Central Valley Project Notice of Rate Order No. WAPA-72
Federal RegisterOct 10, 1995
Ask Donna
What actually matters in this document.
Text
DEPARTMENT OF ENERGY
Western Area Power Administration
Central Valley Project Notice of Rate Order No. WAPA-72
AGENCY: Western Area Power Administration, DOE.
ACTION: Notice of Rate Order--Central Valley Project commercial firm
power rate adjustment.
-----------------------------------------------------------------------
SUMMARY: Notice is given of the confirmation and approval by the Deputy
Secretary of the Department of Energy (DOE) of Rate Order No. WAPA-72
and Rate Schedule CV-F8 placing provisional commercial firm power rates
for capacity and energy from the Central Valley Project (CVP) of the
Western Area Power Administration (Western) into effect on an interim
basis. The provisional rates, will remain in effect on an interim basis
until the Federal Energy Regulatory Commission (FERC) confirms,
approves, and places them into effect on a final basis or until they
are replaced by other rates.
The commercial firm power rates will provide sufficient revenue to
pay all annual costs including interest expense, plus repayment of
required investment within the allowable time period. These rates
consist of a capacity rate, energy base rate, and energy tier rate. The
energy tier rate is applied to energy at a 70 percent and higher load
factor, and is based on the average CVP Northwest energy rate. The load
factor is computed based on the lesser of the customer's (1) maximum
demand for the month, or if a scheduled customer, the maximum scheduled
demand for the month; or (2) the customer's Contract Rate of Delivery
(CRD) for commercial firm power.
A comparison of existing and provisional rates follows:
Comparison of Existing and Provisional Rates
[Commercial Firm Power Rate Schedule]
----------------------------------------------------------------------------------------------------------------
Effective period Existing Provisional Percent Change
----------------------------------------------------------------------------------------------------------------
Composite Rate (mills/kWh):
10/01/95 to 09/30/96..................................... 31.55 23.35 (26)
10/01/96 to 09/30/97..................................... 31.55 25.00 (21)
10/01/97 to 04/30/98..................................... 34.37 26.50 (23)
Capacity Rate ($/kW/month):
10/01/95 to 09/30/96..................................... 6.57 4.03 (39)
10/01/96 to 09/30/97..................................... 6.57 4.32 (34)
10/01/97 to 04/30/98..................................... 7.16 4.58 (36)
Energy Base Rate (mills/kWh):
10/01/95 to 09/30/96..................................... 17.73 14.83 (16)
10/01/96 to 09/30/97..................................... 17.73 15.93 (10)
10/01/97 to 04/30/98..................................... 19.33 16.93 (12)
Energy Tier Rate (mills/kWh):
10/01/95 to 09/30/96..................................... 34.70 25.90 (25)
10/01/96 to 09/30/97..................................... 34.70 26.27 (24)
10/01/97 to 04/30/98..................................... 37.46 26.48 (29)
----------------------------------------------------------------------------------------------------------------
[[Page 52672]]
DATES: Rate Schedule CV-F8 will be placed into effect on an interim
basis on October 1, 1995 and will be in effect until FERC confirms,
approves, and places the rate schedule in effect on a final basis for a
2\1/2\-year period, or until the rate schedule is superseded.
FOR FURTHER INFORMATION CONTACT:
Mr. James C. Feider, Area Manager, Sacramento Area Office, Western Area
Power Administration, 114 Parkshore Drive, Folsom, CA 95630, Telephone
(916) 353-4418
Mr. Joel K. Bladow, Assistant Administrator for Washington Liaison,
Power Marketing Liaison Office, Room 8G-027, Forrestal Building, 1000
Independence Avenue SW., Washington, DC 20585-0001, Telephone (202)
586-5581
SUPPLEMENTARY INFORMATION: By Amendment No. 3 to Delegation Order No.
0204-108, published November 10, 1993 (58 FR 59716), the Secretary
delegated (1) the authority to develop long-term power and transmission
rates on a nonexclusive basis to the Administrator of Western; (2) the
authority to confirm, approve, and place such rates into effect on an
interim basis to the Deputy Secretary; and (3) the authority to
confirm, approve, and place into effect on a final basis, to remand, or
to disapprove such rates to FERC. Existing DOE procedures for public
participation in power rate adjustments are located at 10 CFR Part 903.
These power rates were developed pursuant to section 302(a) of the
DOE Organization Act, 42 U.S.C. 7152(a), through which the power
marketing functions of the Secretary of the Interior and the Bureau of
Reclamation (Reclamation) under the Reclamation Act of 1902, 43 U.S.C.
371 et seq., as amended and supplemented by subsequent enactments,
particularly section 9(c) of the Reclamation Project Act of 1939, 43
U.S.C. 485h(c), and other acts specifically applicable to the project
involved, were transferred to and vested in the Secretary of Energy.
The Procedures for Public Participation in Power and Transmission
Rate Adjustments and Extensions, 10 CFR Part 903, have been followed by
Western in the development of these commercial firm power rates. A
summary of the steps Western took to ensure involvement of interested
parties in the rate process follows:
1. The proposed rate adjustment was initiated on June 9, 1995, when
a letter announcing an informal customer meeting was mailed to all
commercial firm power customers and interested parties. The meeting was
held on June 26, 1995, in Sacramento, California. At this informal
meeting, Western explained the rationale for the rate decrease and rate
design methodology, and answered questions.
2. A Federal Register notice was published on July 10, 1995 (60 FR
35556), officially announcing the commercial firm power rate
adjustment, initiating the public consultation and comment period,
announcing the public information and public comment forums, and
presenting procedures for public participation.
3. On July 17, 1995, letters were mailed from Western's Sacramento
Area Office to all commercial firm power customers and interested
parties transmitting the Federal Register notice of July 10, 1995.
4. On July 19, 1995, a rate brochure was mailed to all commercial
firm power customers and interested parties.
5. At the public information forum held on the morning of July 26,
1995, Western explained the rationale for the rate decrease and rate
design methodology in greater detail, and answered questions.
6. The comment forum was held on the afternoon of July 26, 1995, to
give the public an opportunity to comment for the record. Two customer
representatives made oral comments.
7. Eight comment letters were received during the consultation and
comment period. The consultation and comment period ended August 11,
1995. All formally submitted comments have been considered in the
preparation of this rate order.
Rate Order No. WAPA-72, confirming, approving, and placing the
proposed CVP commercial firm power rates into effect on an interim
basis, is issued, and the new Rate Schedule CV-F8 will be submitted
promptly to FERC for confirmation and approval on a final basis.
Issued in Washington, D.C., September 19, 1995.
Charles B. Curtis,
Deputy Secretary.
Order Confirming, Approving, and Placing the Central Valley Project
Commercial Firm Power Service Rates into Effect on an Interim Basis
September 19, 1995.
These power rates were developed pursuant to section 302(a) of the
Department of Energy (DOE) Organization Act, 42 U.S.C. 7152(a), through
which the power marketing functions of the Secretary of the Interior
and the Bureau of Reclamation under the Reclamation Act of 1902, 43
U.S.C. 371 et seq., as amended and supplemented by subsequent
enactments, particularly section 9(c) of the Reclamation Project Act of
1939, 43 U.S.C. 485h(c), and other acts specifically applicable to the
project involved were transferred to and vested in the Secretary of
Energy (Secretary).
By Amendment No. 3 to Delegation Order No. 0204-108, published
November 10, 1993 (58 FR 59716), the Secretary delegated (1) the
authority to develop long-term power and transmission rates on a
nonexclusive basis to the Administrator of the Western Area Power
Administration; (2) the authority to confirm, approve, and place such
rates into effect on an interim basis to the Deputy Secretary; and (3)
the authority to confirm, approve, and place into effect on a final
basis, to remand, or to disapprove such rates to the Federal Energy
Regulatory Commission. Existing DOE procedures for public participation
in power rate adjustments are located at 10 CFR Part 903.
Acronyms and Definitions
As used in this rate order, the following acronyms and definitions
apply:
Composite rate:
Energy rate that recovers capacity and energy revenue requirements.
Contract 2948A:
Pacific Gas and Electric Company's contract with Western for the
sale, interchange and transmission of power; Contract No. 14-06-200-
2948A, as amended.
Corps:
United States Army Corps of Engineers.
CRD:
Contract rate of delivery. The maximum amount of capacity that
Western is contractually obligated to provide to a customer.
CVP:
Central Valley Project.
DOE:
Department of Energy.
DOE Order RA6120.2:
An order dealing with power marketing administration financial
reporting.
Energy base rate:
Energy rate applied to energy sales below a 70 percent monthly load
factor.
Energy component:
The component of this rate which sets forth the charges for energy.
It is expressed in mills/kWh and applied to each kWh made available to
each customer.
Energy tier rate:
Energy rate applied to energy sales at a 70 percent and higher
monthly
[[Page 52673]]
load factor.
FERC:
Federal Energy Regulatory Commission.
FY:
Fiscal year.
Intertie:
Pacific Northwest-Pacific Southwest Intertie.
kW:
Kilowatt (1000 watts).
kW/month:
Kilowatt per month.
kWh:
Kilowatthour.
Load factor:
The ratio of total energy delivered compared to the maximum energy
available during a specified period of time.
mills/kWh:
Mills per kilowatthour.
MW:
Megawatt (1000 kW).
NEPA:
National Energy Policy Act of 1969 (42 U.S.C. 4321 et seq.).
Northwest:
Northwest United States.
O&M:
Operation and maintenance.
PG&E:
Pacific Gas and Electric Company.
Power factor:
The ratio of real (kW) to apparent power (kVA) at any given point
and time in an electrical circuit. Generally it is expressed as a
percentage ratio.
PRS:
Power repayment study.
Provisional rates:
A rate which has been confirmed, approved, and placed in effect on
an interim basis by the Deputy Secretary.
RAC:
Revenue adjustment clause.
Rate brochure:
A document prepared for public distribution explaining the
rationale and background of the rate proposal contained in this rate
order dated July 1995.
Reclamation:
U.S. Department of the Interior, Bureau of Reclamation.
Revenue requirement:
The revenues required to recover O&M expenses, purchase power and
transmission service expenses, interest, deferred expenses, and Federal
investments.
Secretary:
Secretary of Energy.
Western:
U.S. Department of Energy, Western Area Power Administration.
Effective Date
The new rates will become effective on an interim basis on the
first day of the first full billing period beginning on or after
October 1, 1995, and will be in effect pending FERC's approval of them
or substitute rates on a final basis for a 2\1/2\-year period ending
April 30, 1998, or until superseded.
Public Notice and Comment
The Procedures for Public Participation in Power and Transmission
Rate Adjustments and Extensions, 10 CFR Part 903, have been followed by
Western in the development of these commercial firm power rates. The
following summarizes the steps Western took to ensure involvement of
interested parties in the rate process:
1. The proposed rate adjustment was initiated on June 9, 1995, when
a letter announcing an informal customer meeting was mailed to all
commercial firm power customers and interested parties. The meeting was
held on June 26, 1995, in Sacramento, California. At this informal
meeting, Western explained the rationale for the rate decrease and rate
design methodology, and answered questions.
2. A Federal Register notice was published on July 10, 1995 (60 FR
35556), officially announcing the commercial firm power rate
adjustment, initiating the public consultation and comment period,
announcing the public information and public comment forums, and
presenting procedures for public participation.
3. On July 17, 1995, letters were mailed from Western's Sacramento
Area Office to all commercial firm power customers and interested
parties transmitting the Federal Register notice of July 10, 1995.
4. On July 19, 1995, a rate brochure was mailed to all customers
and interested parties.
5. At the public information forum held on the morning of July 26,
1995, Western explained the rationale for the rate decrease and the
rate design methodology in greater detail and answered questions.
6. The comment forum was held on the afternoon of July 26, 1995, to
give the public an opportunity to comment for the record. Two customer
representatives made oral comments.
7. Eight comment letters were received during the consultation and
comment period. The consultation and comment period ended August 11,
1995. All formally submitted comments have been considered in the
preparation of this rate order.
Project History
The CVP in the Central Valley Basin of California has twelve dams
that create reservoirs with a total capacity of 10.66 million acre-feet
of water. The CVP contains 615 miles of canals, five pumping plants,
and eleven powerplants.
The Emergency Relief Appropriations Act of 1935 initially
authorized the CVP to be constructed by Reclamation. In 1944, Congress
authorized the American River Division to be constructed by the Corps.
In 1949, the Division was reauthorized for integration into the CVP.
The Trinity River Division was authorized by Congress in 1955. The San
Luis Unit was authorized by Congress in 1960. In 1965, Congress
authorized construction of the Auburn-Folsom South Unit as an addition
to the CVP. Congress authorized the San Felipe Division in 1967, and
the Allen Camp Unit in 1976. In 1964, Congress authorized the Intertie,
of which the CVP has the right to use 400 MW of transmission capacity
to import power from the Pacific Northwest.
PG&E and Western operate under Contract 2948A, executed in 1967,
which provides for the sale, interchange, and transmission of capacity
and energy between Western and PG&E. Contract 2948A also includes
provisions for the integration of power generated from the CVP
facilities with the 400 MW of entitlement on the Intertie. The contract
also provides that PG&E will support a maximum simultaneous demand of
1,152 MW for the CVP preference customers through calendar year 2004.
If the CVP power facilities cannot meet obligations to the preference
customers, Contract 2948A provides Western the right to purchase
capacity and energy from PG&E to meet those requirements. Any energy in
excess of Western's obligations to preference customers can be sold to
PG&E through a banking provision in the contract. The energy made
available under this banking arrangement allows Western to supplement
CVP generation to meet preference customer load.
Power generated from the CVP system is first dedicated to meeting
the project pumping facilities' power requirements. The remaining power
generated at the power facilities is allocated to various preference
customers in California.
Each preference customer's CRD is composed of firm long-term power
allocations, and may include short-term withdrawable allocations that
are currently allocated, but unused by another customer. For this rate
adjustment it is assumed that all customer withdrawable CRDs can be
withdrawn in the event the load level of 1,152 MW is exceeded.
Western's preference customer load level is limited under Contract
2948A to
[[Page 52674]]
a maximum simultaneous demand, excluding project loads, of 1,152 MW.
The maximum simultaneous demand is the sum of each preference
customer's demand for CVP power at a coincidental moment, adjusted to
the load center at the Tracy Switchyard. Notwithstanding the
simultaneous demand limit, Western has contractual obligations to serve
approximately 1,478 MW of firm CRD to its preference customers. This
level of CRD can be served because of the diversity in customers' loads
and load management arrangements Western has with certain customers.
Power Repayment Study
PRSs are prepared each fiscal year to determine if power revenues
will be sufficient to pay, within the prescribed time periods, all
costs assigned to the power function. Repayment criteria are based on
law, policies, and authorizing legislation. DOE Order RA6120.2, section
12b, requires that:
In addition to the recovery of the above costs (operation and
maintenance and interest expenses) on a year-by-year basis, the
expected revenues are at least sufficient to recover (1) each dollar of
power investment at Federal hydroelectric generating plants within 50
years after they become revenue producing, except as otherwise provided
by law; plus, (2) each annual increment of Federal transmission
investment within the average service life of such transmission
facilities or within a maximum of 50 years, whichever is less; plus,
(3) the cost of each replacement of a unit of property of a Federal
power system within its expected service life up to a maximum of 50
years; plus, (4) each dollar of assisted irrigation investment within
the period established for the irrigation water users to repay their
share of construction costs.
Existing and Provisional Rates
A comparison of the existing and provisional rates follows:
Comparison of Existing and Provisional Rates
[Commercial Firm Power Rate Schedule]
----------------------------------------------------------------------------------------------------------------
Effective period Existing Provisional Percent change
----------------------------------------------------------------------------------------------------------------
Composite Rate (mills/kWh)
10/01/95 to 09/30/96..................................... 31.55 23.35 (26)
10/01/96 to 09/30/97..................................... 31.55 25.00 (21)
10/01/97 to 04/30/98..................................... 34.37 26.50 (23)
Capacity Rate ($/kW/month):
10/01/95 to 09/30/96..................................... 6.57 4.03 (39)
10/01/96 to 09/30/97..................................... 6.57 4.32 (34)
10/01/97 to 04/30/98..................................... 7.16 4.58 (36)
Energy Base Rate (mills/kWh):
10/01/95 to 09/30/96..................................... 17.73 14.83 (16)
10/01/96 to 09/30/97..................................... 17.73 15.93 (10)
10/01/97 to 04/30/98..................................... 19.33 16.93 (12)
Energy Tier Rate (mills/kWh):
10/01/95 to 09/30/96..................................... 34.70 25.90 (25)
10/01/96 to 09/30/97..................................... 34.70 26.27 (24)
10/01/97 to 04/30/98..................................... 37.46 26.48 (29)
----------------------------------------------------------------------------------------------------------------
Certification of Rate
Western's Administrator has certified that the CVP commercial firm
power rates placed into effect on an interim basis herein are the
lowest possible rates consistent with sound business principles. The
rates have been developed in accordance with administrative policies
and applicable laws.
Discussion
The CVP provisional rates for commercial firm power change the CVP
rate design and lower the rates currently in effect under Amended Rate
Schedule CV-F7.
The CVP provisional composite rates reflect a 21 percent to 26
percent decrease from the current composite rates established in
Amended Rate Schedule CV-F7. The recent decrease in customer CVP power
purchases and the corresponding decrease in purchase power expenses are
the major factors in the reduced rates.
The existing rate design collects 40 percent of the revenue
requirement from capacity sales and 60 percent from energy sales.
Effective October 1, 1995, the rate design will change to collect 35
percent of the revenue requirement from capacity sales and 65 percent
from energy sales, to reflect the greater portion of Western's costs
associated with energy. A reduction in capacity purchase costs also
result from Western's Sacramento Area Office entering into an
arrangement with PG&E that will reduce the cost of capacity supplied by
PG&E, from the current rate of approximately $17.00/kW/month to $5.875/
kW/month beginning in June 1996.
The capacity rate percentage decreases are larger than the energy
base rate decreases for two reasons: (1) The change in rate design from
a 40 percent capacity/60 percent energy split to a 35 percent capacity/
65 percent energy split, and (2) the forecasted energy tier sales were
reduced disproportionately to the overall reduced forecast of customer
energy sales. Therefore, the energy tier revenues are smaller, leaving
more revenue to be recovered through the energy base rate.
The energy tier rate is based on the average CVP Northwest energy
rate in both the existing and the provisional rates. The energy tier
rate decreases between 24 percent to 29 percent from the existing rates
in Amended Rate Schedule CV-F7. The decrease is due to the reduction in
current market prices for energy from the Northwest from the level
projected in the PRS supporting the current CVP commercial firm power
rates.
The provisional composite rates increase approximately 7 percent in
FY 1997 and 6 percent in FY 1998 as a result of increases in purchase
power rates from Northwest suppliers and a 3 percent escalation factor
in Western's O&M expenses.
The existing and proposed revenue requirements for the Central
Valley Project are as follows:
[[Page 52675]]
------------------------------------------------------------------------
Estimated 1996 revenue
-----------------------------------
Existing Proposed
------------------------------------------------------------------------
Revenue requirements:............... $247,898,000 $193,618,000
------------------------------------------------------------------------
The provisional rates provide sufficient revenues to satisfy the
cost recovery criteria set forth in DOE Order RA6120.2.
Statement of Revenue and Related Expenses
The following table provides a summary of revenue and expense data
through the 2\1/2\-year proposed rate approval period.
Central Valley Project--Comparison of Cost Evaluation Rate Period
Revenues and Expenses
[$1,000]
------------------------------------------------------------------------
Provisional
ratesetting Current rate Difference
PRS 1996-98 PRS 1996-98
------------------------------------------------------------------------
Revenue Distribution:
O&M................. 105,521 113,066 (7,545)
Purchase Power...... 407,804 704,129 (296,325)
Transmission........ 45,098 46,191 (1,093)
Interest............ 29,933 26,902 3,031
Investment Repayment 21,598 25,077 (3,479)
Total Revenues.... 609,954 915,365 (305,411)
------------------------------------------------------------------------
Basis for Rate Development
The CVP rate adjustment is needed to reflect reduced purchase power
expenses that have occurred due to a decrease in customers' CVP power
purchases. A major contributing factor in the rate decrease is reduced
purchase power costs from PG&E. A rate decrease of 21 percent to 26
percent from the existing rate schedule occurs during the FY 1996 to FY
1998 period.
The provisional rates consist of a capacity rate, energy base rate,
and energy tier rate. The energy tier rate will be applied in the same
manner as it is in the current rate schedule, to any energy purchased
at a 70 percent and higher monthly load factor. The energy tier rate is
based on the average CVP Northwest energy rate.
The revenue recovery split between capacity and energy has changed
from that in the existing rate schedule. Currently, the split is 40
percent capacity/60 percent energy. Under the provisional rates the
split is 35 percent capacity/65 percent energy. This change reflects a
greater portion of Western's costs associated with energy, and a
decrease in capacity purchase costs.
The RAC, the Power Factor Adjustment Clause, the Low Voltage Loss
Adjustment, and other provisions which are part of the commercial firm
power rate schedule are not being modified at this time, and will
remain as specified in the Amended Rate Schedule CV-F7.
Comments
During the public comment period, Western received eight written
comments on the rate adjustment. In addition, two customer
representatives commented during the July 26, 1995 public comment
forum. All comments were reviewed and considered in the preparation of
this rate order.
Written comments were received from the following sources:
Broadview Water District (California)
Calaveras Public Power Agency (California)
National Aeronautics and Space Administration--Ames Research Center
(California)
Northern California Power Agency (California)
City of Palo Alto (California)
City of Santa Clara (California)
Trinity Public Utilities District (California)
Tuolumne Public Power Agency (California)
Representatives of the following organizations made oral comments:
City of Palo Alto (California)
Sacramento Municipal Utility District (California)
The comments received at the public meetings and in correspondence
dealt with the commercial firm power rate design, specifically, the
capacity/energy split for revenue recovery. All comments supported
Western's efforts to reduce the rates and have the provisional rates in
effect by October 1, 1995. Discussion of comments will address the
capacity/energy split, and Western will address several comments with
one response. The comments and responses, paraphrased for brevity, are
discussed below. Direct quotes from comment letters are used for
clarification where necessary.
Commercial Firm Power Rate Design (Capacity/Energy Split)
The following comments relate to the change in CVP rate design from
recovering 40 percent of the revenue requirement from capacity sales
and 60 percent from energy sales, to 35 percent from capacity and 65
percent from energy. Several comments supported the change in the
capacity/energy split.
Comments: One customer commented that they opposed the change from
a 40 percent capacity/60 percent energy split to a 30 percent capacity/
70 percent energy split due to an inappropriate allocation of costs to
energy, and for the reason that an unfair cost responsibility would be
placed on the high load factor customers. However, this same customer
sent a subsequent letter concurring with Western's proposal to change
the 40 percent capacity/60 percent energy split to the 35 percent
capacity/65 percent energy split used to develop the provisional rates.
Other customers argued against keeping the 40 percent capacity/60
percent energy split for the reason that the 40 percent capacity/60
percent energy split is inequitable to the low load factor customers,
and recommended that Western should change its capacity/energy ratio to
be more in line with rate structures of other utility operations
[[Page 52676]]
providing comparable services and serving the same area as Western.
Other comments received recommended Western consider changing the
capacity/energy split to at least a 30 percent capacity/70 percent
energy split.
Response: Western initially proposed to continue the existing 40
percent capacity/60 percent energy revenue requirement split. Western
then developed two studies analyzing the appropriate revenue
requirement split for capacity and energy. In the first study the
associated costs of each CVP resource were allocated to capacity or
energy. This study indicated that approximately 45 percent of the total
resource cost could be allocated to capacity and 55 percent allocated
to energy. An initial study analyzing a fixed/variable cost approach
indicated that approximately 30 percent of Western's costs could be
fixed and allocated to capacity and approximately 70 percent could be
variable and allocated to energy. Further refinement of this fixed/
variable cost study resulted in 35 percent allocated to capacity and 65
percent to energy. Based on these studies, the future reduction in the
capacity purchase rate from PG&E, current market conditions, and
comments from the CVP preference customers, Western concluded that a 35
percent allocation to capacity and 65 percent allocation to energy was
a reasonable split. By shifting a larger percentage of the costs from
capacity to energy, Western believes that the provisional rates will
more closely reflect the cost of providing capacity and energy to its
customers. The rate design reflects Western's cost of capacity and
energy to provide power to all CVP customers, not an individual
customer's consumption of capacity or energy. The impact on individual
customers will vary depending on that customer's usage of capacity or
energy from the CVP. It is Western's position that Western has an
obligation to meet all its contractual commitments and that the
capacity/energy revenue split coupled with the energy tier rate
recognizes Western's overall cost of power.
Environmental Evaluation
In compliance with the National Environmental Policy Act of 1969,
42 U.S.C. 4321 et seq.; Council on Environmental Quality Regulations
(40 CFR Parts 1500-1508); and DOE NEPA Regulations (10 CFR Part 1021),
Western has determined that this action is categorically excluded from
the preparation of an environmental assessment or an environmental
impact statement.
Executive Order 12866
DOE has determined that this is not a significant regulatory action
because it does not meet the criteria of Executive Order 12866, 58 FR
51735. Western has an exemption from centralized regulatory review
under Executive Order 12866; accordingly, no clearance of this notice
by the Office of Management and Budget is required.
Availability of Information
Information regarding this rate adjustment, including PRSs,
comments, letters, memorandums, and other supporting material made or
kept by Western for the purpose of developing the power rates, is
available for public review in the Sacramento Area Office, Western Area
Power Administration, Office of the Assistant Area Manager for Power
Marketing, 114 Parkshore Drive, Folsom, California 95630, and the Power
Marketing Liaison Office, Office of the Assistant Administrator for
Washington Liaison, Room 8G-027, Forrestal Building, 1000 Independence
Avenue SW., Washington, DC 20585.
Submission to the Federal Energy Regulatory Commission
The rate herein confirmed, approved, and placed into effect on an
interim basis, together with supporting documents, will be submitted to
FERC for confirmation and approval on a final basis.
Order
In view of the foregoing and pursuant to the authority delegated to
me by the Secretary of Energy, I confirm and approve on an interim
basis, effective October 1, 1995, Rate Schedule CV-F8 for the Central
Valley Project. The rate schedule shall remain in effect on an interim
basis, pending confirmation and approval on a final basis by the
Federal Energy Regulatory Commission, through April 30, 1998, or until
superseded.
Issued in Washington, D.C., September 19, 1995.
Charles B. Curtis,
Deputy Secretary.
Schedule of Rates for Commercial Firm Power Service
Effective: October 1, 1995.
Available: Within the marketing area served by the Sacramento Area
Office.
Applicable: To the commercial firm power customers for general
power service supplied through one meter, at one point of delivery,
unless otherwise provided by contract.
Character: Alternating current, 60 hertz, three-phase, delivered
and metered at the voltages and points established by contract.
Monthly Rates
------------------------------------------------------------------------
Period Capacity Energy
------------------------------------------------------------------------
10/01/95-09/30/96...... $4.03/kW/month......... Base: 14.83 mills/kWh.
Tier: 25.90 mills/kWh.
10/01/96-09/30/97...... 4.32/kW/month.......... Base: 15.93 mills/kWh.
Tier: 26.27 mills/kWh.
10/01/97-04/30/98...... 4.58/kW/month.......... Base: 16.93 mills/kWh.
Tier: 26.48 mills/kWh.
------------------------------------------------------------------------
Billing
Demand: The rates listed above for capacity shall be the charge per
kW of billing demand. The billing demand is the highest 30-minute
integrated demand measured or scheduled during the month up to, but not
in excess of, the delivery obligation under the power sales contract.
Energy: The rates listed above for energy shall be a charge per kWh
for all energy use up to, but not in excess of, the maximum kWh
obligation of the United States during the month as established under
the power sales contract.
The energy base rate shall be applied to all energy sales below a
70 percent monthly load factor. The energy tier rate shall be applied
to all energy sales at a 70 percent and higher monthly load factor. The
monthly load factor shall be calculated based on the lesser of the
customer's (1) maximum demand for the month or, if a scheduled
customer, the maximum scheduled demand for the month; or (2) the CRD.
Only power offered under this Rate Schedule CV-F8 will be used in the
calculation of the load factor.
Adjustments
Billing for Unauthorized Overruns
For each billing period in which there is a contract violation
involving an unauthorized overrun of the contractual obligation for
capacity and/or energy, such overrun shall be billed at 10 times the
applicable rates above. The energy base rate will be used as the
overrun rate for energy.
For Revenue Adjustment
The following methodology shall be used for the revenue adjustment
clause (RAC) calculation:
1. If the actual net revenue is greater than the projected net
revenue for the RAC calculation period, a revenue credit will be
allocated during the RAC
[[Page 52677]]
adjustment period. The credit will equal the difference between the
actual net revenue and projected net revenue, represented by the
following formula:
ANR > PNR ; C = ANR - PNR
Where:
ANR = Actual Net Revenue
PNR = Projected Net Revenue
C = Credit
2. If actual net revenue is less than the projected net revenue for
the RAC calculation period, a revenue surcharge will be allocated
during the RAC adjustment period.
2.1 If the actual net revenue is negative, the surcharge will be
equal to the minimum investment payment plus the annual deficit,
represented by the following formula:
ANR 0 ; S = MIP - ANR (if ANR > MIP, S = 0)
Where:
ANR = Actual Net Revenue
PNR = Projected Net Revenue
MIP = Minimum Investment Payment
S = Surcharge
Provided, that if the actual net revenue is greater than the minimum
investment payment, the surcharge will be equal to zero.
3. The maximum RAC credit allocation will equal $20 million plus
the amount of the Pacific Gas and Electric Company refund credit
applied to Western power bills for the fiscal year. The maximum
allocation for a RAC surcharge shall not exceed $20 million.
4. The RAC credit or surcharge shall be allocated to each CVP
commercial firm power customer based on the proportion of the
customer's billed obligation to Western for CVP commercial firm
capacity and energy to the total billed obligation for all CVP
commercial firm power customers for CVP commercial firm capacity and
energy for the RAC calculation period.
5. For purposes of the RAC calculation, the following terms are
defined:
5.1 Actual Net Revenue--The Recorded Net Revenue.
5.2 Annual Deficit--The amount the recorded annual expenses,
including interest, exceeding recorded annual revenues.
5.3 Minimum Investment Payment--The lesser of 1 percent of the
recorded unpaid investment balance at the end of the prior FY that the
RAC is being calculated, or the projected net revenue.
5.4 Projected Net Revenue--The annual net revenue available for
investment repayment projected in the PRS for the rate case during the
FY that the RAC is being calculated (see Table 1).
5.5 RAC Adjustment Period--The period January 1 through September
30, following the RAC calculation period when credits or surcharges
will be applied to the power bills.
5.6 RAC Calculation Period--The last recorded FY (October 1
through September 30).
5.7 Recorded Net Revenue--The annual net revenue available for
repayment recorded in the PRS for the FY that the RAC is being
calculated.
6. Subject to modification by a superseding rate schedule, the
final RAC will be allocated to the customers during the period January
1, 1999, to September 30, 1999.
Table 1.--Projected net revenue Available for Investment Repayment for
Revenue Adjustment Clause
------------------------------------------------------------------------
Projected Net
Period Revenue `
------------------------------------------------------------------------
October 1, 1995-September 30, 1996.................... $11,783,544
October 1, 1996-September 30, 1997.................... 4,506,910
October 1, 1997-September 30, 1998.................... 5,307,779
------------------------------------------------------------------------
For Transformer Losses
If delivery is made at transmission voltage but metered on the low-
voltage side of the substation, the meter readings will be increased to
compensate for transformer losses as provided for in the contract.
For Power Factor:
The customer will be required to maintain a power factor at all
points of measurement between 95-percent lagging and 95-percent
leading. The low power factor charge (LPFC) will be calculated by
multiplying the customer's maximum monthly demand by the kVar/kW rate
for the customer's mean power factor as provided in the following Table
2:
Table 2.--kVar/kW Rate Table
------------------------------------------------------------------------
Power factor Rate
------------------------------------------------------------------------
0.94...................................................... $0.09
0.93...................................................... 0.17
0.92...................................................... 0.24
0.91...................................................... 0.32
0.90...................................................... 0.39
0.89...................................................... 0.46
0.88...................................................... 0.53
0.87...................................................... 0.60
0.86...................................................... 0.66
0.85...................................................... 0.73
0.84...................................................... 0.79
0.83...................................................... 0.86
0.82...................................................... 0.92
0.81...................................................... 0.99
0.80...................................................... 1.05
0.79...................................................... 1.12
0.78...................................................... 1.18
0.77...................................................... 1.25
0.76...................................................... 1.32
0.75 & below.............................................. 1.38
------------------------------------------------------------------------
A LPFC will be assessed when a customer's power factor is less than
95 percent.
(a) A charge of $2.50 per kVar will be assessed for every kVar
required to raise a customer's power factor to 95 percent. The
calculated power factor used to determine if a charge will be assessed
is the arithmetic mean of a customer's measured monthly average power
factor and their measured onpeak power factor, rounded to the nearest
whole percent with 0.5 percent or greater rounded to the next higher
percent.
(b) The mean power factor will be calculated at each customer's
point of delivery. If a customer has multiple points of delivery, the
power factor will be determined from totalized information from the
points of delivery.
(c) No credit will be given for customers operating between 95
percent and 100 percent.
(d) Customers that have a monthly peak demand less than or equal to
50 kW will not be subject to the LPFC.
(e) The Contracting Officer may waive the LPFC for good cause in
whole or in part.
[FR Doc. 95-25043 Filed 10-6-95; 8:45 am]
BILLING CODE 6450-01-P
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.