Tucson Electric Company, et al.; Electric Rate and Corporate Regulation Filings

Federal RegisterMay 12, 1995

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF ENERGY

[Docket No. EC95-11-000, et al.]

Tucson Electric Company, et al.; Electric Rate and Corporate

Regulation Filings

May 4, 1995.

Take notice that the following filings have been made with the

Commission:

1. Tucson Electric Power

[Docket No. EC95-11-000]

Take notice that on April 26, 1995 Tucson Electric Power Company

(TEP) submitted an application pursuant to Section 203 of the Federal

Power Act for authority to effect a ``disposition of facilities'' that

would be deemed to occur as a result of implementation of a proposed

holding company structure, all as more fully set forth in the

application, which is on file with the Commission and open for public

inspection.

The application states that implementation of the holding company

structure proposed would be accomplished through the creation of a

holding company of which TEP would be a subsidiary. It is stated that

the proposed holding company structure is intended to facilitate the

separation of TEP's traditional utility operations from its operations

in other segments of the electric energy business. Such operation will

provide the optimal structure for participation in the various segments

of the evolving and expanding electric energy business, and will avoid

cross-subsidization and the transfer of business risk from these other

segments of the business to traditional utility operations. The holding

company structure, it is said, will not affect jurisdictional

facilities, rates or services.

Comment date: May 19, 1995, in accordance with Standard Paragraph E

at the end of this notice.

2. Pennsylvania Power & Light Company

[Docket No. ER95-720-000]

Take notice that on April 26, 1995, Pennsylvania Power & Light

Company (``PP&L''), tendered for filing with the Federal Energy

Regulatory Commission supplemental material relating to the above

docket.

Comment date: May 18, 1995, in accordance with Standard Paragraph E

at the end of this notice.

3. Louis Dreyfus Electric Power Company

[Docket No. ER92-850-011]

Take notice that on April 27, 1995, Louis Dreyfus Electric Power

Company tendered for filing a summary of its activity for the quarter

ending March 31, 1995.

4. Consolidated Edison Company Of New York, Inc.

[Docket No. ER93-568-000]

Take notice that on April 27, 1995, Consolidated Edison Company of

New York, Inc. (``Con Edison'') tendered for filing additional

information concerning two agreements for the interconnection and

delivery of energy between the JFK Cogeneration Project and the JFK

International Airport.

Con Edison states that a copy of this filing has been served by

mail upon KIAC Partners and the Port Authority of the New York and New

Jersey.

Comment date: May 18, 1995, in accordance with Standard Paragraph E

at the end of this notice.

5. CRSS Power Marketing, Inc.

[Docket No. ER94-142-005]

Take notice on April 24, 1995, CRSS Power Marketing, Inc. tendered

for filing its quarterly informational filing reporting no activity for

the quarter ending March 31, 1995.

6. EDC Power Marketing, Inc.

[Docket No. ER94-1538-002]

Take notice on April 24, 1995, EDC Power Marketing, Inc. tendered

for filing its quarterly informational filing reporting no activity for

the quarter ending March 31, 1995.

7. Equitable Power Services Company

[Docket No. ER94-1539-003]

Take notice that on April 27, 1995, Equitable Power Services

Company tendered for filing its quarterly report ending March 31, 1995,

reporting no activity during this quarter.

8. Citizens Lehman Power Sales

[Docket No. ER94-1685-002]

Take notice that on April 27, 1995, Citizens Lehman Power Sales

tendered for filing its quarterly report ending March 31, 1995

reporting no activity during this quarter.

9. Koch Power Services, Inc.

[Docket No. ER95-218-001]

Take notice that on April 26, 1995, Koch Power Services, Inc. filed

certain information as required by the Commission's January 4, 1995

letter Order in Docket No. ER95-218-000. Copies of Koch Power Services,

Inc.'s information filing are on file with the Commission and are

available for public inspection.

10. Tenneco Energy Marketing Company

[Docket No. ER95-428-001]

Take notice that on April 27, 1995, Tenneco Energy Marketing

Company tendered for filing its quarterly report for the period ending

March 31, 1995, reporting no activity during this quarter.

11. New England Power Company

[Docket No. ER95-554-000]

Take notice that on April 26, 1995, New England Power Company

tendered for filing an amendment in the above-referenced docket.

Comment date: May 18, 1995, in accordance with Standard Paragraph E

at the end of this notice.

12. Washington Water Power Company

[Docket No. ER95-677-000]

Take notice that on April 19, 1995, Washington Water Power Company

tendered for filing an amendment in the above-referenced docket.

Comment date: May 18, 1995, in accordance with Standard Paragraph E

at the end of this notice.

13. Northeast Utilities Service Company

[Docket No. ER95-946-000]

Take notice that Northeast Utilities Service Company (NUSCO) on

April 24, 1995, tendered for filing, a Service Agreement with Enron

Power Marketing, Inc. (Enron) under the NU System Companies' System

Power Sales/Exchange Tariff No. 6.

NUSCO states that a copy of this filing has been mailed to Enron.

NUSCO requests that the Service Agreement become effective on April

1, 1995.

Comment date: May 18, 1995, in accordance with Standard Paragraph E

at the end of this notice.

14. New England Power Company

[Docket No. ER95-950-000]

Take notice that on April 26, 1995, New England Power Company (NEP)

tendered for filing a Notice of Termination to the Service Agreement

between NEP and Commonwealth Electric Company under NEP's FERC Electric

Tariff, Original Volume No. 3.

Comment date: May 18, 1995, in accordance with Standard Paragraph E

at the end of this notice. [[Page 25708]]

15. Northeast Utilities Service Company

[Docket No. ER95-952-000]

Take notice that Northeast Utilities Service Company (NUSCO), on

April 26, 1995, tendered for filing, a Service Agreement and a

Certificate of Concurrence with Vermont Public Power Supply Authority

(VPPSA) under the NU System Companies' System Power Sales/Exchange

Tariff No. 6.

NUSCO states that a copy of this filing has been mailed to VPPSA.

NUSCO requests that the Service Agreement become effective on May

1, 1995.

Comment date: May 18, 1995, in accordance with Standard Paragraph E

at the end of this notice.

16. Maine Public Service Company

[Docket No. ER95-954-000]

Take notice that on April 26, 1995, Maine Public Service Company

(Maine Public), tendered for filing an agreement providing for short-

term interim transmission for Central Maine Power Company.

Comment date: May 18, 1995, in accordance with Standard Paragraph E

at the end of this notice.

17. Robert Mehrabian

[Docket No. ID-2878-000]

Take notice that on April 24, 1995, Robert Mehrabian (Applicant)

tendered for filing an application under Section 305(b) of the Federal

Power Act to hold the following positions:

Outside Director: Duquesne Light Company

Outside Director: Mellon Bank Corporation

Outside Director: Mellon Bank, N.A.

Comment date: May 19, 1995, in accordance with Standard Paragraph E

at the end of this notice.

18. Air Products Hycal Company, L.P.

[Docket No. QF95-260-000]

On April 25, 1995, Air Products Hycal Company, L.P., (Applicant),

of 7201 Hamilton Boulevard, Allentown, Pennsylvania 18195-1501,

submitted for filing an application for certification of a facility

pursuant to Section 292.207(b) of the Commission's Regulations. No

determination has been made that the submittal constitutes a complete

filing.

According to the Applicant, the bottoming-cycle cogeneration

facility will be located adjacent to Ultramar Inc.'s Wilmington

Refinery, in Wilmington, California, and will consist of a steam-

methane hydrogen reformer, heat recovery boilers, a double-extraction/

condensing steam turbine generator, and a substation. Heat captured

from the hydrogen production process will be used for power production.

The maximum net electric power production capacity will be 20.9 MW. The

facility is expected to begin commercial operation in January of 1996.

Comment date: June 12, 1995, in accordance with Standard Paragraph

E at the end of this notice.

19. Central Hudson Gas & Electric Corporation

[Docket No. ER95-945-000]

Take notice that Central Hudson Gas and Electric Corporation

(Central Hudson) on April 24, 1995, tendered for filing its development

of actual costs for 1994 related to substation service provided to

Consolidated Edison Company of New York, Inc. (Con Edison) in

accordance with the provisions of its Rate Schedule FERC No. 43.

Central Hudson indicates that the actual cost amounted to $253,028

for 1994 and will be the basis on which estimated charges for 1995 will

be billed.

Central Hudson requests waiver of the notice requirements to permit

charges to become effective January 1, 1995 as agreed by the parties.

Central Hudson states that a copy of its filing was served on Con

Edison and the State of New York Public Service Commission.

Comment date: May 18, 1995, in accordance with Standard Paragraph E

at the end of this notice.

Standard Paragraphs

E. Any person desiring to be heard or to protest said filing should

file a motion to intervene or protest with the Federal Energy

Regulatory Commission, 825 North Capitol Street, NE., Washington, DC

20426, in accordance with Rules 211 and 214 of the Commission's Rules

of Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such

motions or protests should be filed on or before the comment date.

Protests will be considered by the Commission in determining the

appropriate action to be taken, but will not serve to make protestants

parties to the proceeding. Any person wishing to become a party must

file a motion to intervene. Copies of this filing are on file with the

Commission and are available for public inspection.

Lois D. Cashell,

Secretary.

[FR Doc. 95-11710 Filed 5-11-95; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.