Savannah River Operations Office; Interim Management of Nuclear Materials at Savannah River Site
Federal RegisterDec 19, 1995
Ask Donna
What actually matters in this document.
Text
DEPARTMENT OF ENERGY
Savannah River Operations Office; Interim Management of Nuclear
Materials at Savannah River Site
AGENCY: Department of Energy.
ACTION: Record of decision and notice of preferred alternatives.
-----------------------------------------------------------------------
SUMMARY: The U.S. Department of Energy (DOE) prepared a final
environmental impact statement (EIS), ``Interim Management of Nuclear
Materials'', (DOE/EIS-0220, October 20, 1995) to assess the potential
environmental impacts of actions necessary to manage nuclear materials
at the Savannah River Site (SRS), Aiken, South Carolina, until
decisions on their ultimate disposition are made and implemented. The
actions evaluated in the EIS would stabilize SRS materials that
represent environment, safety and health vulnerabilities in their
current storage condition or which may represent a vulnerability within
the next 10 years. These vulnerabilities are the result of the
suspension of nuclear materials production and processing operations
which accompanied the end of the Cold War. Although DOE has initiated
programmatic and project specific environmental evaluations on the
ultimate disposition of the nuclear materials in the DOE complex which
are
[[Page 65301]]
now surplus to national defense requirements, the implementation of
decisions regarding ultimate disposition will take several years. In
the interim, DOE wants to eliminate vulnerabilities associated with
certain current nuclear material storage configurations in order to
protect the environment and the health and safety of workers and the
public.
Several reviews conducted by DOE and the Defense Nuclear Facilities
Safety Board (DNFSB) have identified environment, safety and health
vulnerabilities associated with the continued storage of certain
nuclear materials at the SRS in their current location and physical
condition. The Final EIS evaluates alternatives for managing these
materials. In making the decisions announced in this Record of
Decision, DOE considered environmental and other factors, such as
costs, security and nuclear nonproliferation, facility usage,
technology availability, required new facilities, skilled labor
availability, minimization of continuing custodial care for the
materials, the need for maintenance or modifications to aging SRS
facilities, and, to the greatest possible extent, stakeholder concerns
and preferences.
DOE organized the nuclear materials at the SRS into one of three
categories: stable, programmatic, and candidates for stabilization. The
nuclear materials, the alternatives, and the potential environmental
impacts of implementing the alternatives are all described in detail in
the Final EIS. DOE is announcing its decisions with respect to most of
these nuclear materials today. With respect to the neptunium-237
solutions and targets and the plutonium-239 solutions, DOE has
determined that stabilization is necessary and has narrowed the
alternatives under consideration regarding how to stabilize these
materials. Upon completion of further analysis, DOE will issue a
subsequent Record of Decision to further specify the final
stabilization strategy for these materials. With respect to the Mark-16
and Mark-22 fuels, and other aluminum-clad targets, DOE has designated
new preferred alternatives and will announce its decision on the
management of these materials in an amended Record of Decision no
sooner than 30 days from the availability of this notice.
RECORD OF DECISION: DOE has decided to initiate actions which will
stabilize certain of the SRS materials that represent environment,
safety and health vulnerabilities in their current storage condition or
which may represent a vulnerability within the next 10 years. Based on
the analysis in the Final EIS, and the other factors identified above,
DOE has made the following decisions:
Stable Materials
DOE has decided that stable materials can be safely managed in
their existing physical and chemical forms over the next several years.
Programs and projects to consolidate storage of stable materials in
order to reduce surveillance and maintenance costs will continue. These
materials will remain stored at SRS until DOE makes decisions relative
to their future use or disposition.
Programmatic Materials
DOE identified nuclear materials at SRS which may be required to
support ongoing or planned programs after consultation with national
laboratories and other appropriate federal agencies, such as the
National Aeronautics and Space Administration (NASA). The bulk of the
following programmatic nuclear materials at the SRS are contained in
acidic solutions stored in tanks in the canyon facilities and would
otherwise be considered Candidates for Stabilization.
Plutonium-242
DOE has decided to process plutonium-242 solutions stored in the H-
Canyon facility to an oxide using the HB-Line facility. The plutonium-
242 oxide will be packaged into containers and stored at the SRS until
DOE makes programmatic decisions on its use or disposition.
Americium and Curium
DOE has decided to process solutions of americium and curium
isotopes stored in the F-Canyon facility into a glass matrix within
small stainless steel canisters, and to store the resulting canisters
at the SRS until programmatic decisions on use or disposition are made
by DOE. Vitrification equipment will be installed in an existing
portion of the F-Canyon facility (previously called the Multi-Purpose
Processing Facility). DOE has decided to continue the storage of metal
reactor targets and slugs containing americium and curium isotopes in
existing SRS basin facilities until DOE makes programmatic decisions on
their use or disposition.
Neptunium-237
DOE will dissolve, chemically separate and process neptunium
contained in the nine (9) obsolete reactor targets and will process
existing solutions in the H-Canyon to either a glass matrix using the
same vitrification equipment installed in F-Canyon or to an oxide using
the HB-Line facility. The final form of the neptunium-237 depends on
actions taken, if any, to consolidate certain activities in the F-
Canyon as outlined in a recently issued DOE staff report entitled
Facility Utilization Strategy for the Savannah River Site Chemical
Separation Facilities (December 1995) . The study principally considers
what effect the consolidation of two primary processing areas to one
would have on the ability to stabilize nuclear materials at the SRS.
Budgetary pressures and safety requirements as well as preserving
capability for future missions necessitates a thorough examination of
the options for these facilities. The report is available to the public
(see below). At this time, DOE is narrowing the potential stabilization
alternatives for the neptunium-237 from the four considered in the EIS
to either the oxide or vitrified (F-Canyon) form. As noted above, DOE
will issue a subsequent Record of Decision to specify which of these
two alternatives will be used to stabilize these materials.
To vitrify the neptunium solutions in F-Canyon, DOE would develop
or procure a container suitable for transporting the solutions from H-
Canyon to F-Canyon and make minor modifications to each facility to
support loading and unloading operations. DOE is currently evaluating
the feasibility of using a container designed for transport of
radioactive solutions which is licensed by the International Atomic
Energy Agency (IAEA). In order to process the solutions to an oxide,
DOE would start up a new portion of the HB-Line facility (Phase II)
which has never been operated. Neptunium recovered from the targets
will be processed along with the existing neptunium solutions into
either a glass or an oxide. The glass canisters or containers of oxide
would be stored inside the shielded canyon facilities or in a new
Actinide Packaging and Storage Facility until DOE makes programmatic
decisions on their future use or disposition.
Candidates for Stabilization
Materials that are candidates for stabilization are in forms (e.g.,
liquid) that present inherent management risks, are stored in
facilities that were not designed for long-term storage, or both.
Generally, these materials currently present, or can be expected to
present over the interim period (approximately 10 years),
environmental, worker or public safety and health concerns or
vulnerabilities.
[[Page 65302]]
Highly Enriched Uranium (HEU) Solutions
DOE has decided to stabilize highly enriched uranium solutions
stored in H-Area by blending them with depleted uranium at the SRS to
produce solutions containing low enriched uranium (LEU). DOE will make
minor modifications to the F-Canyon and H-Canyon facilities to enable
loading and unloading of the uranium solutions into containers for
transport between the facilities and install a spare dissolver in FA-
Line. The LEU solutions will either be stored in existing tanks at SRS
or converted to a low enriched uranium oxide using the FA-Line
facility. The final form of the HEU solutions after they are blended
down will be dependent upon the timing of DOE decisions related to the
disposition of surplus HEU and upon facility utilization considerations
related to cost and schedule.
Plutonium and Uranium Stored in Vaults
DOE has decided to stabilize plutonium and uranium materials stored
in vaults by (1) heating or repackaging the material into better
containers, and (2) dissolving some materials to chemically remove
impurities or radioactive decay products, converting the resulting
purified solutions to a metal, an oxide or a glass. DOE will determine
the appropriate method to use upon inspection and analysis of the
material in each package. DOE will use the H-Canyon, HB-Line, F-Canyon
and FB-Line facilities to process the materials and remove impurities
that contribute to the stability concerns. DOE will use the FB-Line
facility to convert resulting plutonium-239 solutions to a metal, HB-
Line to convert resulting plutonium-238 and plutonium-239 solutions to
an oxide, and a modified portion of F-Canyon to convert plutonium-239
solutions to a glass matrix. The use of the modified portion of the F-
Canyon will be subject to the successful vitrification of the solutions
containing americium and curium isotopes (see above) and additional
analytical laboratory work. DOE will use a glove box being installed in
FB-Line to package the plutonium metal. DOE has decided to construct a
new Actinide Packaging and Storage Facility in F-Area to enable heating
and repackaging of plutonium metals and oxides to meet new storage
criteria (DOE Criteria for Safe Storage of Plutonium Metals and Oxides
(DOE-STD-3013-94)) and to provide space for consolidated storage of
plutonium and special actinide materials at SRS. The storage standard
imposes stringent requirements regarding the chemical stability of
plutonium metals and oxides along with requirements for design and
construction of packages used for storage of the material. The standard
identifies such measures as residual moisture content allowed in the
plutonium metal or oxide, materials to be avoided in contact with the
plutonium or used in the packaging configuration, thermal loading
limitations, and packaging seals, closures and containment features.
DOE will incorporate requirements of the IAEA into the design and
construction of the new Actinide Packaging and Storage Facility to
provide the latitude for placing the nuclear materials under
international safeguards in the future. DOE is also pursuing
declassification of information related to the amount of plutonium that
would be stored in the new facility.
Mark-31 Targets
DOE has decided to stabilize Mark-31 targets (short cylindrical
metal slugs fabricated with depleted uranium and, if irradiated,
containing plutonium) by dissolving them in the F-Canyon facility and
chemically separating the plutonium and depleted uranium from fission
products and other constituents. The resulting plutonium solutions will
be converted to a metal using the FB-Line facility. Upon installation
of a new glove box in FB-Line, the metal will be packaged in accordance
with DOE's storage standard. DOE will use the depleted uranium
recovered from the Mark-31 targets for blending with highly enriched
uranium solutions in H-Area (see above).
Aluminum-clad Taiwan Research Reactor (TRR) Fuel and Experimental
Breeder Reactor (EBR)-II Slugs
DOE has decided to stabilize 81 canisters of failed fuel from the
Taiwan Research Reactor and one failed canister of de-clad metal slugs
from the Experimental Breeder Reactor-II by dissolving the materials in
F-Canyon and processing them in conjunction with the Mark-31 targets.
The failed fuel and de-clad metal slugs contain natural or depleted
uranium and plutonium, similar to the Mark-31 targets. The resulting
solutions containing plutonium recovered from the fuel and slugs will
be converted to a metal using the FB-Line facility. The plutonium metal
will be packaged in accordance with DOE's storage standard. The
depleted and natural uranium recovered from the fuel and slugs will be
used for blending with the highly enriched uranium solutions stored in
H-Area.
Plutonium-239 Solutions
DOE has decided to stabilize plutonium-239 solutions stored in the
H-Canyon facility to either a glass using the vitrification equipment
installed in a modified F-Canyon, an oxide using the HB-Line facility,
or a metal using the FB-Line facility. At this time, DOE is narrowing
the potential stabilization alternatives from the five considered in
the EIS to either the vitrified (F-Canyon), metal, or oxide form. The
final stabilization strategy would depend in part on actions taken, if
any, to consolidate certain activities in the F-Canyon as described
above for the neptunium-237 stabilization activities. As with the
neptunium-237 materials, a subsequent Record of Decision will be issued
to specify the final strategy for stabilizing the plutonium-239
solutions.
To vitrify the solutions in F-Canyon, DOE would move the solutions
from H-Canyon to F-Canyon using the same container as described above
for the transport of the neptunium solutions and also use the same
facility modifications for loading and unloading the container. The use
of the modified portion (the vitrification equipment) of the F-Canyon
would be subject to the successful vitrification of the solutions
containing americium and curium isotopes (see above) and additional
analytical laboratory work. In order to process the existing solutions
to an oxide in HB-Line, DOE would have to start up a new portion of the
facility which has never been operated. To process the solutions to
metal, DOE would move the solutions from H-Canyon to F-Canyon as
described for the vitrification alternative and would use FB-Line to
convert the solutions to metal.
Notice: Announcement of Preferred Stabilization Alternatives. DOE
also is announcing today new preferred alternatives for managing the
Mark-16 and Mark-22 fuels, and the ``other aluminum-clad targets.'' In
the Final EIS, DOE identified continued storage (i.e., No Action) as
the preferred alternative for managing the Mark-16 and Mark-22 fuels
(aluminum-clad, highly enriched uranium fuel from SRS reactors) and the
other aluminum-clad targets (irradiated in SRS reactors) pending
further review of cost, schedules, and technical uncertainties
associated with dry storage techniques for failed fuel. DOE has since
completed its review of these issues and is now announcing the
designation of processing and blending down to low enriched uranium as
the preferred alternative for stabilizing the Mark-16 and Mark-22
fuels. DOE is also
[[Page 65303]]
announcing the designation of Processing and Storage for Vitrification
in the Defense Waste Processing Facility as the preferred alternative
for stabilizing the other aluminum-clad targets. DOE will issue a
subsequent Record of Decision on the Mark-16 and Mark-22 fuels and the
other aluminum-clad targets no sooner than thirty (30) days from the
availability of this notice.
FOR FURTHER INFORMATION CONTACT: For further information on the interim
management of nuclear materials at the SRS or to receive a copy of the
Final EIS, the Facility Utilization Strategy Study, or this Record of
Decision contact: Andrew R. Grainger, NEPA Compliance Officer, U.S.
Department of Energy, Savannah River Operations Office, P.O. Box 5031,
Aiken, South Carolina 29804-5031, (800) 242-8259, Internet:
[email protected].
For further information on the DOE National Environmental Policy
Act (NEPA) process, contact: Carol M. Borgstrom, Director, Office of
NEPA Policy and Assistance, EH-42, U.S. Department of Energy, 1000
Independence Avenue, SW., Washington, DC 20585, (202) 586-4600, or
leave a message at (800) 472-2756.
SUPPLEMENTARY INFORMATION:
I. Background
The U.S. Atomic Energy Commission, a predecessor agency of the
Department of Energy (DOE), established the Savannah River Site in the
early 1950's. The SRS occupies approximately 800 square kilometers (300
square miles) adjacent to the Savannah River, mostly in Aiken and
Barnwell Counties of South Carolina, about 40 kilometers (25 miles)
southeast of Augusta, Georgia, and about 32 kilometers (20 miles) south
of Aiken, South Carolina. The SRS mission for the past 40 years has
been the production of special radioactive isotopes to support national
programs. The primary mission was the production of strategic isotopes
(plutonium-239 and tritium) used in the development and production of
nuclear weapons for national defense. The Site produced other special
isotopes (e.g., californium-252, plutonium-238, americium-241) to
support research in nuclear medicine, space exploration, and commercial
applications. To produce the isotopes, DOE fabricated selected
materials into metal targets and irradiated them in the SRS nuclear
reactors. After irradiation and cooling, the targets and reactor fuel
were dissolved in acid and the special isotopes were chemically
separated and converted to a solid form, either an oxide powder or a
metal. The oxide or metal was fabricated into a usable form at the SRS
or at other DOE sites. The final form of the material depended on the
application (nuclear weapon component, encapsulated medical source,
power source, etc.).
Due to the large scale chemical separation capabilities at the SRS,
materials containing significant quantities of plutonium-239, uranium-
235, and other special isotopes were shipped to the Site for processing
and recovery. The materials were in a wide variety of physical shapes
and forms, including (1) small encapsulated plutonium sources returned
after use by national laboratories and domestic universities; (2) cans
or drums of scrap metals and oxides from weapons manufacturing
operations at other DOE sites; (3) irradiated metal fuel rods, tubes,
plates, or assemblies from experimental DOE reactors, university
research reactors, and foreign research reactors; and (4) cans,
bottles, or drums containing residues or samples used in laboratory
experiments at other DOE sites. All the materials were stored until
they could be dissolved and processed in the chemical separations
facilities (F-Canyon or H-Canyon). The small sources, scrap metals,
oxides, residues, and samples were typically stored in cans, bottles,
or drums in safeguarded concrete vaults. The irradiated fuel and
targets were stored under water in metal racks or buckets. The offsite
materials were typically processed in conjunction with the materials
produced at the SRS.
In March 1992, DOE suspended chemical processing operations in the
F- and H-Canyon facilities to address a safety concern regarding the
capacity of the F- and H-Canyon ventilation systems to withstand an
earthquake. That concern, involving the potential failure of the canyon
exhaust stack liner in the event of a severe earthquake, was addressed
through the preparation of appropriate response procedures, training,
and response drills. However, in April 1992, before operation of the F-
and H-Canyons could resume, the Secretary of Energy directed that the
SRS phase out defense-related chemical separations activities in these
facilities. World events in the late 1980's and early 1990's resulted
in the end of the Cold War and a reduction in the demand for new
material for nuclear weapons. As a result, DOE stopped operating the
SRS reactors to produce strategic isotopes. After the Secretarial
decision in April 1992, DOE did not process nuclear materials at the
SRS chemical separations facilities to recover special isotopes, with
the exception of scrap materials containing plutonium-238. DOE
continued the processing of plutonium-238 for use as a thermal power
source by the National Aeronautics and Space Administration (NASA) in
exploratory space missions.
By September 1992, SRS had developed plans to phase out chemical
reprocessing. The plans included actions for removing the material that
remained in the canyons, spent fuel basins, and storage vaults as a
result of the suspension of chemical separation activities in March
1992. In February 1993 the Site requested approval from DOE to restart
F-Canyon after the completion of operational readiness reviews
conducted as part of the response to the March 1992 safety concern. The
SRS made this startup request in light of the Secretary's direction to
accelerate the transition of F-Area reprocessing facilities to a
standby condition and because all contemplated actions were typical of
ongoing or previous facility operations.
During this same time period, DOE was developing new requirements
for the performance of operational readiness reviews prior to the
startup (or restart) of nuclear facilities. Under these requirements,
facilities had to be able to demonstrate the capability to perform
satisfactorily in relation to a broad range of topics associated with
the safe operation of a nuclear facility. DOE promulgated these
requirements in DOE Order 5480.31, ``Startup and Restart of Nuclear
Facilities'', which it issued in September 1993. DOE decided that the
SRS should apply these requirements to the F and H-Canyons and, in
November 1993, determined that the Site should hold the proposed F-
Canyon (and FB-Line) restart in abeyance until it had completed a
restart review in accordance with the new Order. In part due to
stakeholder concerns, DOE decided in January 1994 that absent an
emergency condition, there should be no further material processed in
the canyons (beyond processing of plutonium-238 for NASA) before
completion of an environmental impact statement.
On March 17, 1994, DOE published a Notice of Intent (NOI) (59 FR
12588) to prepare an environmental impact statement on the interim
management of nuclear materials at the SRS. The proposed DOE interim
management actions are to stabilize those nuclear materials at the SRS
that represent a health or safety concern for the public, workers, and
the environment and to convert certain materials to a usable form to
support DOE program needs. These interim actions are necessary while
DOE makes and implements long-term decisions on the disposition of
nuclear materials. DOE is addressing
[[Page 65304]]
long-term decisions in the Programmatic Environmental Impact Statement
for Storage and Disposition of Weapons-Usable Fissile Materials, for
which it issued an NOI on June 21, 1994 (59 FR 31985), and in the
Disposition of Surplus Highly Enriched Uranium EIS (60 FR 17344, April
5, 1995) (for which the draft EIS was issued in October 1995 (60 FR
55021, October 27, 1995)).
The NOI for the Interim Management of Nuclear Materials EIS
requested public comments and suggestions for DOE to consider in its
determination of the scope of that EIS, and announced a public scoping
period that ended on May 31, 1994. DOE held scoping meetings in
Savannah, Georgia, North Augusta and Columbia, South Carolina, on May
12, 17, and 19, 1994, respectively.
In May 1994, the Manager of the Savannah River Operations Office
recommended that the DOE Assistant Secretary for Defense Programs seek
alternative methods pursuant to the emergency provisions of 10 CFR
1506.11 to comply with the National Environmental Policy Act (NEPA) to
allow stabilization of plutonium solutions stored in F-Canyon and Mark-
31 targets stored in the L-Reactor Disassembly Basin.
In June 1994, the DOE Office of Environment, Safety and Health
performed an independent evaluation of the SRS request for alternative
arrangements for compliance with NEPA. DOE evaluated the SRS request in
light of the Office of Environment, Safety and Health's report and
determined that the appropriate action would be to accelerate the
evaluation of stabilization alternatives for the F-Canyon plutonium
solutions by preparing a separate expedited environmental impact
statement on this subject. In February 1995, following completion of
the F-Canyon Plutonium Solutions EIS and issuance of that Record of
Decision, DOE resumed F-Canyon operations to eliminate the risks
involved in storing plutonium in solution form.
DOE issued a Draft EIS on the Interim Management of Nuclear
Materials for public review and comment on March 17, 1995 (60 FR
14432). DOE has revised the Draft EIS in response to the comments
received in letters and electronic messages from individuals,
organizations, Federal and state agencies and comments received during
public hearings held in Savannah, Georgia (April 11, 1995) and North
Augusta, South Carolina (April 13, 1995). On October 20, 1995, EPA
published a Notice of Availability of the Final EIS on the Interim
Management of Nuclear Materials in the Federal Register (60 FR 54226),
following distribution of approximately 400 copies to government
officials and interested groups and individuals.
DOE prepared this Record of Decision in accordance with the
regulations of the Council on Environmental Quality for implementing
NEPA (40 CFR 1500-1508) and DOE's NEPA Implementing Procedures (10 CFR
1021). This Record of Decision is based on DOE's Final Environmental
Impact Statement on the Interim Management of Nuclear Materials,
Savannah River Site, Aiken, South Carolina (DOE/EIS-0220).
II. Studies of Vulnerabilities of Storage of Nuclear Materials at SRS
The cessation of processing activities resulted in a large
inventory of nuclear materials being caught in various stages of the
production cycle (fabrication, irradiation, reprocessing, and isotope
recovery). These materials include irradiated and unirradiated reactor
fuel, targets, and components; solutions containing dissolved nuclear
materials and recovered isotopes in stainless- steel tanks; and product
and scrap forms of metals or oxides in containers (cans, drums, etc.)
typically used for temporary storage or shipment off the Site.
Between November 1993 and November 1994, DOE completed two
nationwide reviews of how nuclear materials are stored at the SRS and
other sites: Spent Fuel Working Group Report on Inventory and Storage
of the Department's Spent Nuclear Fuel and Other Reactor Irradiated
Nuclear Materials and Their Environment, Safety and Health
Vulnerabilities, and Plutonium Working Group Report on Environment,
Safety and Health Vulnerabilities Associated with the Department's
Plutonium Storage. The reviews identified vulnerabilities with the
continued storage of several nuclear materials at SRS: corroded spent
fuel and targets stored in water-filled basins; tanks with thousands of
gallons of acidic solutions containing plutonium, neptunium, americium
and curium isotopes stored in the canyon facilities; and packages
containing plutonium-bearing materials stored in vaults. The reviews
defined vulnerabilities as conditions or weaknesses that might lead to
radiation exposure to the public, unnecessary or increased exposure to
workers, or release of radioactive materials to the environment.
The Defense Nuclear Facilities Safety Board (DNFSB) is an
independent organization established by Congress to provide oversight
of DOE. In May 1994, the DNFSB transmitted Recommendation 94-1 to the
Secretary of Energy. In its recommendation, the Board observed that the
halt in production of nuclear weapons had frozen the manufacturing
pipeline in a state, that for safety reasons, should not be allowed to
persist unremediated. The Board concluded from observations and
discussions with others that imminent hazards could arise within two to
three years unless certain problems are corrected. The Board expressed
special concern about specific liquids and solids containing fissile
materials and other radioactive substances in spent fuel storage pools,
reactor basins, reprocessing canyons, processing lines, and various
buildings once used for processing and weapons manufacture. On August
3, 1995, the Chairman of the DNFSB transmitted a staff report to the
Assistant Secretary for Environmental Management identifying concerns
with leaking containers of corroded spent fuel stored in the Receiving
Basin for Offsite Fuel at SRS. The staff report from the Board
expressed concerns with DOE having previously identified all of the
nuclear materials in the basin as ``stable'' in the Draft EIS issued
for public comment.
III. Categories of Nuclear Materials at the Savannah River Site
DOE used information from the two nationwide reviews on spent fuel
and plutonium storage, an SRS site-wide review, and input from the
DNFSB to categorize the nuclear materials at SRS as either Stable or
Candidates for Stabilization. Stable materials have physical and
chemical forms that, combined with their storage configurations, do not
currently pose environmental, safety, or health concerns and are not
likely to pose a concern over the next 10 years. Candidates for
Stabilization are materials that exhibit or could be expected to
exhibit over the next 10 years, health, safety or environmental
vulnerabilities because of their physical condition, chemical
composition, or the manner in which they are stored.
DOE categorized materials containing plutonium-242, neptunium-237
and various isotopes of americium and curium as Programmatic after
consultation with national laboratories and other appropriate federal
agencies, such as NASA. The bulk of these Programmatic nuclear
materials are contained in acidic solutions stored in tanks in the
canyon facilities and would otherwise be considered Candidates for
Stabilization. Programmatic materials contain special isotopes that
could be needed to support DOE programs. In their current forms these
materials are
[[Page 65305]]
not usable and may not be suitable for continued safe storage. DOE may
use plutonium-242 in the nuclear weapons stockpile stewardship program.
Americium-243 and curium-244 are considered national assets for
potential support of research in nuclear medicine, nuclear chemistry,
solid-state chemistry, and nuclear physics. The higher isotopes of
curium (curium-244 through -248) are irreplaceable feedstocks for the
production of californium-252, which is used as a neutron source for
both military and industrial applications. DOE may use neptunium-237 in
the future production of plutonium-238 to provide a power source for
remote terrestrial and space applications. Future DOE decisions will
determine if these Programmatic materials will actually be used. Table
1 lists the nuclear materials at SRS in each category.
IV. Alternatives Evaluated in the Final EIS
DOE evaluated the following alternatives for managing the nuclear
materials: (a) Continued Storage (i.e., ``No Action'' within the
context of NEPA), (b) Processing to Metal, (c) Processing to Oxide, (d)
Blending Down to Low Enriched Uranium, (e) Processing and Storage for
Vitrification, (f) Vitrification, and (g) Improving Storage. As shown
in Table 2, DOE has evaluated the environmental impacts of managing the
nuclear materials using one or more of these alternatives. The
following is a brief description of each alternative.
A. Continuing Storage (No Action)
Under this alternative, DOE would continue to store materials in
their current physical form. DOE would relocate, repackage, or re-can
nuclear materials stored in vaults, tanks or basins to consolidate the
material or to respond to an immediate safety problem. Periodic
sampling, destructive and non-destructive examination, weighing, visual
inspection and similar activities would continue in order to monitor
the physical and chemical condition of the nuclear material. Chemicals
would be added to existing solutions in order to maintain concentration
and chemistry within established parameters. Repackaging would include
removing materials from a damaged storage container and placing them in
a new container or placing the damaged container in a larger container.
Re-canning would primarily entail placing damaged or degraded fuel or
targets in metal containers, sealing the containers, and keeping them
in wet storage.
Many activities would be required by DOE irrespective of the
management alternative used. For example, DOE would maintain facilities
in good working condition and would continue to provide utilities
(water, electricity, steam, compressed gas, etc.) and services
(security, maintenance, fire protection, etc.) for each facility.
Training activities would ensure that personnel maintain the skills
necessary to operate the facilities and equipment. DOE would continue
with ongoing projects to alleviate facility-related vulnerabilities
associated with storage of the nuclear materials and projects to
upgrade or replace aging equipment (ventilation fans, etc.).
As shown in Table 2, DOE designated Continuing Storage as the
preferred alternative for managing all stable nuclear materials and
metal targets containing isotopes of americium and curium. DOE also
designated Continuing Storage as the preferred alternative for managing
Mark-16 and Mark-22 fuels and other aluminum-clad targets until
additional reviews on dry storage technologies, costs and schedules
versus chemical processing techniques could be completed.
B. Processing to Metal
Under this alternative, DOE would convert plutonium nitrate
solutions to plutonium metal using the FB-Line facility. After
conversion, the metal would be packaged and stored in accordance with
DOE's storage standard. A new glove box is being installed in FB-Line
to provide the equipment necessary to meet the storage standard
criteria for packaging of plutonium metal. The plutonium metal would be
stored at SRS until programmatic decisions are made by DOE on long-term
storage or disposition.
The plutonium would come from existing nitrate solutions in H-
Canyon or would be generated as a result of dissolving and chemically
processing plutonium-bearing material in the F-Canyon. Existing nitrate
solutions in H-Canyon contain plutonium-239 and plutonium-242.
Additional plutonium-239 solutions would be generated by dissolving and
processing plutonium-bearing metals and oxides stored in SRS vaults,
Mark-31 targets, canisters of failed Taiwan Research Reactor fuel, and
a failed canister of de-clad Experimental Breeder Reactor-II metal
slugs.
DOE would design or procure a container to transport the existing
plutonium-239 and plutonium-242 solutions from H-Canyon to F-Canyon.
Some degree of uncertainty exists on the ability to transfer these
solutions from one canyon to the other. Minor modifications would be
made to the canyon facilities to support loading and unloading of the
solutions into the transport container.
As shown in Table 2, DOE designated Processing to Metal as the
preferred alternative for stabilizing some of the plutonium and uranium
vault materials, the Mark-31 targets, failed Taiwan Research Reactor
fuel, and the failed canister of Experimental Breeder Reactor-II slugs.
C. Processing to Oxide
Under this alternative, DOE would convert plutonium to an oxide in
HB-Line or FB-Line. The plutonium would come from existing nitrate
solutions in H-Canyon or would be generated as a result of dissolving
and chemically processing material in H-Canyon or F-Canyon. Existing
nitrate solutions in H-Canyon contain plutonium-239 and plutonium-242
and would be converted to an oxide in HB-Line. Additional plutonium-239
nitrate solutions would be generated by dissolving and processing Mark-
31 targets, canisters of failed Taiwan Research Reactor fuel, and a
failed canister of de-clad slugs from the Experimental Breeder Reactor-
II. FB-Line would require modification to convert the resulting
plutonium-239 solutions to an oxide. Plutonium-239 solutions and a
small quantity of plutonium-238 solution could also be generated by
dissolving plutonium-bearing metals and oxides currently stored in SRS
vaults. This material would be dissolved and processed in H-Canyon/HB-
Line and converted to an oxide in HB-Line. After conversion, the
plutonium oxide would be packaged and stored in accordance with the DOE
Criteria for Safe Storage of Plutonium Metals and Oxides (DOE-STD-3013-
94). Modifications would be made to the FB-Line facility to provide the
equipment necessary to heat and package the oxide in accordance with
the DOE storage standard or a new Actinide Packaging and Storage
Facility would be constructed.
DOE would convert neptunium-237 solutions to an oxide in HB-Line.
The neptunium would come from existing solutions in H-Canyon and from
dissolving and processing the obsolete reactor targets containing
neptunium in H-Canyon. Additionally, if one of the alternatives
involving dissolution and chemical separation (Processing to Oxide or
Blending Down to Low Enriched Uranium) were implemented for
stabilization of irradiated SRS reactor fuels (Mark-16 and Mark-22),
neptunium would be recovered. After
[[Page 65306]]
conversion of the neptunium solutions to an oxide, the oxide would be
packaged and stored in the Actinide Packaging and Storage Facility.
DOE would convert the americium and curium solutions in F-Canyon to
an oxide. DOE would modify an existing portion of F-Canyon to provide
the necessary equipment. After conversion, the americium and curium
oxide would be packaged and stored in an existing vault or the new
Actinide Packaging and Storage Facility. DOE could also transport the
obsolete targets and slugs containing americium and curium isotopes to
F-Canyon, dissolve them and convert the resulting solutions in a
similar manner.
DOE would convert highly enriched uranium solutions to highly
enriched uranium oxide. To provide conversion capability, DOE would
complete the partially constructed Uranium Solidification Facility
(USF) in H-Canyon. DOE would also dissolve Mark-16 and Mark-22 fuels
containing highly enriched uranium in H-Canyon and convert the
resulting solutions to an oxide in the same manner. The highly enriched
uranium oxide would be packaged and stored in a vault in USF until DOE
makes long-term management and disposition decisions.
As shown in Table 2, DOE designated Processing to Oxide as the
preferred alternative in the Final EIS for stabilizing plutonium-242
solutions, neptunium-237 solutions and targets, plutonium-239
solutions, and some of the plutonium and uranium vault materials.
D. Blending Down to Low Enriched Uranium
This alternative is only relevant to materials containing highly
enriched uranium. Existing solutions of highly enriched uranium stored
in H-Area would be blended with existing depleted uranium at SRS. DOE
would modify the canyon facilities to support loading and unloading of
tanks used for transport and install a spare oxide dissolver in FA-
Line. The highly enriched and depleted uranium would be blended to
produce a low enriched uranium solution.
Mark-16 and Mark-22 fuels containing highly enriched uranium would
be transported to either H-Canyon or F-Canyon by rail casks, dissolved
in nitric acid, and the highly enriched uranium separated from fission
products and other materials. The highly enriched uranium solutions
would be blended with natural or depleted uranium to produce low
enriched uranium solutions. The low enriched uranium solutions would be
converted to an oxide using FA-Line. The oxide would be stored in drums
in existing facilities or in a new warehouse constructed at SRS.
Dependent upon the timing of future DOE decisions, the highly
enriched uranium solutions and the uranium recovered from the
dissolution of Mark-16 and Mark-22 fuels could also be dispositioned in
conjunction with other highly enriched uranium (by commercial sale,
etc.).
As shown in Table-2, DOE designated Blending Down to Low Enriched
Uranium as the preferred alternative for stabilizing highly enriched
uranium solutions.
E. Processing and Storage for Vitrification in the Defense Waste
Processing Facility (DWPF)
DOE would perform research and development work to develop a method
for chemically adjusting existing solutions in the canyons in order to
transfer them to the high level waste tanks in F- or H-Area. The
research and development work would be to ensure nuclear criticality
safety due to the large amounts of plutonium-239 and uranium-235
contained in the existing solutions and to evaluate the effects on the
systems and facilities used to store and treat the liquid high level
waste. Upon completion of the studies, existing solutions containing
plutonium-239, plutonium-242, highly enriched uranium, neptunium-237,
and americium and curium isotopes would be chemically adjusted and
transferred to the high level waste tanks via underground pipelines.
Plutonium-bearing vault materials would be dissolved in either a
canyon or B-Line dependent upon the amount of material and the chemical
composition. The degraded reactor components (fuel and targets) stored
in water-filled basins would be transported by rail casks to F- or H-
Canyon and dissolved in nitric acid. The resulting solutions from
dissolution of the vault materials and reactor components would be
chemically adjusted and transferred to the high level waste tanks along
with existing canyon solutions. The solutions would be mixed with the
existing volume of high level waste stored in the F- and H-Area tanks.
The bulk of the radioactivity in the solutions would eventually be
immobilized in borosilicate glass by the Defense Waste Processing
Facility (DWPF). The glass would be contained within stainless steel
canisters that would be stored in an adjacent facility to the DWPF
awaiting geological disposal by DOE. The bulk of the liquid would be
immobilized by the Saltstone facility into a grout containing very low
levels of radioactivity. The grout would be poured into concrete vaults
located at the Saltstone facility.
As shown in Table-2, Processing and Storage for Vitrification in
DWPF was not designated by DOE as a preferred alternative for any of
the materials.
F. Vitrification (in F-Canyon)
This alternative would involve modifying existing space in the F-
Canyon, providing equipment to vitrify radioactive solutions using a
process similar to that developed for the DWPF. The equipment would be
much smaller in scale to that of the DWPF and the stainless-steel
canisters of glass produced would contain much higher concentrations of
actinides, including fissile isotopes. After completing the
modifications, DOE would vitrify existing solutions of plutonium-242,
plutonium-239, neptunium-237, and americium and curium isotopes. The
solutions stored in H-Canyon would be transported to F-Canyon for
vitrification upon development (or procurement) of a suitable shipping
container and upon completion of modifications to the canyon facilities
for loading and unloading.
Plutonium-bearing vault materials would be dissolved in either a
canyon or a B-Line and vitrified in the same manner. Similarly,
degraded reactor components (Mark-31 targets, canisters of failed TRR
fuel and the failed canister of EBR-II slugs) would be transported by
rail cask to F-Canyon, dissolved in nitric acid, and the plutonium
vitrified. The depleted or natural uranium contained in the reactor
components would be chemically separated and stored in tanks or used
for blending with highly enriched uranium (see description of Blending
Down to Low Enriched Uranium).
The obsolete reactor targets and slugs containing neptunium,
americium and curium would be transported to F-Canyon, dissolved in
nitric acid, and the programmatic isotopes chemically separated from
fission products and other materials. The resulting neptunium,
americium and curium solutions would be vitrified in conjunction with
the existing solutions containing those same isotopes.
Neptunium separated from Mark-16 and Mark-22 fuels processing in F-
Canyon for blending down to low enriched uranium would be vitrified in
conjunction with the existing neptunium solutions.
As shown in Table-2, DOE designated Vitrification in F-Canyon as
the preferred alternative for stabilizing americium and curium
solutions and
[[Page 65307]]
some of the plutonium and uranium vault materials.
G. Improving Storage
This alternative would be applicable to plutonium-bearing materials
stored in vaults and degraded reactor components stored in water-filled
basins. Based on earlier DOE decisions to stabilize plutonium solutions
stored in F-Canyon (see background), DOE is modifying the FB-Line
facility by installing a glove box to enable handling and packaging of
plutonium without the use of plastic and other organic materials
(rubber, elastomeric seals, etc.). The existing plutonium metal stored
in vaults would be repackaged in FB-Line to meet the DOE storage
standard. DOE would provide the capability to heat, repackage, and
store plutonium oxide by modifying an existing facility (FB-Line or
Building-235) or by building a new Actinide Packaging and Storage
Facility in F-Area. The plutonium-bearing vault materials would be
repackaged to meet the DOE storage standard and would be stored at SRS
until DOE makes long-term storage or disposition decisions.
For degraded reactor components (Mark-31 targets, Mark-16 and -22
fuels, other aluminum-clad targets, failed TRR fuel, and the failed
canister of EBR-II metal slugs), DOE would remove the materials from
the basins and place them in dry storage. Because of technical
uncertainties (e.g., potentially pyrophoric hydrides of uranium,
elimination of potential reactive material) associated with the dry
storage of failed fuel and targets, DOE would perform additional
research to demonstrate concepts for drying and placing the materials
into canisters for storage. Work related to the dry storage of low
enriched uranium and commercial spent nuclear fuel has already been
done in the United States and other countries. This work has not
focused on aluminum-clad highly enriched uranium fuels. In conjunction
with this work, DOE would design and construct a Dry Storage Facility
at SRS.
A typical dry storage facility would be a Modular Dry Storage
Vault. This facility would consist of four major components: a
receiving/unloading area, fuel storage canisters, a shielded container
handling machine, and a modular vault for storing the fuel in storage
canisters. As a variation, canisters could be stored in dry storage
casks rather than a vault. The degraded fuel and target materials would
be removed from the basins and dried; canned or placed directly in
canisters; the cans or canisters would be filled with an inert gas to
inhibit further corrosion; and if cans were used, loaded into storage
canisters. This process could be varied as dictated by the condition of
the material. After the targets were loaded in a canister, a machine
would transport the canister to the modular storage vault. The vault
would consist of a large concrete structure with an array of vertical
tubes to hold the canisters. The canister transport machine would move
into the vault and load the canister into a storage tube. A shielded
plug would be placed on top of the tube. The transport machine and the
vault storage tubes would be heavily shielded to reduce radiation
levels from the canister. To use dry storage casks, the machine would
transport the canister to a cask (horizontal or vertical) and discharge
the canister into the cask, and then the cask would be sealed.
DOE evaluated the potential environmental impacts associated with
two variations for implementing this alternative. The first involved
the use of a traditional project schedule for design and construction
of the facility, estimated to take about ten years. The second was an
accelerated schedule for design and construction, estimated to take
about five years. Until the Dry Storage Facility was completed, DOE
would store the materials in existing basins, as described under
Continued Storage (No Action).
As shown in Table-2, DOE designated Improving Storage as the
preferred alternative for stabilizing some of the plutonium and uranium
vault materials.
V. Environmental Impacts of Alternatives
The Final EIS for Interim Management of Nuclear Materials evaluated
alternative stabilization methods for each category of nuclear
materials at the Savannah River Site, as shown in Table 2. DOE analyzed
the potential environmental impacts that would result from
implementation of the alternatives and believes there would be little
or no impact from implementation of any of the alternatives for any
material group in the areas of geologic resources, ecological resources
(including threatened or endangered species), cultural resources,
aesthetic and scenic resources, noise, and land use. Impacts in these
areas would be limited because facility modifications or construction
of new facilities would occur within existing buildings or
industrialized portions of the Savannah River Site. DOE anticipates
that the existing SRS workforce would support any construction projects
and other activities required to implement any of the alternatives. As
a result, DOE expects negligible socioeconomic impacts from
implementation of any of the alternatives.
Management alternatives requiring the use of the large chemical
separations facilities (the canyons and B-Lines) would have greater
environmental impacts during the time dissolving, processing or
conversion activities are underway than when these facilities are
storing nuclear materials. After materials have been stabilized,
impacts of normal facility operations related to management of those
materials would decline, and potential impacts of accidents associated
with those materials would be reduced with certain kinds of accidents
eliminated. Potential health effects from normal operations from any of
the alternatives, including those involving the operation of the canyon
facilities, would be low and well within regulatory limits.
Alternatives requiring the use of the canyons are: Processing to Metal,
Processing to Oxide, Blending Down to Low Enriched Uranium, Processing
and Storage for Vitrification in the DWPF, and Vitrification (F-
Canyon).
Improving Storage alternatives generally have lower impacts in the
near term because they involve only heating, drying and repackaging the
nuclear materials. These alternatives also potentially involve the use
of new facilities, such as an Actinide Packaging and Storage Facility
and a Dry Storage Facility. The newer facilities would incorporate
improved designs for remote handling, shielding, containment, air
filtration, etc.; these improvements could reduce worker exposures and
releases to the environment below levels associated with existing
storage basins and vaults.
Annual impacts from normal operations and potential accidents
associated with material storage would be reduced after material
stabilization alternatives are implemented. Stabilization alternatives
requiring longer periods of time to complete are estimated to have
relatively higher impacts from normal operation and potential accidents
than alternatives requiring less time to complete.
Continuing Storage (or ``No Action'') alternatives are estimated to
result in relatively low annual environmental impacts, but the impacts
would continue for an indefinite period of time. Stabilization
alternatives typically are estimated to result in slightly higher
annual environmental impacts than ``No Action'' in the near-term, but
upon completion of the stabilization action, result in lower annual
impacts. Under Continuing Storage alternatives, no actions would be
taken to chemically or
[[Page 65308]]
physically stabilize the storage conditions and reduce the potential
for accidents. All of the stabilization alternatives, upon completion
of the actions required, are estimated to reduce the potential for
accidents and the associated consequences. Several of the stabilization
alternatives would involve a short-term increase in the risks from
accidents until the required actions are completed.
Emissions of hazardous air pollutants and releases of hazardous
liquid effluents for any of the alternatives would be within applicable
federal standards and existing regulatory permits for the SRS
facilities. Similarly, high level liquid waste, transuranic waste,
mixed hazardous waste and low level solid waste generated by
implementation of any of the alternatives would be handled by existing
waste management facilities. All of the waste types and volumes are
within the capability of the existing SRS waste management facilities
for storage, treatment or disposal.
SRS facilities that will be used to stabilize and store the nuclear
materials incorporate engineered features to limit the potential
impacts of facility operations to workers, the public and the
environment. All of the engineered systems and administrative controls
are subject to DOE Order requirements to ensure safe operation of the
facilities. No other mitigation measures have been identified;
therefore DOE need not prepare a Mitigation Action Plan.
VI. Other Factors
In addition to comparing the environmental impacts of implementing
the various alternatives, DOE considered other factors in reaching the
decisions announced here. These other factors included issues addressed
by the National Academy of Sciences in the 1994 report, Management and
Disposition of Excess Weapons Plutonium; the Office of Technology
Assessment's 1993 report, Dismantling the Bomb and Managing the Nuclear
Materials; comments received during the scoping period for the EIS on
the Interim Management of Nuclear Materials, and comments received on
the Draft and Final EIS's. The other factors considered are briefly
summarized in the following paragraphs.
Implementation of certain alternatives would require construction
and operation of new facilities. The new facilities described in the
EIS are: (1) F-Canyon Vitrification Facility (for the Vitrification (F-
Canyon) Alternative), (2) a Dry Storage Facility (for the Improving
Storage Alternative for degraded reactor fuel and targets currently
stored in basins), (3) a Uranium Solidification Facility (for the
Processing to Oxide Alternative for highly enriched uranium solutions
in H-Area and the Mark-16 and -22 fuel stored in basins), (4) an
Actinide Packaging and Storage Facility (for the Processing to Metal
and Processing to Oxide Alternatives for plutonium-bearing materials,
for the Improving Storage Alternative for plutonium-bearing vault
materials, for the Processing to Oxide Alternative for neptunium-237
materials, and for the Vitrification (F-Canyon) Alternative for
materials containing plutonium and neptunium). Implementation of some
alternatives would require minor modifications of existing facilities,
as described in the EIS. Examples include minor modifications to the F-
Canyon and H-Canyon facilities to provide the capability to load and
unload radioactive solutions into containers for transport between
facilities and installation of a spare dissolver in the FA-Line
facility.
Preventing the spread of nuclear weapons has been a fundamental
national security and foreign policy goal of the United States since
1945. The current U.S. policy is summarized in the White House Fact
Sheet on Nonproliferation and Export Control Policy, dated September
27, 1993. This policy makes it clear that the United States does not
encourage the civil use of plutonium and, accordingly, does not itself
engage in plutonium reprocessing (that is, separation of plutonium from
spent nuclear fuel) for either nuclear power or nuclear explosives
purposes. In addition, it is U.S. policy to seek to eliminate where
possible the accumulation of stockpiles of highly enriched uranium and
plutonium. The stabilization alternatives vary in regard to the
attractiveness of the stabilized plutonium or highly enriched uranium
for use in nuclear weapons (either by the U.S. or an adversary). None
of the alternatives would denature or eliminate the plutonium from the
current inventory; it would still exist in some form. Of the
alternatives for stabilization of highly enriched uranium, only
Processing and Storage for Vitrification in the Defense Waste
Processing Facility and Blending Down to Low Enriched Uranium would
reduce the inventory of highly enriched uranium. Because of the
potential concern regarding any processing and consolidating plutonium
or highly enriched uranium from the SRS inventory, the Secretary of
Energy has committed that any separated or stabilized plutonium-239 and
highly enriched uranium would be prohibited from use for nuclear
explosive purposes. This prohibition would apply to plutonium-239 and
highly enriched uranium stabilized through actions implemented by this
Record of Decision.
In the EIS on the Interim Management of Nuclear Materials, DOE
examined the potential impacts associated with an integrated
implementation schedule for management of nuclear materials. DOE
examined several combinations of alternatives, or management scenarios,
including continued storage of all the materials (No Action),
stabilization using the preferred alternatives for each material, and
alternatives requiring a minimum of chemical processing. DOE expects
that it will take at least 6 to 7 years to stabilize all of the nuclear
materials at SRS under any scenario due to the resources (primarily
trained personnel) required and the time required to make facility
modifications or construct new facilities. DOE has developed an optimum
schedule of proposed actions in response to DNFSB Recommendation 94-1.
DOE will revise and update the schedule as stabilization actions
proceed and as future budget considerations dictate.
DOE considered technology availability and technical feasibility in
reaching decisions on management alternatives. DOE considered the
extent to which technology development would be required and the
likelihood of success of such endeavors. All of the alternatives are
technically feasible. In general, however, the more alternatives vary
from the historical processes and facilities used at SRS, the greater
the technical uncertainty and extent to which new facilities or
modifications to existing facilities would have to be made.
DOE evaluated labor availability and the existence of core
competency at the SRS in reaching decisions on management alternatives.
DOE expects to use the existing workforce at SRS to implement the
management alternatives selected. There would be differences between
the level of personnel knowledge and training required for each
alternative. In general, as an alternative varies from historical
processes and facilities used at the SRS for material management,
additional training of personnel may be required. The more unique or
extensive the differences from past facility operations, the more
training may be required.
In reaching decisions on management alternatives, DOE considered
the fact that many SRS facilities are 30 to 40 years old and do not
meet all current DOE requirements for the design and
[[Page 65309]]
construction of new nuclear facilities. DOE and the DNFSB have
conducted many reviews to evaluate facility vulnerabilities and assess
facility compliance with current requirements. One vulnerability common
to many older facilities is that the facility could sustain structural
damage in the event of a severe earthquake. Rather than initiate
extremely expensive modifications, DOE has chosen to mitigate the
potential consequences of a severe earthquake by using engineering
safeguards, such as structurally reinforcing tanks, and administrative
controls, such as limiting the amount of radioactive material that can
be stored in a facility. Ultimately, removal of nuclear materials from
vulnerable facilities would reduce the risks. All of the alternatives
except Continued Storage (No Action) would support DOE's objective of
removing nuclear materials from vulnerable facilities in preparation
for decontamination and decommissioning.
Some level of custodial care will be required for the nuclear
materials as long as they are stored at the SRS, and DOE considered
minimizing the level of custodial care in reaching management
decisions. Radioactive solutions require the greatest amount of
custodial care to ensure safe storage, and radioactive materials in a
glass matrix (i.e., vitrified) are expected to require the least. Many
alternatives would produce concentrated oxide or metal forms that would
be packaged and stored in compliance with new DOE standards for storage
of nuclear materials. Compliance with the storage criteria will reduce
the need to handle and repackage the material and is intended to
minimize the future level of custodial care required.
In reaching decisions on management alternatives, an important
consideration for DOE was cost. DOE evaluated the costs of implementing
the various management alternatives for each type of material on both
an individual basis and collectively, as part of an integrated
stabilization program. DOE estimates it will cost approximately $3
billion to operate and staff the facilities used to stabilize and store
the SRS nuclear materials over the next 10 years. A large fraction of
this cost (approximately $2.8 billion) would be required for continued
storage of the nuclear materials even if DOE implemented no
stabilization alternatives (i.e., No Action). DOE expects annual costs
of operating and maintaining the facilities to decrease as nuclear
materials are removed, stabilized and consolidated for interim
management. DOE expects further reductions in costs as, and if,
facilities are deactivated.
VII. Environmentally Preferable Alternatives
As described in the Final EIS for Interim Management of Nuclear
Materials, certain management alternatives are expected to result in
lower environmental impacts than others. However, a single alternative
was rarely estimated to have lower impacts for all environmental
factors evaluated by DOE. For example, an alternative might be expected
to result in lower releases of hazardous pollutants to air or water
than the other alternatives, but might generate slightly higher amounts
of radioactive waste. DOE reviewed the environmental impacts estimated
for the alternatives evaluated for each type of nuclear material and
identified the following as the environmentally preferable for each.
The health effects from any of the alternatives are all low and well
within regulatory limits. Included below is a qualitative description
of how the identified environmentally preferable alternative compared
with the other stabilization alternatives for the environmental factors
that generally are of most interest.
Plutonium-242--Processing and Storage for Vitrification (DWPF)
Processing and Storage for Vitrification in DWPF is the
environmentally preferable alternative for stabilizing the plutonium-
242 solutions stored in H-Canyon. Processing and storage for
vitrification in DWPF is estimated to result in the lowest radiological
doses to the offsite public and the SRS workers; result in air and
water emissions of hazardous pollutants comparable to the other
alternatives; and result in the least amount of transuranic and mixed
waste generated among the alternatives with comparable amounts of high
level and low level waste.
Americium and Curium--Processing and Storage for Vitrification (DWPF)
Processing and storage for vitrification in the DWPF is the
environmentally preferable alternative for stabilizing solutions and
metal targets and slugs containing americium and curium isotopes. Of
the stabilization alternatives, processing and storage for
vitrification in DWPF is estimated to result in the lowest radiological
doses to the offsite public and the SRS workers; have the lowest level
of hazardous pollutant emissions to the air with comparable levels of
liquid effluent emissions; and result in the least amount of high
level, transuranic and mixed waste with comparable amounts of low level
waste.
Neptunium-237--Vitrification (F-Canyon)
Vitrification in F-Canyon is the environmentally preferable
alternative for stabilizing solutions and targets containing neptunium.
Although vitrification in F-Canyon is estimated to result in slightly
higher radiological doses to the SRS workers, it is estimated to result
in the lowest radiological doses to the offsite public. Similarly,
although it could result in higher airborne emissions of hazardous
pollutants, the levels of liquid effluent emissions would be comparable
to the other alternatives. Vitrification (F-Canyon) would generate the
least amount of high level, transuranic and mixed waste, and would
generate comparable amounts of low level waste to the other
alternatives.
Plutonium-239 Solutions--Vitrification (F-Canyon)
Vitrification in F-Canyon is the environmentally preferable
alternative for stabilizing the plutonium-239 solutions stored in H-
Canyon. Of the stabilization alternatives, Vitrification in F-Canyon is
estimated to result in the lowest radiological doses to the offsite
public and SRS workers; result in comparable levels of hazardous
pollutant emissions to the air and water; and result in the least
amount of transuranic, mixed, and low level waste with comparable
amounts of high level waste.
Highly Enriched Uranium Solutions--Processing to Oxide
Processing to Oxide is the environmentally preferable alternative
for stabilizing highly enriched uranium solutions stored in H-Area
facilities. Although it is estimated to result in slightly higher
radiological doses to the offsite public and SRS workers, the
Processing to Oxide alternative has comparable levels of air and water
emissions to the other alternatives and would generate the least amount
of high level, transuranic, mixed and low level waste.
Plutonium and Uranium Vault Materials--Improving Storage
Improving Storage in the environmentally preferable alternative for
stabilizing plutonium and uranium vault materials. Although it is
estimated to result in higher radiological doses to the offsite public
and SRS workers, the Improving Storage alternative has comparable
levels of air and water emissions to the other alternatives and
[[Page 65310]]
would generate the least amount of high level and mixed waste, with
comparable amounts of transuranic and low level waste.
Mark-31 Targets--Improving Storage (Accelerated Schedule)
Improving Storage on an accelerated schedule is the environmentally
preferable alternative for stabilizing the Mark-31 targets. Improving
storage is estimated to result in lower radiological doses to the
offsite public with doses to the SRS workers comparable to other
alternatives; have the lowest estimates of air and water emissions; and
result in the generation of the least amount of high level and
transuranic waste with comparable levels of mixed and low level waste.
However, improving storage will not reverse or arrest the corrosion of
these targets and the release of fission products and radionuclides to
the basin water for the several years prior to the construction and
operation of the improved storage capability.
Failed TRR Fuel and EBR-II Slugs--
Improving Storage (Accelerated Schedule) Improving Storage on an
accelerated schedule is the environmentally preferable alternative for
stabilizing failed TRR fuel and EBR-II slugs stored in canisters in the
Receiving Basin for Offsite Fuels. Improving Storage is estimated to
result in the lowest radiological doses to the offsite public with
doses to the SRS workers comparable to other alternatives; have the
lowest estimates of air and water emissions; and, result in the
generation of the least amount of high level, transuranic, mixed, and
low level waste. However, as with the Mark-31 targets, improving
storage will not reverse or arrest the corrosion of the fuel or slugs
and the release of fission products and radionuclides to the basin
water for the several years prior to the construction and operation of
the improved storage capability.
VIII. Decision
After completion of the Final EIS, DOE received several letters
from stakeholders on issues related to the interim management of
nuclear materials at the SRS. Letters were received from the following
individuals and organizations: DNFSB, U.S. Senator Strom Thurmond, U.S.
Representative Charlie Norwood, U.S. Representative Lindsey Graham,
U.S. Representative Edward J. Markey, U.S. Representative Frank
Pallone, Jr., the Energy Research Foundation (ERF), the Natural
Resources Defense Council (NRDC), and Governor David M. Beasley of
South Carolina. Two principal issues were raised in the letters: (1)
the method to be used for the interim- to long-term management of spent
nuclear fuel, and (2) the operational status of the F- and H-Canyon
processing facilities. The DNFSB, Congressional, and Governor Beasley
letters recommended that DOE stabilize the Mark-16 and Mark-22 fuels
through chemical treatment (processing), and that both the F- and H-
Canyon facilities be maintained in support of DOE missions and tasks.
The ERF/NRDC joint letter urged the Department to thoroughly consider
alternatives, to include the development of new methods, for the
management of spent nuclear fuel, and to consider carefully all
factors, particularly safety, environmental, nonproliferation, and
budgetary issues, in making its materials management and facility
utilization decisions. Congressmen Markey and Pallone's joint letter
urged the Department to pursue the closing of the H-Canyon at the
earliest possible date on the understanding that substantial savings to
taxpayers could be achieved. After careful consideration of the issues
identified in these letters (addressed below), along with the analyses
of environmental impacts and other factors identified in the Final EIS,
DOE has made the following decisions for the interim management of the
nuclear materials at the Savannah River Site:
Stable Material--Continuing Storage
DOE will continue storage of the stable materials in their existing
physical and chemical forms. Programs and projects to consolidate
material storage in order to reduce surveillance and maintenance costs
to DOE will continue.
Plutonium-242--Processing to Oxide
DOE has decided to process the existing plutonium-242 solutions
stored in H-Canyon to a purified oxide in HB-Line. The plutonium-242
oxide will be packaged and stored at the SRS. Processing to Oxide was
selected for many reasons. First, the facilities and equipment to
implement the alternative already exist, with HB-Line specifically
designed for converting purified plutonium nitrate solutions to an
oxide. The portions of the HB-Line facility required to convert the
solutions to an oxide are already fully staffed and operational,
nearing completion of plutonium-238 work in support of NASA. Although
DOE could transfer the solutions to the adjacent high level waste tanks
in H-Area along with other liquid high level waste for processing,
storage and eventual vitrification in DWPF (the environmentally
preferable alternative), the concentration of plutonium-242 would be
significantly diluted due to the existing volume of liquids contained
in the high level waste tanks (approximately 1 million gallons in each
tank). The dilution and mixing of the plutonium-242 with cesium,
strontium and other long-lived fission products contained in the high
level waste tanks would effectively render any future recovery or use
of the material impractical due to cost and technical complexity. In
order not to preclude its recovery while the future use of plutonium-
242 is being decided, DOE considers it prudent to stabilize the
material to a concentrated oxide form, thereby preserving its
availability for potential use. In evaluating the alternatives, DOE
determined Processing to Oxide could be implemented sooner than the
other alternatives, thus eliminating the need to further extend storage
of the solutions. Although Processing to Oxide is not the
environmentally preferable alternative, it is estimated to result in a
similar level of impacts. Processing to Oxide is estimated to have
slightly higher radiological doses to the public and worker
populations, but result in the least amount of high level waste for the
stabilization alternatives.
Americium and Curium--Vitrification (F-Canyon)--Solutions; Continued
Storage (No Action)--Metal Targets and Slugs
DOE has decided to process the existing solutions containing
americium and curium isotopes in F-Canyon to a glass contained within
small stainless steel canisters. DOE will modify an existing portion of
F-Canyon (previously called the Multi-Purpose Processing Facility) to
install the necessary vitrification equipment. The glass canisters will
be stored at the SRS until DOE makes programmatic decisions on the use
of the americium and curium. DOE has also decided to continue wet
storage of the reactor targets and slugs until such programmatic
decisions are made.
DOE selected vitrification in F-Canyon for several reasons. First,
no capability currently exists in either F-Canyon or its associated
facilities (FA-Line or FB-Line) to convert the americium and curium
solutions to a solid physical form suitable for continued safe storage.
DOE could transfer the solutions via underground pipelines to the
adjacent high level waste tanks in F-Area. The solutions, however,
would have to remain stored in the high level waste tanks until they
could be vitrified into glass by the DWPF (the environmentally
preferable alternative). Vitrification of the
[[Page 65311]]
solutions by DWPF would not occur within the next 10 years due to the
large existing inventory (34 million gallons) of high level waste which
must be vitrified in DWPF. Transfer of the solutions to the high level
waste tanks would result in significant dilution of the concentration
of the americium and curium isotopes due to the large volume of the
tanks (approximately 1 million gallons). The americium and curium
isotopes would also be mixed with long-lived fission products such as
cesium and strontium if transferred to the high level waste tanks. The
vitrified glass form produced in DWPF would contain very dilute
quantities of americium and curium combined with highly radioactive
fission products. This would render use of the americium and curium
isotopes impractical due to the technical complexity and cost of future
recovery.
To maintain the americium and curium in a concentrated physical
form, thus preserving their potential future use, DOE evaluated
alternatives for converting the solutions to either an oxide or glass.
Either form could support future use of the material, if required. The
conversion process associated with the two alternatives would require a
similar level of modifications and new equipment to be installed in F-
Canyon. However, DOE found that the glass form offers significant
advantages over the oxide form for future storage and handling. The
glass matrix produced by the vitrification process provides some
``self-shielding'' compared to oxide. This reduces the radiation levels
associated with the glass form, thereby reducing exposure to workers.
The glass matrix is also a much less dispersible form of radioactive
material compared to the oxide in the event of a severe facility-
related accident, such as a major fire. Americium and curium isotopes
do not pose a nonproliferation concern, irrespective of their physical
form. Existing personnel at SRS will be used to operate the facilities
and equipment required, and the level of additional training required
would be similar whether DOE selected conversion to oxide or glass.
DOE has decided to maintain storage of the metal targets and slugs
containing significant quantities of americium and curium isotopes in
the existing storage basins at SRS primarily because there is not an
immediate need for the isotopes. The targets are stored in the
Receiving Basin for Offsite Fuel (RBOF). The RBOF facility has
excellent water chemistry and the targets are in good physical
condition, capable of being safely stored over the next 10 years. The
metal slugs represent a very small amount of nuclear material whose
continued storage can be accommodated by relocation to either the RBOF
facility or the K-Reactor disassembly basin. DOE has made physical
upgrades to the K-Reactor disassembly basin to provide storage
conditions comparable to those in RBOF. By maintaining the targets and
slugs in storage at the SRS, DOE can preserve the option of recovering,
if needed, the americium and curium isotopes at a later date for
programmatic use. The targets and slugs contain varying amounts and
isotopes of americium and curium. It would not necessarily be
advantageous for DOE to process and recover all of the americium and
curium isotopes into a single physical form for continued storage,
because such an operation would result in the mixing of many isotopes,
increasing the technical complexity of their future separation and
recovery or making it impractical.
Neptunium-237--Vitrification (F-Canyon) or Processing to Oxide
DOE has narrowed its alternatives under consideration for the
stabilization of the neptunium-237 materials (neptunium contained in
the H-Canyon solutions and nine (9) obsolete reactor targets) into
either one of two physical forms: (1) a glass matrix using the same
modified portion of F-Canyon used to vitrify the americium and curium
solutions (the environmentally preferable alternative), or (2) a
purified oxide using the HB-Line facility. Only one of these
stabilization methods will be used. Both the vitrified glass and oxide
forms can be stored safely pending DOE's decision on use or
disposition. To implement the vitrification alternative, DOE would move
the neptunium solutions from H-Area to F-Area using a special truck
container designed for transport of highly radioactive solutions. The
nine (9) obsolete reactor targets containing neptunium would be
transported to F-Canyon in shielded casks, dissolved and the neptunium
chemically separated from radioactive decay products and other
impurities. The resulting purified neptunium solution would be
vitrified in F-Canyon. SRS would store the canisters of neptunium glass
until programmatic decisions on neptunium's use are made by DOE. To
implement the Processing to Oxide alternative, DOE would start up and
operate the Phase II portion of the HB-Line facility and would dissolve
and process the obsolete reactor targets in H-Canyon.
Potential environmental impacts, as detailed in the Interim
Management of Nuclear Materials EIS, of implementing any of the
stabilization alternatives, irrespective of location, are low and well
within acceptable regulatory and management limits. In addition, there
are no substantial differences in potential environmental impacts
should DOE operate either or both canyon facilities.
The final form of the neptunium depends on actions taken, if any,
to consolidate certain activities in the F-Canyon as outlined in the
facility utilization strategy report. The study principally considers
what effect the consolidation of two primary processing areas to one
would have on the ability to stabilize nuclear materials at the SRS.
Budgetary pressures and safety requirements as well as preserving
capability for future missions necessitates a thorough examination of
the options for these facilities. The report is available to the
public. A subsequent Record of Decision will be issued when DOE's
review of the utilization strategy, the EIS, and the other relevant
factors is complete.
Highly Enriched Uranium Solutions--Blending Down to Low Enriched
Uranium
DOE has selected Blending Down to Low Enriched Uranium for
stabilization of highly enriched uranium (HEU) solutions. These include
existing HEU solutions stored in H-Area facilities and any HEU
solutions produced in conjunction with the stabilization of other
materials (e.g., plutonium and uranium vault materials). DOE will
modify portions of the F- and H-Canyon facilities to provide the
capability to load and unload containers for the transport of depleted,
natural or low enriched uranium solutions. DOE will dissolve depleted
uranium oxide in FA-Line. DOE will transport depleted uranium solutions
to H-Area for blending with the highly enriched uranium solutions. The
resulting low enriched uranium solutions will be transported back to F-
Area and converted to an oxide in FA-Line. The low enriched uranium
oxide will be stored at SRS until disposition decisions can be
implemented.
DOE selected this stabilization alternative for several reasons.
Blending down the highly enriched uranium will reduce DOE's inventory
of this weapons-useable fissile material. This alternative can be
implemented expeditiously at relatively low cost. Processing the
solutions to a highly enriched uranium oxide (the environmentally
preferable alternative) would require the completion and startup of the
Uranium Solidification Facility. Processing for storage and
vitrification in the DWPF would extend
[[Page 65312]]
the period of HEU solution storage with its attendant vulnerabilities
while mechanisms are developed to assure the safe transfer and
stabilization of this fissile material through the affected facilities.
Plutonium and Uranium Stored in Vaults--Improving Storage, Processing
to Metal, Processing to Oxide, and Vitrification (F-Canyon)
DOE has decided to use a variety of alternatives to stabilize
plutonium and uranium materials stored in vaults at SRS. DOE is
installing a glove box in FB-Line (based upon previous decisions to
stabilize F-Canyon plutonium solutions--see ``Background'') to provide
the capability to handle and package plutonium metal without the use of
plastic and other organic materials (rubber, elastomeric seals, etc.).
This will provide SRS the capability to package (or repackage)
plutonium metal in accordance with the DOE storage standard. Upon
completion of the FB-Line modifications, DOE will repackage plutonium
metal stored at SRS in accordance with the storage standard. This
implements the environmentally preferable alternative for the candidate
plutonium metals.
DOE will dissolve some of the existing vault materials that are
Candidates for Stabilization in FB-Line and F-Canyon, and H-Canyon and
HB-Line, chemically separate the plutonium from impurities that
contribute to the stability concerns and radioactive decay products,
and process the plutonium to a metal in FB-Line and an oxide in HB-
Line. After vitrification of the americium and curium solutions in F-
Canyon (see above) and subject to successful analytical laboratory
work, timing and facility availability, and future decisions on
plutonium disposition, DOE may stabilize some of the plutonium-bearing
vault materials by vitrification in F-Canyon. DOE will dissolve vault
materials containing scrap amounts of plutonium-238 that require
chemical stabilization in HB-Line, chemically separate the plutonium-
238 from impurities that contribute to the stability concerns and
radioactive decay products, and convert the plutonium-238 to an oxide
in HB-Line. The plutonium-238 oxide will be stored in an existing SRS
vault.
DOE has decided to construct an Actinide Packaging and Storage
Facility to provide the capability for handling, heating and packaging
of plutonium oxide and metal in accordance with the storage standard
(the environmentally preferable alternative) and to provide space
necessary to consolidate storage of plutonium and special actinides at
the SRS. DOE will incorporate requirements of the IAEA into the design
and construction of the facility to provide the latitude for future
international safeguards inspections. DOE is also pursuing
declassification of information related to the amount of plutonium
resulting from stabilization actions at the SRS that will be stored in
the new packaging and storage facility.
The plutonium oxide and existing SRS vault materials that do not
require chemical processing for stabilization, will be heated and
repackaged in the Actinide Packaging and Storage Facility to meet
criteria in the DOE storage standard. The amount of vault materials
stabilized using each of the methods will be dependent upon: (a) the
physical condition and chemical composition of the material (which DOE
will determine upon opening each of the containers or packages inside a
glove box in either FB-Line or HB-Line) and, (b) the availability of
the required facilities. The plutonium will be stored at SRS until DOE
can implement long-term storage or disposition decisions. Uranium
recovered from the chemical stabilization of any vault materials will
be blended down to low enriched uranium and the solutions will be
stored or converted to an oxide, as described under the stabilization
of highly enriched uranium solutions.
As previously discussed, the Improving Storage alternative is the
environmentally preferable alternative. The environmental impacts
associated with the other alternatives selected for stabilization of
vault materials which require chemical processing (i.e., Processing to
Metal, Processing to Oxide, and Vitrification in F-Canyon) all involve
slightly higher but similar levels of impacts.
As explained in the Final EIS, some of the containers stored in
vaults at SRS have internal packaging configurations which are unknown
and the exact chemical composition of the material inside the
containers may also be unknown, with the exception of its content of
special nuclear materials. Because of the unknown content of some of
the vault containers, and in light of pending DOE decisions on long-
term management or disposition of surplus materials, several
stakeholder groups have raised concerns regarding DOE's current and
future compliance with the Resource Conservation and Recovery Act
(RCRA). DOE has provided existing information on the vault materials
and other materials stored at SRS to the applicable regulatory agency
for RCRA at SRS, the South Carolina Department of Health and
Environmental Control (SCDHEC). DOE is continuing the dialog with
SCDHEC on the applicability of RCRA to any of the nuclear materials
that will be stabilized as a result of this Record of Decision and will
take appropriate management actions, as necessary to ensure compliance
with RCRA.
Mark-31 Targets--Processing to Metal
DOE has selected Processing to Metal for stabilization of the Mark-
31 targets stored in the F-Canyon basin, reactor disassembly basins and
the Receiving Basin for Offsite Fuels (RBOF). DOE will dissolve the
Mark-31 targets in F-Canyon and chemically separate the plutonium and
depleted uranium from fission products and other materials. The
plutonium solutions will be processed to metal in FB-Line. After
modification of the FB-Line (see vault materials above), the metal will
be packaged to meet the DOE storage standard. The plutonium metal will
remain at SRS until DOE can implement long-term storage or disposition
decisions on weapons usable forms of plutonium. The depleted uranium
solutions recovered from dissolving the targets will be used to blend-
down the highly enriched uranium solutions in H-Area (see highly
enriched uranium solutions discussion above).
The stabilization of the Mark-31 targets by processing to metal can
be accomplished one and one-half to nine years earlier than the other
stabilization alternatives (four to nine years earlier than Improved
Storage (the environmentally preferable alternative)). DOE believes
further delay in removing the Mark-31 targets from wet basin storage
where they have undergone significant corrosion and release of fission
and radioactive products would serve no practicable purpose. This
selected stabilization alternative relies upon existing operating
equipment and trained personnel; the stabilized plutonium metal will be
repackaged in conformance with DOE's storage standard within 3 years
using the FB-Line bagless transfer facility. The technical uncertainty
for this alternative is very low and the associated costs are well
established. Potential waste generation impacts are comparable to the
other alternatives, but greater than the environmentally preferable
alternative for high level and transuranic waste, but lower for
hazardous/mixed and low level radioactive wastes. Potential safety and
health impacts to workers and the public are comparable for all the
stabilization alternatives. Potential impacts to air and water
resources are comparable to the other processing alternatives, and
greater, but well within
[[Page 65313]]
regulatory and management control limits, than the Improved Storage
alternatives. Processing and Storage for Vitrification in DWPF would
make the plutonium more difficult to recover than the selected
alternative. However, this alternative would also require the extended
wet storage of these targets, continuing their corrosion and the
release of fission and radioactive products to the basin water.
The selected stabilization action will result in plutonium metal, a
weapons-useable product. However, the quantity produced will be a small
fraction of DOE's existing inventory of plutonium metal, and DOE
believes this small amount does not present nuclear proliferation
concerns. None of the stabilization alternatives would denature the
plutonium to preclude its recovery and use in nuclear weapons
manufacture. The plutonium metal produced from this stabilization
action will be prohibited for use in nuclear weapons. In addition, DOE
is pursuing options for placing this material under international
safeguards (e.g., International Atomic Energy Agency).
Taiwan Research Reactor Fuel and Experimental Breeder Reactor-II
Slugs--Processing to Metal
The 81 canisters of failed Taiwan Research Reactor fuel and a
single canister of Experimental Breeder Reactor-II slugs will be
dissolved in F-Canyon and the plutonium recovered will be converted to
a metal in FB-Line. The processing of these materials will be done in
conjunction with processing of the Mark-31 targets (see above). Upon
installation of the new glove box in FB-Line, the plutonium metal will
be packaged in accordance with the DOE storage standard and be placed
in an SRS vault until long-term storage or disposition decisions can be
implemented on weapons usable plutonium. Natural or depleted uranium
recovered by processing the fuel and slugs located in a failed canister
will be stored at SRS in tanks or used to support blending down of
highly enriched uranium solutions (see above).
DOE selected processing to metal for the Taiwan Research Reactor
fuel and Experimental Breeder Reactor-II slugs for similar reasons as
described for the Mark-31 targets. These materials are very similar in
composition to the Mark-31 targets and can be stabilized concurrently,
four to nine years earlier than the environmentally preferred
alternative (Improving Storage--Accelerated Schedule). Potential waste
generation impacts from the selected alternative are greater than those
of the environmentally preferable alternative, but less than potential
high-level waste impacts (equivalent DWPF canisters) from the
Processing and Storage for Vitrification in DWPF alternative. The
Processing and Storage for Vitrification in DWPF would make the
plutonium more difficult to recover. However, this alternative would
require the extended wet storage of these elements, continuing their
corrosion and the release of fission and radioactive products to the
basin water.
As with the Mark-31 targets, the plutonium metal produced would be
in a form that is weapons-useable. None of the stabilization
alternatives would denature the plutonium to preclude its recovery and
use in nuclear weapons manufacture. The quantity of plutonium to be
produced is such a small amount (a very small fraction) of DOE's
current plutonium metal inventory that, standing alone, it does not
present nuclear proliferation concerns. The plutonium metal produced
will be prohibited for use in nuclear weapons. In addition, DOE is
pursuing options for placing this material under international
safeguards (e.g., International Atomic Energy Agency).
If after removing the Mark-31 targets, failed TRR fuel, and the
failed canister of EBR-II slugs from RBOF, DOE determines that
additional fuel, targets, or canisters have failed, as indicated by gas
releases from a canister, or visible failure of cladding or canisters,
DOE would categorize those materials as Candidates for Stabilization.
DOE would perform the appropriate National Environmental Policy Act
review and evaluation for the stabilization of any additional materials
in RBOF that may be determined at a later date to have failed (e.g.,
Supplement Analysis).
Potential environmental impacts, as detailed in the Interim
Management of Nuclear Materials EIS, of implementing any of the
stabilization alternatives, irrespective of location, are low and well
within acceptable regulatory and management limits. In addition, there
are no substantial differences in potential environmental impacts
should DOE operate either or both canyon facilities. DOE is considering
this study and the results of the Interim Management of Nuclear
Materials EIS, and at this time is announcing a narrowing of potential
stabilization alternatives for the following materials.
Plutonium-239 Solutions--Processing to Metal, Processing to Oxide, or
Vitrification (F-Canyon)
DOE will stabilize the existing plutonium-239 solutions stored in
H-Canyon using one of three alternatives: (1) Processing the solutions
to an oxide in HB-Line, (2) processing to a glass matrix by vitrifying
the solutions in F-Canyon (the environmentally preferable alternative),
or (3) processing to a metal in FB-Line. Only one of these
stabilization methods will be used. To implement the processing to
oxide alternative, DOE would start up and operate Phase II of the HB-
Line facility. The oxide produced would be packaged and stored in an
existing vault at SRS until the new Actinide Packaging and Storage
Facility is constructed. To implement the vitrification alternative,
DOE would transport the solutions from H-Canyon to F-Canyon using a
special truck/container as described above for the movement of the
neptunium solutions and the modifications made to F- and H-Canyon for
loading/unloading of the solutions. The plutonium would be vitrified in
F-Canyon using the equipment installed for vitrification of the
americium and curium solutions. The canisters of plutonium glass would
be stored in an existing SRS vault or the Actinide Packaging and
Storage Facility, upon construction. To implement the processing to
metal alternative, DOE would transfer the solutions to F-Canyon in the
same manner as the vitrification alternative. The plutonium would be
converted to a metal using the currently operating F-Canyon and FB-Line
facilities. The metal would be packaged in conformance with DOE's
storage standard and stored in an existing vault at SRS until the new
Actinide Packaging and Storage Facility is available. Using any of
these methods, the form of the plutonium (metal, glass matrix or oxide)
will remain stored at SRS until DOE implements long-term storage and
disposition decisions on weapons usable forms of plutonium. If
vitrification of the plutonium solutions cannot be supported for
technical or programmatic reasons, but the solutions are transferred to
F-Canyon, then DOE will stabilize the plutonium by conversion to metal
using the F-Canyon and FB-Line facilities.
One of the stabilization alternatives remaining under consideration
(Processing to Metal) would result in plutonium metal, a weapons-
useable product. However, the quantity produced will be a small
fraction of DOE's existing inventory of plutonium metal, and DOE
believes this small amount does not present nuclear proliferation
concerns. None of the stabilization alternatives would denature the
plutonium to preclude its recovery and used in nuclear weapons
manufacture. The plutonium metal produced from this stabilization
action will be prohibited to be used for nuclear
[[Page 65314]]
explosive purposes. In addition, DOE is pursuing options for placing
this material under international safeguards (e.g., International
Atomic Energy Agency).
Potential environmental impacts, as detailed in the Interim
Management of Nuclear Materials EIS, of implementing any of the
stabilization alternatives, irrespective of location, are low and well
within acceptable regulatory and management limits. In addition, there
are no substantial differences in potential environmental impacts
should DOE operate either or both canyon facilities.
The final form of the plutonium solutions depends on actions taken,
if any, to consolidate certain activities in the F-Canyon as outlined
in the facility utilization strategy report. A subsequent Record of
Decision will be issued when DOE's review of the utilization strategy,
the EIS, and the other relevent factors is complete.
IX. Preferred Alternatives for Stabilizing Mark-16 and Mark-22 Fuels
and Other Aluminum-clad Targets
In addition to reaching decisions on the management and
alternatives under consideration for the materials described above, DOE
is now designating its preferred alternatives for stabilization of the
Mark-16 and Mark-22 fuels and Other Aluminum-clad Targets. As explained
in the Final EIS, DOE identified Continued Storage (No Action) as the
preferred alternative for management of these materials pending further
analysis of whether alternatives involving chemical processing or dry
storage were preferable as a stabilization method. The additional
reviews were prompted by public comments that DOE received on potential
stabilization alternatives involving technologies other than chemical
processing. Based on these additional reviews (discussed in Attachment
2 of the Facility Utilization Strategy), DOE is designating the
following as preferred stabilization alternatives:
Mark-16 and Mark-22 Fuels--Blending Down to Low Enriched Uranium
DOE is designating Blending Down to Low Enriched Uranium as its
preferred alternative for stabilization of the Mark-16 and Mark-22
fuels. Under this alternative, DOE would remove the Mark-16 and Mark-22
fuels from the water- filled basins in which they are stored and
transport them to one, or both, of the canyons using the existing SRS
rail casks. All of the cask shipments would be confined within the
boundaries of SRS, occurring near the center of the site. The fuel
assemblies would be dissolved in nitric acid. The highly enriched
uranium contained in the fuel would be chemically separated from
fission products and other materials. The highly enriched uranium would
be blended with existing SRS inventories of depleted uranium to produce
a low enriched uranium solutions. The resulting low enriched uranium
solution will be stored or converted to an oxide in FA-Line. The low
enriched uranium will be stored at SRS until disposition decisions can
be made. The neptunium separated during the processing of the fuels
would be stabilized with the other neptunium solutions.
DOE is designating Blending Down to Low Enriched Uranium as the
preferred alternative for several reasons. Stabilization of the fuels
with their removal from basin wet storage and elimination of the wet
storage vulnerabilities through processing can be accomplished two to
seven years earlier than the improved storage alternatives. Blending
down to LEU reduces the HEU inventory and eliminates nonproliferation
and security issues associated with the indefinite storage of HEU fuel
which is not self-protecting. Cost and cost uncertainties have also
played a significant role in the selection of the preferred
stabilization alternative. Near-term annual costs to process and blend
down the HEU to LEU are estimated at $20 million to $95 million less
than for the improved storage alternatives. Substantial uncertainty
exists concerning the disposition of dry-stored (improved storage) HEU
spent fuel. Little uncertainty exists with the stabilization of the
fuels through blending down to LEU. Life-cycle costs evaluations favor
blending down to LEU ($38 million to greater than $1 billion
advantage)[Facility Utilization Strategy, Attachment 2]. The potential
environmental impacts from any of the stabilization alternatives are
acceptable and well below any regulatory or management control limits.
Projected impacts evaluated in the Final EIS are several times lower
for the improved storage alternatives than the preferred blending down
to LEU alternative.
Other Aluminum-clad Targets--Processing and Storage for Vitrification
in the DWPF
DOE is designating Processing and Storage for Vitrification in the
DWPF as its preferred alternative for stabilization of the other
aluminum-clad targets stored in reactor disassembly basins at SRS.
Under this alternative, DOE would remove the other aluminum-clad
targets stored in reactor disassembly basins and transport them to one
of the canyons via SRS rail casks. The targets would be dissolved, the
resulting solutions chemically adjusted, and transferred to the
adjacent underground high level waste tanks. The solutions would be
stored in the high level waste tanks until they could be processed in
conjunction with the other high level waste in the tanks. The high
level waste would eventually be vitrified in the DWPF. The stainless
steel canisters of glass would be stored in a facility adjacent to the
DWPF, awaiting geological disposal by DOE. DOE is designating this
alternative as its preferred stabilization alternative for several
reasons. These targets contain little or no fissile material, yet are
in a variety of physical forms and shapes. Their dissolution and
transfer for vitrification in DWPF (the environmentally preferable
alternative) has a minimal impact on all processing facilities and
places these many forms into a single physical form suitable for future
emplacement in a geological repository. Improved storage would require
the development of one or more packaging configurations for repository
emplacement. Although vitrification in DWPF will not occur for several
years, processing and storage for vitrification in DWPF can be
implemented one to six years earlier than the improved storage
alternatives. This will remove the targets and their deteriorating
condition from the reactor disassembly basins, precluding further
release of radioactivity to the basin water. As with the improved
storage alternatives for the Mark-16 and Mark-22 fuels, near-term costs
are considerably less for the processing alternative as compared with
the improved storage alternative. The potential environmental impacts
from any of the stabilization alternatives are acceptable and well
below any regulatory or management control limits. As with the Mark-16
and Mark-22 fuels, projected impacts for the improved storage
alternatives are lower than the preferred alternative of processing and
storage for vitrification in DWPF.
Decisions on facility utilization will determine the canyon
location(s) for implementing the preferred stabilization alternatives
for the Mark-16 and Mark-22 fuels, and the other aluminum-clad targets.
DOE will issue a Record of Decision(s) for the stabilization of these
materials no sooner than thirty (30) days following the availability of
this notice.
X. Conclusion
While the Final EIS focuses on the interim management of nuclear
[[Page 65315]]
materials at the Savannah River Site, the decisions associated with the
safe management of these materials directly affect the operational
status of the nuclear material processing facilities at the Site. These
decisions have been made in the context of then Secretary Watkins' 1992
decision to phase out reprocessing at the Savannah River Site. The
decisions in this ROD are structured to effect the earliest completion
of actions necessary to stabilize or convert nuclear materials into
forms suitable for safe storage and prepare the facilities for
subsequent shutdown and deactivation. The actions being implemented
will support the consolidation of the storage of nuclear materials at
the SRS. To a great extent, the alternatives will result in
stabilization of the nuclear materials and alleviation of associated
vulnerabilities within the time frame recommended by the DNFSB.
The stabilization decisions utilize existing facilities and
processes to the extent practical; can be implemented within expected
budget constraints and minimal additional training to required
personnel; rely upon proven technology; and using an integrated
approach, represent the optimum use of facilities to stabilize the
materials in the shortest amount of time. Although minor modifications
of a few facilities will be required, only two new facilities will be
needed: (a) design and construction of an Actinide Packaging and
Storage Facility in F-Area, and (b) a small vitrification facility
within the existing F-Canyon. The decisions in this ROD do not imply or
contribute to any poential decision to change the baseline canyon
operating strategy from the current two-canyon approach.
DOE expects to make decisions related to the future management of
foreign research reactor fuel and on strategies for the disposition of
surplus nuclear materials within the next year. Similarly, DOE is
evaluating alternatives for stabilizing nuclear materials stored at
other locations in the DOE complex. Several years will be required to
achieve stabilization of the nuclear materials within the scope of this
Record of Decision. Stabilization of the nuclear materials at SRS will
entail the operation of many portions of the chemical processing
facilities. Consistent with DNFSB Recommendation 94-1, this will
preserve DOE's capabilities related to the management and stabilization
of other nuclear materials until such decisions are made.
In summary, the Department has structured its decisions on interim
actions related to management of the nuclear materials at SRS to
achieve stabilization as soon as possible, consistent with earlier
decisions to phase out processing activities at the Savannah River
Site, while supporting U.S. nonproliferation policies in a safe and
cost effective manner.
Issued at Washington, DC, December 12, 1995.
Thomas P. Grumbly,
Assistant Secretary for Environmental Management.
Table 1.--Nuclear Materials at the Savannah River Site
[From DOE/EIS-0220, ``Interim Management of Nuclear Materials'']
----------------------------------------------------------------------------------------------------------------
Description Quantity a Location(s)
----------------------------------------------------------------------------------------------------------------
Stable
Spent fuel...................... 3,000 items...................... Receiving Basin for Offsite Fuel (RBOF).
Unirradiated fuel, targets, 315,000 items.................... Buildings 305A, 313-M, 315-M, 320-M, 321-M,
reactor components, and scrap 322-M, 341-M, K- and L-Reactor Assembly
from fabrication operations. Areas.
Unirradiated fuel, targets, and 6,900 items...................... K- and L-Reactors.
reactor components.
Unirradiated and irradiated 420 items........................ C-, K-, L- and P-Reactors.
reactor components and control
rods.
Depleted uranium oxide.......... 36,000 drums..................... R-Reactor, Buildings 221-1F, 221-12F, 221-
21F, 221-22F, 707-R, 714-7N, 728-F, 730-F,
and 772-7B.
Depleted uranium solutions...... 300,000 liters (78,000 gallons).. F-Canyon, F-Area Outside Facilities, and
TNX.
Sources, standards, and samples. 20,000 items..................... Sitewide.
Laboratory materials used in 260 items........................ Savannah River Technology Center (SRTC).
research and development.
Programmatic
Plutonium-242 solutions......... 13,000 liters (3,500 gallons).... H-Canyon.
Americium and curium solutions 14,000 liters (3,800 gallons).... F-Canyon.
and targets.
65 assemblies.................... RBOF.
60 slugs......................... P-Reactor disassembly basin.
114 slugs........................ RBOF.
Neptunium solutions and targets. 6,100 liters (1,600 gallons)..... H-Canyon.
9 targets........................ Building 321-M.
Candidates for Stabilization
Plutonium-239 solutions......... 34,000 (9,000 gallons)........... H-Canyon.
Highly enriched uranium 228,000 liters (60,000 gallons).. H-Canyon and H-Area Outside Facilities.
solutions.
Plutonium vault materials....... 2,800 packages................... FB-Line, HB-Line, Building 772-F, Building
235-F, and SRTC.
Mark-31 targets................. 16,000 slugs..................... K-Reactor, L-Reactor, F-Canyon, and RBOF.
Mark-16 and Mark-22 fuels....... 1,900 assemblies................. K-, L-, and P-Reactors and H-Canyon.
Other aluminum-clad targets..... 1,800 slugs and assemblies....... K-, L-, and P-Reactors.
[[Page 65316]]
Failed TRR b and EBR-II c slugs. 82 canisters..................... RBOF.
----------------------------------------------------------------------------------------------------------------
a Quantities of materials shown are approximate. Quantities of radioactive solutions stored in tanks fluctuate
due to natural evaporation and the addition of materials (e.g., nitric acid) to maintain chemistry within
established parameters.
b Taiwan Research Reactor--81 canisters.
c Experimental Breeder Reactor-II--1 canister.
Table 2.--Alternatives for the Interim Management of Nuclear Materials at the SRS
[From DOE/EIS-0220, ``Interim Management of Nuclear Materials'']
--------------------------------------------------------------------------------------------------------------------------------------------------------
Alternatives
---------------------------------------------------------------------------------------------------
Processing
Material Continuing Blending and storage
storage (no Processing Processing down to low for Vitrification Improving
action) to metal to oxide enriched vitrification (F-canyon) storage
uranium (DWPF)a
--------------------------------------------------------------------------------------------------------------------------------------------------------
Stable.............................................. ............ ............ ............ ............. ............. ............
Plutonium-242....................................... x x ............ x x ............
Americium and curium................................ 1/2 ............ x ............ x c ............
Neptunium........................................... x ............ ............ x x ............
Plutonium-239 solutions............................. x x ............ x x ............
Highly enriched uranium solutions................... x ............ x x ............. ............
Plutonium and uranium in vaultsd.................... x ............ x
Mark-31 targets..................................... x x ............ x x x
Mark-16 and Mark-22 fuels........................... ............ x x x ............. x
Other aluminum-clad targets......................... ............ ............ ............ x ............. x
Failed TRR fuel and EBR-II slugse................... x x ............ x x x
--------------------------------------------------------------------------------------------------------------------------------------------------------
x=alternative evaluated.
=preferred alternative designated by DOE in Final EIS.
aDWPF=Defense Waste Processing Facility.
bTargets.
cSolutions.
dFor the plutonium and uranium stored in vaults, there were four preferred alternatives. DOE will base its choice of the applicable alternative for a
particular solid upon inspection of the material.
eTRR=Taiwan Research Reactor, EBR-II--Experimental Breeder Reactor-II.
[FR Doc. 95-30750 Filed 12-18-95; 8:45 am]