Regulation XX is to
regulate emissions of NOX and SOX in accordance with the
requirements of the Clean Air Act, as amended in 1990 (CAA or the Act).
EPA's final action on this notice of proposed rulemaking (NPRM) will
incorporate this regulation into the federally approved SIP. EPA has
evaluated this regulation and is proposing to conditionally approve it
under provisions of the CAA regarding EPA action on SIP submittals,
SIPs for national primary and secondary ambient air quality standards
and plan requirements for nonattainment areas. The EPA's final
conditional approval is contingent on the SCAQMD providing the Agency
with an enforceable commitment which addresses and cures all of the
deficiencies associated with NOX and SOX RECLAIM within 12
months of the publication of the proposed conditional approval. In the
event that SCAQMD fails to provide EPA with such a commitment, then EPA
will publish a final rule to approve NOX and SOX RECLAIM in
the form of a limited approval/limited disapproval action. Both the
conditional approval action and the limited approval/limited
disapproval action are discussed in this NPRM.
DATES: Comments must be received on or before March 30, 1995.
ADDRESSES: Comments may be mailed to: Daniel A. Meer, Rulemaking
Section (A-5-3), Air and Toxics Division, U.S. Environmental Protection
Agency, Region IX, 75 Hawthorne Street, San Francisco, CA 94105.
Copies of the new regulation and EPA's evaluation report of the
regulation are available for public inspection at EPA's Region 9 office
(address above) during normal business hours. Copies of the submitted
regulation are also available for inspection at the following
locations:
California Air Resources Board, Stationary Source Division, Rule
Evaluation Section, 2020 ``L'' Street, Sacramento, CA 95814.
South Coast Air Quality Management District, 21865 E. Copley Drive,
Diamond Bar, CA 91765-4182.
FOR FURTHER INFORMATION CONTACT: Kenneth Israels, Rulemaking Section
(A-5-3), Air and Toxics Division, [[Page 10820]] Environmental
Protection Agency, 75 Hawthorne Street, San Francisco, CA 94105,
Telephone: (415) 744-1194.
SUPPLEMENTARY INFORMATION:
Background
On November 15, 1990, the Clean Air Act Amendments of 1990 (CAA)
were enacted. Pub. L. 101-549, 104 Stat. 2399, codified at 42 U.S.C.
7401-7671q. The air quality planning requirements for the reduction of
NOX emissions through reasonably available control technology
(RACT) are set out in section 182(f) of the CAA. On November 25, 1992,
EPA published a NPRM entitled ``State Implementation Plans; Nitrogen
Oxides Supplement to the General Preamble; Clean Air Act Amendments of
1990 Implementation of Title I; Proposed Rule,'' (the NOX
Supplement) which describes the requirements of section 182(f). The
November 25, 1992, notice should be referred to for further information
on the NOX requirements and is incorporated into this proposal by
reference.
Section 182(b)(2) requires submittal of RACT rules for major
stationary sources of VOC emissions (not covered by a pre-enactment
control technologies guidelines (CTG) document or a post-enactment CTG
document) by November 15, 1992. There were no NOX CTGs issued
before enactment and EPA has not issued a CTG document for any NOX
sources since enactment of the CAA. The RACT rules covering NOX
sources and submitted as SIP revisions are expected to require final
installation of the actual NOX controls by May 31, 1995, for those
sources where installation by that date is practicable. Section 182(f)
of the Clean Air Act requires States to apply the same requirements to
major stationary sources of NOX (``major'' as defined in section
302 and section 182 (c), (d), and (e)) as are applied to major
stationary sources of volatile organic compounds (VOCs), in moderate or
above ozone nonattainment areas. The Los Angeles-South Coast Air Basin
is classified as extreme,1 therefore this area was subject to the
RACT requirements of section 182(b)(2), cited above, and the November
15, 1992 deadline.2
\1\The Los Angeles-South Coast Air Basin was designated
nonattainment and classified by operation of law pursuant to
sections 107(d) and 181(a) upon the date of enactment of the CAA.
See 55 FR 56694 (November 6, 1991).
\2\EPA made a finding of nonsubmittal for NOX RACT in
SCAQMD on April 21, 1993. NOX RECLAIM in combination with other
measures satisfy this requirement. On October 21, 1994, EPA found
that SCAQMD had submitted measures satisfying the NOX RACT
requirements.
---------------------------------------------------------------------------
On April 7, 1994, EPA published a final rule concerning EIPs
entitled ``Economic Incentive Program Rules,'' (EIP Rules) in order to
fulfill the requirements of section 182(g)(4)(A) of the Act (see 59 FR
16690). The EIP Rules establish several requirements which State
programs must meet.
These requirements are:
Statement of goals and rationale. This element shall
include a clear statement as to the environmental problem being
addressed, the intended environmental and economic goals of the
program, and the rationale relating the incentive-based strategy to the
program goals.
Program scope. This element shall contain a clear
definition of the sources affected by the program.
Program baseline. A program baseline shall be defined as a
basis for projecting program results and, if applicable, for
initializing the incentive mechanism (e.g., for marketable permits
programs). The program baseline shall be consistent with, and
adequately reflected in, the assumptions and inputs used to develop an
area's reasonable further progress (RFP) plans and attainment and
maintenance demonstrations, as applicable. The State shall provide
sufficient supporting information from the areawide emissions inventory
and other sources to justify the baseline used in the State or local
EIP.
Replicable emission quantification methods. This program
element, for programs other than those which are categorized as
directionally-sound, shall include credible, workable, and replicable
methods for projecting program results from affected sources and, where
necessary, for quantifying emissions from individual sources subject to
the EIP. Such methods, if used to determine credit taken in attainment,
RFP, and maintenance demonstrations, as applicable, shall yield results
which can be shown to have a level of certainty comparable to that for
source-specific standards and traditional methods of control strategy
development.
Source requirements. This program element shall include
all source-specific requirements that constitute compliance with the
program. Such requirements shall be appropriate, readily ascertainable,
and State and federally enforceable.
Projected results and audit/reconciliation procedures.
This program element includes a commitment to ensure the timely
implementation of programmatic revisions or other measures which the
State, in response to the audit, deems necessary for the successful
operation of the program in the context of overall RFP and attainment
requirements. (see 40 CFR 51.493(f)(3)(i))
Implementation schedule. The program shall contain a
schedule for the adoption and implementation of all State commitments
and source requirements included in the program design.
Administrative procedures. The program shall contain a
description of State commitments which are integral to the
implementation of the program, and the administrative system to be used
to implement the program, addressing the adequacy of the personnel,
funding, and legislative authority.
Enforcement mechanisms. The program shall contain a
compliance instrument(s) for all program requirements, which is legally
binding and enforceable by both the State and EPA. This program element
shall also include a State enforcement program which defines
violations, and specifies auditing and inspections plans and provisions
for enforcement actions. The program shall contain effective penalties
for noncompliance which preserve the level of deterrence in traditional
programs. For all such programs, the manner of collection of penalties
must be specified.
The EIP Rule should be referred to for further information on the
EIP requirements and is incorporated into this proposal by reference.
The State of California submitted the regulation being acted on in
this document on March 21, 1994. This document addresses EPA's proposed
action for SCAQMD, Regulation XX, NOX and SOX RECLAIM. SCAQMD
adopted Regulation XX on October 15, 1993. This submitted regulation
was found to be complete on April 11, 1994, pursuant to EPA's
completeness criteria that are set forth in 40 CFR Part 51, Appendix
V,3 and is being proposed for approval into the SIP.
\3\EPA adopted the completeness criteria on February 16, 1990
(55 FR 5830) and, pursuant to section 110(k)(1)(A) of the CAA,
revised the criteria on August 26, 1991 (56 FR 42216).
---------------------------------------------------------------------------
NOX emissions contribute to the production of ground level
ozone and smog. The regulation was adopted as part of SCAQMD's efforts
to achieve the National Ambient Air Quality Standards (NAAQS) for ozone
and in response to the CAA requirements cited above. The following is
EPA's evaluation and proposed action for this regulation.
EPA Evaluation and Proposed Action
In determining the approvability of a NOX regulation, EPA must
evaluate the [[Page 10821]] regulation for consistency with the
requirements of the CAA and EPA regulations, as found in section 110
and Part D of the CAA and 40 CFR Part 51 (Requirements for Preparation,
Adoption, and Submittal of Implementation Plans). The EPA
interpretation of these requirements, which forms the basis for today's
action, appears in the various EPA policy guidance documents.4
Among these provisions is the requirement that a NOX rule must, at
a minimum, provide for the implementation of RACT for stationary
sources of NOX emissions.
\4\Among other things, the pre-amendment guidance consists of
those portions of the proposed post-1987 ozone and carbon monoxide
policy that concern RACT, 52 FR 45044 (November 24, 1987); ``Issues
Relating to VOC Regulation Cutpoints, Deficiencies, and Deviations,
Clarification to Appendix D of November 24, 1987 Federal Register
Notice'' (Blue Book) (notice of availability was published in the
Federal Register on May 25, 1988).
---------------------------------------------------------------------------
For the purpose of assisting state and local agencies in developing
RACT rules, EPA prepared the NOX supplement to the General
Preamble, cited above (57 FR 55620). In the NOX supplement, EPA
provides guidance on how RACT will be determined for stationary sources
of NOX emissions. While most of the guidance issued by EPA on what
constitutes RACT for stationary sources has been directed towards
application for VOC sources, much of the guidance is also applicable to
RACT for stationary sources of NOX (see section 4.5 of the
NOX Supplement). In addition, pursuant to section 183(c) EPA is
issuing alternative control technique documents (ACTs) that identify
alternative controls for all categories of stationary sources of
NOX. The ACT documents will provide information on control
technology for stationary sources that emit or have the potential to
emit 25 or more tons per year of NOX. However, the ACTs will not
establish a presumptive norm for what is considered RACT for stationary
sources of NOX. In general, the guidance documents cited above, as
well as other relevant and applicable guidance documents, have been set
forth to ensure that submitted NOX RACT rules meet federal RACT
requirements and are fully enforceable and strengthen or maintain the
SIP.
In determining the approvability of an EIP, EPA must evaluate the
regulation for consistency with the requirements of the CAA and EPA
regulations, as found in section 110 and Part D of the CAA and 40 CFR
Part 51 (Requirements for Preparation, Adoption, and Submittal of
Implementation Plans). The EPA interpretation of these requirements,
which forms the basis for today's action, appears in the various EPA
policy guidance documents listed in footnote 4 of this notice. Among
these provisions is the requirement that an EIP rule must, at a
minimum, be consistent with attainment and RFP requirements found in
the CAA.
For the purpose of assisting state and local agencies in developing
rules which incorporate economic incentive strategies, EPA prepared the
EIP Rules, cited above (59 FR 16690). In the EIP Rules, EPA provides
guidance on how EIPs can be designed to be consistent with the
attainment and RFP requirements of the CAA. In general, the guidance
documents cited above, as well as other relevant and applicable
guidance documents, have been set forth to ensure that submitted EIPs
meet federal requirements and are fully enforceable and strengthen or
maintain the SIP.
SCAQMD's Regulation XX, NOX and SOX RECLAIM, is a new
rule which was adopted to control NOX and SOX emissions using
an emissions-limiting economic incentives program applicable to
facilities with four or more tons of NOX or SOX emissions per
year. Facilities with NOX or SOX emissions from permitted
equipment participate in a pollutant-specific market in order to reduce
emissions at a significantly lower cost. The program subsumes fourteen
SCAQMD Air Quality Management Plan (AQMP) control measures and is
projected to reduce emissions by an equivalent amount.
The regulation discussed below is being proposed for conditional
approval under Section 110(k)(4) of the CAA because it strengthens the
SIP and EPA is optimistic that the SCAQMD will provide EPA a commitment
within 12 months of the publication of this proposal and prior to the
publication of the final rule. Such a commitment must obligate the
SCAQMD to revise Regulation XX to correct the identified Appendix D
deficiencies, within one year after the date of publication of the
final rule. The conditional approval shall be treated as a disapproval
if the SCAQMD fails to comply with the submitted commitment.
The NOX and SOX RECLAIM program strengthens the SIP by
placing a declining emissions cap on subject facilities. The declining
cap is based on the application of RACT (or requirements more stringent
than RACT) at the facility and is reduced to overall emissions below
RACT levels in order to bring the South Coast Air Basin into attainment
of the ozone NAAQS. Regulation XX is comprised of 12 rules and 2
associated appendices which are described below:
Rule 2000--General. This rule provides the program's
objective, its purpose, and applicable definitions;
Rule 2001--Applicability. This rule provides the criteria
for inclusion in NOX and SOX RECLAIM, requirements for
sources electing to enter NOX and SOX RECLAIM and identifies
provisions in SCAQMD rules and regulations that do not apply to
NOX and SOX RECLAIM sources;
Rule 2002--Allocations for Oxides of Nitrogen (NOX)
and Oxides of Sulfur (SOX). This rule establishes the methodology
for calculating initial facility allocations for NOX and SOX
RECLAIM;
Rule 2004--Requirements. This rule establishes
requirements for operating under the NOX and SOX RECLAIM
program. The rule includes provisions pertaining to permits,
allocations, reporting, variances, penalties, and breakdowns;
Rule 2005--New Source Review (NSR) for RECLAIM. This rule
sets forth pre-construction review requirements for new facilities
subject to the requirements of the NOX and SOX RECLAIM
program and for modifications to existing NOX and SOX RECLAIM
facilities;
Rule 2006--Permits. This rule sets forth procedures for
issuing and amending NOX and SOX RECLAIM facility permits;
Rule 2007--Trading Requirements. This rule defines the
NOX and SOX RECLAIM trading credit (RTC) and establishes the
trading requirements for NOX and SOX RECLAIM;
Rule 2008--Mobile Source Credits. This rule establishes
criteria for and requirements on utilizing emission reductions
generated from SCAQMD 1600 series rules as RTCs;
Rule 2010--Administrative Remedies and Sanctions. This
rule specifies provisions to ensure that NOX and SOX RECLAIM
facilities which exceed their allocation provide compensating emission
reductions. This rule also provides for administrative penalties for
NOX and SOX RECLAIM rule violations;
Rule 2011--Requirements for Monitoring, Reporting, and
Recordkeeping for Oxides of Sulfur Emissions. This rule and its
appendix (Appendix A) establish the monitoring, reporting, and
recordkeeping requirements for SOX emissions under the NOX
and SOX RECLAIM program;
Rule 2012--Requirements for Monitoring, Reporting, and
Recordkeeping for Oxides of Nitrogen Emissions. This rule and its
appendix (Appendix A) establish the monitoring, reporting, and
recordkeeping [[Page 10822]] requirements for NOX emissions under
the NOX and SOX RECLAIM program; and
Rule 2015--Backstop Provisions. This rule specifies
NOX and SOX RECLAIM program auditing requirements and actions
that the SCAQMD will take in the event that the environmental goals of
RECLAIM program are not achieved.
Although the approval of Regulation XX will strengthen the
SIP, the regulation still contains deficiencies, identified below and
in the associated technical support document (TSD), which are required
to be corrected pursuant to section 182(b)(2) of the CAA. The NOX
and SOX RECLAIM program contains the following deficiencies:
The program allows the use of variances to avoid
compliance with program requirements; this results in the program
failing to meet the requirements of section 110(i) of the Act,
The program does not meet certain new source review
requirements of the Act and Part D,
The program allows the use of Executive Officer discretion
in the implementation of certain emissions monitoring provisions; this
results in the program failing to meet the requirements of section
110(i) of the Act,
The program's references to other programs, notably those
involving the use of mobile source emission reduction credits (MERCs)
is inconsistent with section 110(i) of the Act, and
The submittal does not provide all of the necessary
demonstrations to ensure that the requirements of EPA's EIP Rules are
being met.
A detailed discussion of the rule deficiencies can be found in the
TSD for Regulation XX (January 5, 1995), which is available from the
U.S. EPA, Region 9 office. Because SCAQMD is not using Regulation XX as
a means to achieve or maintain attainment of the SO2 NAAQS,5
the PM10 NAAQS,6 or the NO2 NAAQS, EPA does not believe
that Regulation XX will interfere with SCAQMD's ability to meet the
requirements necessary in the Act for achieving or maintaining these
standards. EPA believes that the penalty provisions found in RECLAIM
Rule 2004 will be adequate for enforcement of the RECLAIM program.
However, EPA does not believe that such penalty provisions would
necessarily be adequate for other program designs. EPA will evaluate
the penalty provisions of each program design on an individual basis,
paying particular attention to the program elements found in the EIP
rule (see 40 CFR 51.493(i) and 59 FR 16700-16701 dated April 7, 1994)
where applicable.
\5\SCAQMD is presently in attainment of the SO2 NAAQS.
\6\In this instance, SCAQMD is not asserting and EPA is not
finding that SOX RECLAIM is designed to be used as a means to
identify or implement best available control measures (BACM) for
PM10 in the South Coast Air Basin. If at some point in the
future SCAQMD decides to use SOX RECLAIM as a means of
fulfilling this requirement, an additional SIP submittal must be
made at which time EPA will apply the appropriate review criteria.
---------------------------------------------------------------------------
Because of the above deficiencies, EPA cannot grant approval of
this regulation under section 110(k)(3), section 110(a)(2), section
169A, and Parts C and D of the Act. Also, because the submitted
regulation is not composed of separable parts which meet all the
applicable requirements of the CAA, EPA cannot grant partial approval
of the regulation under section 110(k)(3). However, EPA may grant a
conditional approval under section 110(k)(4) based on a commitment by
the SCAQMD to revise the regulation to correct the identified
deficiencies within one year of the Notice of Final Rulemaking of the
conditional approval. EPA is optimistic that the SCAQMD will commit to
adopt a regulation correcting the deficiencies within the required
timeframe. The commitment letter must contain a schedule of interim
steps (with dates) for the regulation. The State of California must
submit the commitment letter to EPA. Therefore, EPA is proposing to
give conditional approval to submitted Regulation XX under section
110(k)(4) of the CAA.
Under section 110(k)(4), the conditional approval shall be treated
as a disapproval of a rule if the SCAQMD fails to adopt rules
correcting the deficiencies within the time allowed. Under 179(a)(2),
if the Administrator disapproves a submission under section 110(k) for
an area designated nonattainment, based on the submission's failure to
meet one or more of the elements required by the CAA, the Administrator
must apply one of the sanctions set forth in section 179(b) unless the
deficiency has been corrected within 18 months of such disapproval.
Section 179(b) provides two sanctions available to the Administrator:
highway funding and offsets. The 18 month period referred to in section
179(a) will begin on the effective date of EPA's final disapproval.
Moreover, the final disapproval triggers the federal implementation
plan (FIP) requirement under section 110(c). It should be noted that
the regulation covered by this NPRM has been adopted by the SCAQMD and
is currently in effect in the SCAQMD.
In the event that SCAQMD is unable to provide EPA with a commitment
which addresses all of the deficiencies identified by EPA within 12
months of the publication of this NPRM, then EPA will publish a final
rule which finalizes a limited approval/limited disapproval action on
the NOX and SOX RECLAIM program in lieu of publishing a final
rule which finalizes a conditional approval action on the NOX and
SOX RECLAIM program. In the instance in which SCAQMD fails to
provide the commitment within 12 months of the publication of the NPRM,
the limited approval/limited disapproval would be finalized based on
the same deficiencies noted elsewhere in this document and the
associated TSD. As noted above, because of the noted deficiencies, EPA
cannot grant approval or partial approval of this regulation under
section 110(k)(3) and part D. However, EPA may grant a limited approval
of the submitted regulation under section 110(k)(3) in light of EPA's
authority pursuant to section 301(a) to adopt regulations necessary to
further air quality by strengthening the SIP. The approval is limited
because EPA's action also contains a simultaneous limited disapproval.
In the instance where a commitment from SCAQMD is not submitted within
12 months of the publication of the NPRM, in order to strengthen the
SIP, EPA will finalize a limited approval of SCAQMD's submitted
Regulation XX under sections 110(k)(3) and 301(a) of the CAA.
At the same time, EPA will also finalize a limited disapproval of
this regulation because it contains deficiencies that have not been
corrected as required by section 182(a)(2)(A) of the CAA, and, as such,
the regulation does not fully meet the requirements of part D of the
Act. As noted above, if the identified deficiencies are not corrected
within 18 months of EPA's final limited disapproval, the sanctions
described in section 179 of the CAA will be applied. It should be noted
that the regulation covered by this NPRM has been adopted by the SCAQMD
and is currently in effect in the SCAQMD. EPA's final limited
disapproval action in this NPRM will not prevent the SCAQMD or the EPA
from enforcing this regulation.
Nothing in this action should be construed as permitting or
allowing or establishing a precedent for any future request for
revision to any state implementation plan. Each request for revision to
the state implementation plan shall be considered separately in light
of specific technical, economic, and environmental factors and in
[[Page 10823]] relation to relevant statutory and regulatory
requirements.
Regulatory Process
Under the Regulatory Flexibility Act, 5 U.S.C. Section 600 et seq.,
EPA must prepare a regulatory flexibility analysis assessing the impact
of any proposed or final rule on small entities. 5 U.S.C. 603 and 604.
Alternatively, EPA may certify that the rule will not have a
significant impact on a substantial number of small entities. Small
entities include small businesses, small not-for-profit enterprises and
government entities with jurisdiction over populations of less than
50,000.
Conditional approvals of SIP submittals under sections 110 and 301
and subchapter I, Part D of the CAA do not create any new requirements,
but simply approve requirements that the State is already imposing.
Therefore, because the federal SIP-approval does not impose any new
requirements, it does not have a significant impact on any small
entities affected. Moreover, due to the nature of the federal-state
relationship under the CAA, preparation of a regulatory flexibility
analysis would constitute Federal inquiry into the economic
reasonableness of state action. The CAA forbids EPA to base its actions
concerning SIPs on such grounds. Union Electric Co. v U.S. E.P.A., 427
U.S. 246, 256-66 (S.Ct. 1976); 42 U.S.C. 7410(a)(2). This discussion
applies in the case where EPA finalizes a limited approval/limited
disapproval action as well.
If the conditional approval is converted to a disapproval under
section 110(k), based on the State's failure to meet the submitted
commitment, it will not affect any existing state requirements
applicable to small entities. Federal disapproval of the state
submittal does not affect its state-enforceability. Moreover, EPA's
disapproval of the submittal does not impose a new federal requirement.
Therefore, EPA certifies that this disapproval action does not have a
significant impact on a substantial number of small entities because it
does not remove existing state requirements nor does it impose any new
federal requirements.
The Office of Management and Budget (OMB) has exempted this action
from review under Executive Order 12866.
List of Subjects in 40 CFR Part 52
Environmental protection, Air pollution control, Ozone,
Hydrocarbons, Intergovernmental relations, Reporting and recordkeeping
requirements, Volatile organic compounds, Nitrogen dioxide.
Authority: 42 U.S.C. 7401-7671q.
Dated: February 15, 1995.
Felicia Marcus,
Regional Administrator.
[FR Doc. 95-4891 Filed 2-27-95; 8:45 am]