DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

18 CFR Part 385

[Docket No. RM91-12-000]

Administrative Dispute Resolution

November 10, 1994.

AGENCY: Federal Energy Regulatory Commission.

ACTION: Notice of Proposed Rulemaking.

-----------------------------------------------------------------------

SUMMARY: The Commission is proposing to amend its regulations to

implement the Administrative Dispute Resolution Act of 1990 (ADRA). In

issuing a Notice of Proposed Rulemaking the Commission proposes to

adopt a policy endorsing the use of alternative dispute resolution

methods in its proceedings under the provisions of the ADRA. Such

methods would be used in lieu of litigation to resolve disputes in

Commission proceedings.

DATES: Written comments must be received by the Commission by January

17, 1995.

ADDRESSES: Send comments to: Office of the Secretary, Federal Energy

Regulatory Commission, 825 North Capitol Street, NE., Washington, DC

20426. Comments should refer to Docket No. RM91-12-000.

FOR FURTHER INFORMATION CONTACT: David N. Cook, Deputy General Counsel,

Office of the General Counsel, Federal Energy Regulatory Commission,

825 North Capitol Street, NE., Washington, DC 20426, Telephone (202)

208-0955.

SUPPLEMENTARY INFORMATION: In addition to publishing the full text of

this document in the Federal Register, the Commission also provides all

interested persons an opportunity to inspect or copy the contents of

this document during normal business hours in room 3104, at 941 North

Capitol Street, NE., Washington, DC 20426.

The Commission Issuance Posting System, (CIPS), an electronic

bulletin board service, provides access to the texts of formal

documents issued by the Commission. CIPS is available at no charge to

the user and may be accessed using a personal computer with a modem by

dialing (202) 208-1397. To access CIPS, set your communications

software to use 300, 1200, or 2400 bps, full duplex, no parity, 8 data

bits and 1 stop bit. CIPS can also be accessed at 9600 bps by dialing

(202) 208-1871. The full text of this notice of proposed rulemaking

will be available on CIPS for 30 days from the date of issuance. The

complete text on diskette in WordPerfect format may also be purchased

from the Commission's copy contractor, La Dorn Systems Corporation,

also located in room 3104, 941 North Capitol Street, NE., Washington,

DC 20426.

Table Of Contents

I. INTRODUCTION

II. BACKGROUND

III. APPLICATION OF ALTERNATIVE DISPUTE RESOLUTION TO COMMISSION

PROCEEDINGS

A. The Range of Commission Administrative Proceedings

B. Current Commission Practice and Procedures for Resolving

Disputes by Alternative Means

IV. PROPOSED RULES

A. Initiating the Use of an ADR Method

B. Mechanism for Using ADR in a Commission Proceeding

1. Applicability

2. Definitions

3. Submission of a Proposal to Use ADR

a. The Filing

b. Contents of the Proposal to Use ADR

c. Determination by the Decisional Authority

d. Monitoring ADR Proceedings

e. Terminating an ADR Proceeding

4. Selection and Use of Neutrals

C. Arbitration

1. Applicability to Commission Proceedings

2. Authorization

3. Arbitrator

4. Rules of Conduct for Conducting Arbitration

5. Arbitration Awards

6. Vacating an Award

D. Confidentiality

E. Representation of Parties

V. SETTLEMENT RULES

A. Omnibus Settlements

B. Rule 602(g): Uncontested Offers of Settlement and Adequacy of

the Record

C. Rule 602(h): Contested Settlements

1. Severance of Parties or Issues

2. Rule 602(h)(2): Certification of Contested Settlements

a. Genuine Issue of Material Fact

b. Rule 602(h)(2)(iii): Three Conditions for Certification

if Genuine Issues of Material Fact Exist

D. Deadlines

VI. WRITTEN COMMENT PROCEDURE

VII. ADMINISTRATIVE FINDINGS

I. Introduction

The Federal Energy Regulatory Commission (Commission) is issuing a

notice of proposed rulemaking (NOPR) to implement the Alternative

Dispute Resolution Act of 1990 (ADRA).\1\ In the NOPR, the Commission

is adopting a policy endorsing the use of alternative dispute

resolution (ADR) methods in its proceedings under the provisions of the

ADRA.

---------------------------------------------------------------------------

\1\5 U.S.C. 571-83 (1988), as amended by Pub. L. 102-354, 106

Stat. 944 (Aug. 26, 1992).

---------------------------------------------------------------------------

To implement its policy in support of alternative dispute

resolution, the Commission proposes to amend Subparts E and F of Part

385 of its Rules of Practice and Procedure2 to add regulations

adopting provisions authorized in the ADRA and to establish procedures

for approving ADR in particular proceedings.

---------------------------------------------------------------------------

\2\18 CFR Part 385.

---------------------------------------------------------------------------

The Commission proposes to add new Rule 604, adopting guidelines on

applying ADR techniques and definitions from the ADRA and establishing

procedures for the submitting, reviewing, and monitoring proposals to

use ADR in specific proceedings. The Commission also proposes to add

Rule 605, incorporating the provisions of the ADRA regarding binding

arbitration proceedings, arbitral awards, and review of arbitration

results. Third, the Commission proposes to add Rule 606, to adopt the

provisions of the ADRA regarding confidentiality in ADR proceedings

established under proposed new Rules 604 and 605. The Commission also

proposes to amend Subparts E, F, and G of Part 385 of its Rules of

Practice and Procedure to modify existing regulations and to add new

regulations with respect to the submission and review of offers of

settlement.

II. Background

The ADRA amends Chapter 5 of Title 5, United States Code, by adding

a new subchapter to provide explicit statutory authorization allowing

federal agencies to use ADR techniques in lieu of litigation to resolve

a dispute in the agency's administrative programs when all the

participants to the dispute voluntarily agree to its use. ADR methods

include the use of a neutral, an individual who functions to aid the

participants in resolving the controversy. The ADRA provides that ADR

methods may include, but are not limited to, settlement negotiations,

conciliation, facilitation, mediation, factfinding, minitrials, and

arbitration, or any combination of these, as described below.3

\3\Drawn from Administrative Conference of the U.S., Sourcebook:

Federal Agency Use of Alternative Means of Dispute Resolution

(Office of the Chairman, 1987) (Sourcebook) at 44-45.

---------------------------------------------------------------------------

Conciliation is an informal process in which the third party

tries to bring the parties to agreement by lowering tensions,

improving communications, interpreting issues, providing technical

assistance, exploring potential solutions and bringing about a

negotiated settlement, either informally or, in a subsequent step,

through formal mediation. Conciliation is frequently used in

volatile conflicts and in disputes where the parties are unable,

unwilling or unprepared to come to the table to negotiate their

differences.

Facilitation is a collaborative process used to help a group of

individuals or parties with divergent views reach a goal or complete

a task to the mutual satisfaction of the participants. The

facilitator functions as a neutral process expert and avoids making

substantive contributions. The facilitator's task is to help bring

the parties to consensus on a number of complex issues.

Mediation is a structured process in which the mediator assists

the disputants to reach a negotiated settlement of their

differences. Mediation is usually a voluntary process that results

in a signed agreement which defines the future behavior of the

parties. The mediator uses a variety of skills and techniques to

help the parties reach a settlement but is not empowered to render a

decision.

Factfinding is a process used from time to time primarily in

public sector collective bargaining. The fact finder, drawing on

both information provided by the parties and additional research,

recommends a resolution of each outstanding issue. It is typically

nonbinding and paves the way for further negotiations and mediation.

The minitrial is a privately-developed method of helping to

bring about a negotiated settlement in lieu of corporate litigation.

A typical minitrial might entail a period of limited discovery after

which attorneys present their best case before managers with the

authority to settle and a neutral advisor who may be a retired judge

or other lawyer. The managers then enter settlement negotiations.

They may call on the neutral advisor if they wish to obtain an

opinion on how a court might decide the matter. The neutral may also

be called upon to mediate the dispute.

Arbitration is a relatively formal process in which parties

jointly select the decisionmaker to whom they turn over the

decisionmaking. The arbitrator, after hearing each side, issues a

decision following the procedures agreed to in advance.

The ADRA requires each agency to adopt a policy that addresses the

use of alternative means of dispute resolution and case management in

connection with the agency's administrative actions. The Commission

will fulfill this requirement with this rulemaking proceeding and

through revisions to its regulations with respect to the matters under

the Commission's substantive jurisdiction.4

---------------------------------------------------------------------------

\4\Under the Department of Energy Organization Act, Pub. L. No.

95-91, 91 Stat. 565 (Aug. 4, 1988), the Chair is responsible for the

administrative functions of the agency. With respect to those

matters, the Commission's ADR policy is being developed separately.

---------------------------------------------------------------------------

As required by the ADRA, the Commission, in preparing this NOPR,

has consulted with the Administrative Conference of the United States

(ACUS) and reviewed the ACUS guidance to agencies in developing their

ADR policies and in implementing those policies.5 ACUS reviewed a

draft of this NOPR. Its comments were strongly supportive and in

agreement with the overall approach of the Commission's proposed

implementation of the ADRA.

---------------------------------------------------------------------------

\5\Administrative Conference of the U.S., The Administrative

Dispute Resolution Act: Guidance for Agency Dispute Resolution

Specialists (Office of the Chairman, 1992).

---------------------------------------------------------------------------

The Congress further encouraged the use of ADR procedures in the

Energy Policy Act of 1992. Section 1802(e) of that Act directed the

Commission to establish appropriate ADR procedures, including required

negotiations and voluntary arbitration, early in oil pipeline

proceedings as a method preferable to adjudication in resolving

disputes related to rates. The Commission did so by issuing Order No.

561, Revisions to Oil Pipeline Regulations Pursuant to the Energy

Policy Act of 1992 on October 22, 1993.6 The revisions to Part

343, Chapter I, Title 18, Code of Federal Regulations will be effective

January 1, 1995. Additionally, Vice President Gore's National

Performance Review recommended that federal agencies expand their use

of ADR techniques.

---------------------------------------------------------------------------

\6\58 FR 58753 (Nov. 4, 1993), III FERC Stats. & Regs. Preambles

30,985; order on reh'g, Order No. 561-A, 59 FR 40243 (Aug. 8,

1994), III FERC Stats. & Regs. Preambles 31,000 (July 28, 1994).

---------------------------------------------------------------------------

On April 17, 1991, the Commission issued a Notice of Inquiry (NOI)

seeking comments on: (1) how best to implement the ADRA, (2) whether

changes in the Commission's regulations are necessary or appropriate to

facilitate the use of alternative means of dispute resolution, and (3)

whether changes in the Commission's regulations governing settlements

are necessary or appropriate.7

---------------------------------------------------------------------------

\7\Administrative Dispute Resolution Notice of Inquiry, 56 FR

18789 (Apr. 24, 1991), IV FERC Stats. & Regs. Notices 35,523

(1991).

---------------------------------------------------------------------------

The NOI highlighted the statutory amendments promulgated by the

ADRA. These include definitions, guidelines on when ADR techniques

should not be used, guidelines for the selection and use of neutrals,

provisions to protect the confidentiality of ADR proceedings, and

standards for the conduct of binding arbitration proceedings and the

issuance of arbitration awards. Under ADRA, the decision to use, or not

to use, ADR methods is left to the discretion of the agency and is not

subject to judicial review.

Eighteen comments were filed in response to the NOI on behalf of

several pipelines, electric utilities, interest groups, and the

industry. 8 In general, the commenters support the implementation

by the Commission of the ADRA and the use of ADR methods under the

guidelines set out in the ADRA. The commenters commend the Commission's

past use of settlement procedures and various ADR methods to resolve

disputes and expedite the conclusion of proceedings, but believe that

additional measures are needed to resolve contested issues and conclude

proceedings more expeditiously through settlement or other means.

---------------------------------------------------------------------------

\8\See Appendix.

---------------------------------------------------------------------------

The commenters are divided on whether regulations are needed to

implement the ADRA. Several commenters express concern about the misuse

of ADR methods. The commenters present several suggestions on the

potential uses for ADR methods to resolve disputes concerning a variety

of issues and proceedings.

In addition, the commenters support the Commission's policy in

favor of settlements and do not request changes in the overall

framework established by the settlement regulations. However, a number

of the commenters request a variety of specific changes with a view

toward prompter action on all settlements. Included are requests to

provide for the filing and review of omnibus settlements and to modify

the conditions that govern an ALJ's certification of a contested

settlement to the Commission, including the need for unanimity in a

motion to omit the initial decision.

III. Application of Alternative Dispute Resolution to Commission

Proceedings

The ADRA directs the Commission to consider the potential uses for

ADR methods in connection with: (1) Formal and informal adjudications,

(2) rulemakings, (3) enforcement actions, (4) issuing and revoking

licenses or permits, (5) contract administration, (6) litigation

brought by or against the agency, and (7) other agency actions.

It is the policy of the Commission to conclude its administrative

proceedings as fairly, effectively, efficiently, and expeditiously as

possible. To that end, the Commission has long had in place flexible

settlement regulations that encourage and promote the use of settlement

negotiations and other means to resolve disputes. The ADRA gives the

Commission the opportunity to further develop and refine its policies

to achieve less costly, less contentious, and more timely decisions in

its proceedings. Under the existing framework for the review and

determination of its proceedings, the Commission intends to foster the

effective and sound use of innovative ADR procedures pursuant to the

guidelines established in the ADRA.

The Commission now will encourage participants in its

administrative proceedings to consider the use of ADR procedures to

assist them in resolving any differences among them. ADR techniques are

informal procedures based on the informed consent of all the

participants. Flexibility is the mainstay of ADR. Thus, the Commission

will not attempt to identify in advance all of the ADR methods that may

be used in its proceedings.

Creativity is an essential element in designing the appropriate ADR

method for a particular dispute and for a particular set of parties.

The ADRA opens up possibilities for the expanded use of new and varied

ADR methods not typically used under the current settlement regulations

or otherwise during a proceeding, including roles for third-party

neutrals. The ADRA offers expanded opportunities for alternatives to

protracted litigation in appropriate circumstances where the use of ADR

yields more effective and efficient results.

The opportunities for using ADR can occur at any time during the

processing of any filing, whether the filing is subject to informal

adjudicatory procedures or to the formal hearing process. If a filing

is set for hearing, opportunities for ADR may arise during the initial

settlement process prior to direct testimony in rate cases or prior to

the 30-day post-notice period in gas certificate cases, as well as any

time during the presiding officer's management of the hearing process.

Numerous opportunities for ADR also exist in proceedings where formal

hearings are not used. These include hydropower cases under the revised

licensing process, various enforcement actions, or complaint cases,

among others.

Of course, parties are encouraged to pursue ADR methods on their

own to resolve potential disputes before an application or other filing

is submitted to the Commission. Parties to a transaction may wish to

include dispute resolution provisions for resolving future conflicts in

a contract or tariff that is filed with the Commission.

This notice will examine certain areas of administrative action

identified by the ADRA to determine the potential for using ADR

methods. These areas include formal and informal adjudications,

enforcement actions, the issuing and revoking of licenses or permits,

and other actions arising under the Commission's substantive statutes.

No particular formula has been developed as to how ADR methods should

be used, how they relate to the traditional processes, and what their

advantages and disadvantages are in particular settings. Thus, the

purpose of the examination is only to indicate the broad spectrum of

the possibilities for expanded ADR use in the Commission's proceedings

as well as the Commission's intention to consider any method for

participants to work towards resolving their differences, in

appropriate circumstances.\9\

---------------------------------------------------------------------------

\9\Williams Natural Gas Company suggests that the Commission

require every company that comes before the Commission seeking

affirmative relief to show that it has formally adopted a policy

supporting ADR. Clearly, a commitment by each party in a proceeding

in support of ADR would be helpful to promote the goals established

in the Commission's policy. Parties should attempt to work out their

differences in advance of a filing, as well as in the early stages

of a contested proceeding before the disputes result in lengthy

litigation. However, the Commission believes that imposing this

condition on parties is neither necessary nor appropriate at this

time.

---------------------------------------------------------------------------

A. The Range of Commission Administrative Proceedings

The Commission oversees key operating functions of the Nation's

natural gas, electric utility, hydroelectric power, and oil pipeline

transportation industries. To do so, the Commission administers

numerous statutes and regulations that establish procedures for the

filing of applications to authorize, among other things, certificates

for the construction and operation of natural gas facilities, rates and

service conditions for the transportation and sale for resale of

natural gas and electric energy in interstate commerce, rates and terms

and conditions of services for the transportation of petroleum, and

licenses for the construction and operation of hydroelectric power

projects. The regulations also provide for the Commission's review of

enforcement actions, complaints, accounting matters, and other actions

related to its certification or licensing and ratemaking functions.

Because of the complexity of the issues and the number of persons

with interests in the outcome of the issues, many filings are contested

and lead to highly litigated, complicated, and protracted proceedings.

The Commission in many cases sets the filings for adjudication under

the formal, trial-type hearing procedures set forth in Subpart E of

Part 385 of the Commission's Rules of Practice and Procedure. In

response to the NOI, the commenters identified certain significant

issues that are contested in many of the filings and earmark the

filings that could particularly benefit from innovative ADR methods.

For example, in determining whether an application for a

certificate to construct and operate natural gas facilities is

consistent with the public convenience and necessity, the Commission

must resolve such issues as the sources and adequacy of supply and

market for gas, safety and operational aspects, financing, and

environmental impacts. Environmental analysis is becoming increasingly

complex and time-consuming. As a result, the Commission has been

issuing phased orders that provide a preliminary determination on non-

environmental issues or on discrete portions of a project while

continuing the review process.\10\ A major factor in many of these

cases is the timely construction of a proposed project. The use of

innovative ADR methods may help to accelerate the conclusion of these

applications.

---------------------------------------------------------------------------

\10\E.g., Northwest Pipeline Corp., 56 FERC 61,006 (1991);

Great Lakes Transmission Limited Partnership, 56 FERC  61,051

(1991).

---------------------------------------------------------------------------

Applications to establish natural gas, electric, or oil rates and

terms of service are determined on the basis of whether the proposals

are just, reasonable, and not unduly discriminatory or preferential.

Issues that arise, such as the prudence of the purchasing practices of

the pipeline or electric utility, have in the past proved highly

litigious involving extensive discovery.

The traditional method for setting rates uses a cost-based process,

which can involve extensive analysis. However, the Commission has begun

to approve market-based rates in certain circumstances if the seller

lacks market power. Determining a seller's market power requires an

extremely detailed factual analysis of sophisticated and contentious

issues. As a result, some of the inquiries have led to complicated and

lengthy proceedings in oil rate filings,\11\ natural gas rate

proceedings,\12\ and electric rate cases.\13\ Electric utilities also

seek Commission authority for various corporate transactions, such as

mergers, which can require a hearing to consider issues concerning

costs, rates, and the competitive situation.\14\ Although many of these

filings are settled, innovative ADR methods should be useful in

clarifying the many complex issues and bringing the many parties

together to achieve settlement more quickly.\15\

---------------------------------------------------------------------------

\11\E.g., Williams Pipe Line Co., 68 FERC  61,136 (1994), reh'g

pending; Buckeye Pipe Line Co., L.P., 53 FERC  61,473 (1990); reh'g

granted in part and denied in part, 55 FERC  61,084 (1991).

\12\El Paso Natural Gas Co., 54 FERC 61,316 (1991), reh'g, 56

FERC 61,290 (1991); Transcontinental Gas Pipe Line Corp., 55 FERC

61,446 (1991), reh'g, 57 FERC  61,345 (1991).

\13\PSI Energy, Inc., Opinion No. 349, 49 FERC  61,346 (1989).

\14\Northeast Utilities Service Co., Opinion No. 364, 56 FERC 

61,269 (1991).

\15\Kansas Power & Light Co., 54 FERC  61,077 (1991).

---------------------------------------------------------------------------

ADR may be particularly useful in resolving an array of complex

transmission issues facing the electric utility industry in the

competitive era following the Energy Policy Act of 1992 (EPAct).

Recently, several utilities have volunteered to open their transmission

systems. Other utilities have been ordered to attempt to negotiate

transmission services under the newly amended Sections 211 and 212 of

the Federal Power Act. The Commission is also in the process of

analyzing new concepts for the pricing of transmission services. In

addition, there has been considerable activity across the country in

the development of regional transmission groups to provide vehicles for

the voluntary resolution of transmission access and pricing disputes.

ADR will be an important component of RTG agreements.\16\

---------------------------------------------------------------------------

\16\Policy Statement Regarding Regional Transmission Groups, 58

FR 41626 (Aug. 5, 1993), III FERC Stats. & Regs., Regulations

Preambles 30,976 (1993) (Policy Statement).

---------------------------------------------------------------------------

Whether transmission access and pricing are voluntary or pursuant

to a Section 211 Commission order, ADR could make an important

contribution by facilitating resolution of complex technical issues.

Prompt resolution of disputes over transmission services could often

mean the difference between success and failure of short-term

transactions under an open access transmission system.

Environmental issues and the balancing of various competing uses

for water resources are significant factors in the review of

applications to license or relicense a hydropower project.\17\ Under

recently revised application procedures, the Commission evaluates the

environmental and developmental impacts of a project by a process that

includes extensive pre-filing consultation, considers the

recommendations of various agencies and other concerned groups, and

balances all relevant public interest considerations.\18\ These issues

can be highly contentious and frequently involve numerous parties with

conflicting interests. In all of these cases, there may be a role for

ADR.

---------------------------------------------------------------------------

\17\Central Nebraska Public Power and Irrigation District,

Project No. 1417-017, 50 FERC 61,180 (1990), order on reh'g, 51

FERC  61,256 (1990).

\18\Hydroelectric Relicensing Regulations Under the Federal

Power Act, Order No. 513, 54 FR 23756 (June 2, 1989), FERC Stats. &

Regs. Preambles 1986-90  30,854 (May 17, 1989); Order No. 513-A,

FERC Stats. & Regs. Preambles 1986-90 30,869 (Dec. 26, 1989);

Regulations Governing Submittal of Proposed Hydropower License

Conditions and Other Matters, Order No. 533, 56 FR 23108 (May 20,

1991), III FERC Stats. & Regs. Preambles 30,921 (May 8, 1991);

Order No. 533-A, III FERC Stats. & Regs. Preambles  30,932 (Nov.

22, 1991).

---------------------------------------------------------------------------

B. Current Commission Practice and Procedures for Resolving Disputes by

Alternative Means

The Commission has for a long time relied on voluntary settlement

procedures to avoid litigation and for the orderly, expeditious conduct

of its business. Over the years, the Commission, the ALJs, and the

federal courts have agreed that voluntary settlements are important and

desirable methods of avoiding the delays and uncertainties of

litigation.19

---------------------------------------------------------------------------

\1\9Texas Gas Transmission Corp. v. FPC, 441 F.2d 1392, 1394

(6th Cir. 1971); Texas Eastern Transmission Corp. v. FPC, 306 F.2d

345, 347 n.2 (5th Cir. 1962).

---------------------------------------------------------------------------

In response to the NOI, the commenters commend in general the

Commission's settlement rules and procedures, which they state have

provided beneficial mechanisms for resolving contested issues.

According to the Federal Energy Bar Association (FEBA), the Commission

is far ahead of many other federal agencies in promoting the settlement

process. The commenters request that the Commission's existing

procedures not be undermined in implementing the ADRA and that the

Commission continue to promote the innovative settlement techniques

allowed under the current rules.

As the commenters point out, the current settlement rules provide a

simplified, flexible mechanism for initiating and approving a

settlement in any proceeding. Specifically, Rule 601 provides for the

convening of conferences by the Commission or the decisional authority,

upon motion of any participant or otherwise, in any proceeding for any

purpose, including consideration of offers of settlement, related to

the conduct or disposition of the proceeding. Rule 602 provides the

procedures for the submission of offers of settlement and for their

review by the ALJ or the Commission. The rules were adopted to

encourage participants in all proceedings to avoid the alternative of

costly and sometimes lengthy litigation before the Commission.20

---------------------------------------------------------------------------

\2\0Procedures for Submission of Settlement Agreements, Order

No. 32, 44 FR 34936 (June 18, 1979), FERC Stats. & Regs. Preambles

1977-81 30,061 (June 13, 1979); Order No. 32-A, 8 FERC 61,160

(1979).

---------------------------------------------------------------------------

In any proceeding set for hearing, Rule 603 allows the Commission,

the presiding ALJ, or a participant to request appointment of a neutral

settlement judge to preside over settlement negotiations.21 This

procedure was added to the settlement rules to reduce the inherent and

tactical delays in the settlement process and to provide structure and

control over the pace of negotiations.22 The Commission has found

that these rules are sufficiently broad to enable the Commission and

the ALJs to convene conferences and handle settlements

expeditiously.23

---------------------------------------------------------------------------

\2\1The Commission's settlement judge procedures are recommended

by the Administrative Conference of the United States as one of the

settlement techniques that the Administrative Conference urges

agencies to use routinely. Sourcebook at 116, n.3.

\2\2Rules of Practice and Procedure, Order No. 90, 45 FR 45902

(July 8, 1980), FERC Stats. & Regs. Preambles 1977-81 30,169 (June

23, 1980).

\2\3Revision of Rules of Practice and Procedures to Expedite

Trial-Type Hearings, Order No. 225, 47 FR 19014 (May 3, 1982), FERC

Stats. & Regs. Preambles 1982-85 30,358 (Apr. 26, 1982); Order No.

225-A, 47 FR 35952 (Aug. 18, 1982), FERC Stats. & Regs. Preambles

1982-85 30,385 (Aug. 12, 1982).

---------------------------------------------------------------------------

The Commission has taken an active role in promoting the settlement

rules and providing opportunities for the initiation of settlements at

the outset of all its proceedings. For example, the Commission adopted

top sheet procedures that provide for a settlement conference to be

convened during the pre-hearing stage of a rate case set for

hearing.24 Whether under these or other procedures, Commission

trial staff presents a settlement position which serves as a basis for

negotiations among the parties in an effort to reduce the need for

detailed testimony or formal hearing. Procedures were also adopted to

encourage settlement in each gas certificate application filed for

blanket authority and certain other authority.25 If a protest is

filed in response to the notice of the filing of such an application, a

30-day period is established for the parties and Commission staff to

establish informal settlement conferences to resolve the protest.

---------------------------------------------------------------------------

\2\4Initiated by Administrative Order No. 157, Apr. 1, 1976.

\2\518 CFR 157.205(g).

---------------------------------------------------------------------------

The Commission also directs the parties to consider settlements on

a case-by-case basis. In Order No. 528, the Commission encouraged

pipelines and their customers to reach settlements concerning any

proposed method for recovery of take-or-pay costs, and determined that

settlement conferences should be used to that end.26 Consequently,

the Commission has directed the convening of a settlement conference in

each proceeding in which the Commission accepts and suspends rate

filings pursuant to Order No. 528. This has resulted in the settlement

of many of these cases.27 In fiscal year 1993, the Commission

established 30 proceedings under Order Nos. 528 and 528-A to resolve

issues by settlement. By September 30, 1993, the Commission had

approved 19 settlements and more settlements were pending.28

---------------------------------------------------------------------------

\2\6Mechanisms for Passthrough of Pipeline Take-or-Pay Buyout

and Buydown Costs, 53 FERC 61,163 (1990); Order No. 528-A, 54 FERC

61,095 (1991); Order No. 528-B, 55 FERC 61,372 (1991).

\2\7E.g., Arkla Energy Resources, 54 FERC 61,011 (1991) and 58

FERC 61,359 (1992).

\2\8FERC 1993 Annual Report at 7.

---------------------------------------------------------------------------

Under the current settlement procedures, the Commission has been

able to settle a large number of contested proceedings. Approximately

70 to 80 percent of electric and gas rate cases settle without the need

to complete the litigation process. During fiscal year 1992, the

Commission issued 50 hearing orders involving 64 electric rate filings

and accepted 45 settlement agreements in electric rate cases. During

fiscal year 1993, the Commission issued 28 orders instituting hearing

or settlement judge procedures involving 31 electric rate filings and

accepted 29 offers of settlement resolving some or all of the issues

presented. An examination of the electric proceedings that settled

reveals that settlement generally is reached shortly after the

establishment of hearing procedures and the commencement of settlement

conferences.29

---------------------------------------------------------------------------

\2\9E.g., Indiana Michigan Power Co., 51 FERC 61,191 (1990);

reh'g, 56 FERC 61,019 (1991); Cincinnati Gas & Electric Co., 46

FERC 61,298 (1989) and 51 FERC 61,162 (1991).

---------------------------------------------------------------------------

A total of 41 new gas and oil pipeline filings were set for

hearings in fiscal year 1993. Also during fiscal year 1993, the

Commission approved 34 settlements of gas and oil pipeline rate cases.

For example, one settlement resolved issues in 33 different dockets,

many of which were at different stages of processing at hearing.30

Settlements also are frequently used to resolve disputes between the

Commission's Enforcement section and violators of pertinent statutory

or regulatory requirements in order to terminate enforcement

proceedings before full litigation.31

---------------------------------------------------------------------------

\3\0El Paso Natural Gas Co., 54 FERC 61,316 (1991), reh'g, 56

FERC 61,290 (1991).

\3\1The Washington Water Power Co., Project No. 2545, 56 FERC

61,048 (1991).

---------------------------------------------------------------------------

For the most part, the Commission's existing settlement procedures

fit into a category that might be called ``unassisted negotiation.''

What distinguishes the ADR techniques highlighted in the ADRA from

settlement negotiations under the Commission's existing rules is the

addition of a neutral, so that the process becomes one of ``assisted

negotiation.'' However, many commenters point out that, under the

Commission's current settlement rules, parties are able to avail

themselves of a wide variety of ADR techniques that involve the

informal use of a neutral. They urge the Commission to continue

supporting the flexible use of these procedures in developing

mechanisms to resolve disputes.

The Commission has incorporated the use of a wide variety of ADR

techniques in attempting to resolve disputes and bring its cases to

settlement. The settlement conference and settlement judge procedures

often involve techniques characteristic of those identified in the

ADRA. The convener of the conference or the settlement judge employs

such ADR techniques as conciliation, facilitation, mediation, and fact-

finding to bring the parties together to discuss their differences. The

settlement judge is expected to take an active role in the process as a

facilitator or mediator to keep the parties talking. In cases set for

hearing, trial staff plays an active and important role in facilitating

settlements at the prehearing conference (for example, through its top

sheets), other settlement conferences, or any time during the hearing.

The Commission and the ALJs have begun to encourage the use of more

structured ADR methods not typically used in the settlement procedures

but that specifically include the additional methods identified in the

ADRA. The Commission has recently made more use of the settlement judge

procedure in an effort to resolve a case without having to institute a

hearing or some other form of investigation.32 In July, 1994, the

Commission initiated a multi-party negotiation process in the New Don

Pedro proceeding, Project No. 2299. The negotiations are being led by

mediators from the Federal Mediation and Conciliation Service. The goal

of the mediators is to obtain a consensus on the issues surrounding the

in-stream flow from the New Don Pedro Dam. In another example, under

section 343.5 of the new oil pipeline regulations, which go into effect

in January 1995, all protested rate filings will be sent initially to a

settlement judge for possible resolution by negotiation. The

participants may also request the use of other ADR procedures to

resolve all or part of any pending matter.33 There is substantial

commonality between the ADR provisions for oil pipelines and the rules

proposed here. The Commission is interested in obtaining comment on

whether to integrate the oil pipeline provisions into these proposed

rules, so that the Commission would then have a single set of ADR

rules.

---------------------------------------------------------------------------

\3\2See Central Maine Power Co., 65 FERC  61,296 (1993);

Edwards Manufacturing Company, Inc., 63 FERC  61,199 (1993); UNITIL

Power Company v. Public Service Company of New Hampshire and

Northeast Utilities, 62 FERC  61,055 (1993).

\3\3Revisions to Oil Pipeline Regulations Pursuant to the Energy

Policy Act of 1992, 58 FR 58753, 58781 (Nov. 4, 1993).

---------------------------------------------------------------------------

In addition, the Commission has adopted shortened and simplified

procedures to resolve disputes on an informal basis in a wide range of

proceedings. These include the Enforcement Task Force Hotline to

resolve complaints before a filing is made and, under the accounting

rules, the option of an abbreviated process for resolving accounting

disputes.34 Under the revised regulations governing the filing and

review of hydropower licensing applications, the Commission has

incorporated mechanisms in the pre-filing consultation process that

permit the applicant or parties to refer disputes to the Director of

OHL for resolution.35 The Commission has made clear that it

intends to do everything possible to encourage all the participants to

work out their differences at any stage of the consultation

process.36 The Commission has also used settlement processes to

attempt to resolve hydropower environmental and water resource issues

after an application has been filed.37

---------------------------------------------------------------------------

\3\418 CFR 41.2, 158.2.

\3\5Order No. 513, FERC Stats. & Regs. Preambles, 1986-1990 

30,854, at 31,393-96, Rule 16.8(b)(5); Order No. 533, III FERC

Stats. & Regs. Preambles  30,921, at 30,125-27 (1991), Rule 4.38(b)

and (c).

\3\6Order No. 533, III FERC Stats. & Regs. Preambles  30,921,

at 30,126.

\3\7See, e.g., Edwards Manufacturing Company, Inc., 63 FERC 

61,199 (1993) (order directing appointment of settlement judge).

---------------------------------------------------------------------------

The Commission's settlement procedures have provided a framework of

sufficient flexibility to enable the Commission to pursue settlement

and the expeditious conclusion of proceedings before the full

litigation of the issues at formal hearing. The Commission does not

propose to undermine the existing settlement procedures, but instead

will continue to promote their use through specific regulations or on a

case-by-case basis.

The Commission expects the use of settlement and other procedures

to continue to reduce the conflicts in cases and promote conclusion of

cases without full litigation. The procedures currently used would not

be interrupted or affected by the policies proposed in this notice. The

ALJs and other Commission staff are expected to continue to take the

initiative not only in implementing traditional methods of establishing

settlements through negotiation or mediation, but also in considering

the newer methods, such as minitrials, reflected in recent cases. The

ADR rules proposed here would supplement the Commission's existing

rules and practices regarding settlement.

IV. Proposed Rules

The Commission believes that regulations are needed to provide

guidance to the parties in instituting an ADR procedure under the

provisions of the ADRA and to avoid confusion or uncertainty about the

integration of ADR methods into the Commission's overall decision-

making process. Therefore, the Commission is proposing regulations to

facilitate the use of ADR in Commission proceedings and to provide

guidance for such proceedings. The new ADR provisions are intended to

supplement existing Commission settlement regulations, and not to limit

or replace them in any way. The Commission expects that the new rules

will result in more effective, fair, timely, and less costly dispute

resolution.

Because the use of ADR complements current settlement practices,

the Commission proposes to include the proposed rules in Subpart F of

Part 385 of the Commission's Rules of Practice and Procedure concerning

settlements. Specifically, Rule 601(a) would be revised to provide for

the convening of conferences to evaluate whether ADR is practicable in

a particular proceeding. New Rule 604 is proposed to establish a

mechanism for filing proposals to use ADR, Rule 605 to adopt the

provisions in the ADRA for binding arbitration procedures, and Rule 606

to adopt the provisions in the ADRA for confidentiality in ADR

proceedings. The settlement rules are retained separately so that as

many options as possible would be available for expediting resolution

of disputes before the Commission.

Apart from the provisions in proposed Rule 605 for binding

arbitration proceedings, these proposed rules do not include separate

provisions for the Commission's review of the ultimate outcome of an

ADR proceeding. It is the Commission's intent that the ultimate outcome

of an ADR proceeding, like any other settlement, be subject to

Commission review in a manner that conforms with the Commission's

statutory duties using existing procedures for evaluating settlements.

As with the outcome of any settlement, the Commission's approval of the

outcome of the ADR method used in a particular proceeding would not

constitute approval of, or precedent regarding, any principle or issue

in that proceeding. To the extent ADR techniques are used to resolve

issues in licensing or certificate cases, that resolution would become

part of the Commission's evaluation of any license or certificate that

might be issued.

A. Initiating the Use of an ADR Method

The Commission seeks to encourage parties to consider the use of

ADR as a routine part of the Commission's decision-making processes.

Accordingly, the Commission proposes to amend Rule 601(a) by adding at

the end of Rule 601(a) the words ``or the use of alternative dispute

resolution procedures'' to specifically provide for a conference to

address the possibility of using ADR techniques. The Commission also

proposes to amend Rule 504(b)(7) to conform to the amendment proposed

in Rule 601(a).

By amending the rules to expressly identify ADR as a potential

topic for conferences convened by ALJs or any other decisional

authority, participants will be encouraged to request a conference for

the purpose of determining whether an ADR proceeding would be

appropriate for resolving the participants' differences. In addition,

the proposed amendments would comport with the ADRA, which amended

Section 556(c) of the Administrative Procedure Act (APA) to authorize

ALJs to consider the use of ADR methods when they are holding

conferences for settlement of the issues.

The Commission does not propose to require ADR or to impose a

deadline on parties to decide whether to use ADR. Thus, as under the

existing rule, a conference could be convened at any time during any

proceeding.

The ADRA also amended Section 556(c) of the APA to allow the

presiding officer to require the attendance at any such conference of

at least one representative of each party who has authority to

negotiate concerning resolution of issues in controversy. This

authority already is included in existing Rule 601(b)(2), which

requires that any person in a representative capacity at a conference

be authorized to act as a principal with respect to the matters to be

addressed.

In addition, the Commission's Rule 601(b)(3) provides that the

failure of any party to attend a conference convened under Rule 601(a)

constitutes waiver of all objections that party may have to any order

or ruling arising out of, or agreement reached at, the conference. That

condition would apply as well in the context of a conference at which

an agreement to use ADR was reached. Rule 601(b)(3) would operate to

waive an absent party's objections to an ADR proposal reached in the

conference if the conference was noticed in advance as a conference

addressing the possibility of using ADR.

The Commission does not believe that such provisions are

inconsistent with the voluntary nature of ADR. First, while a party may

be required to attend a conference that is convened for purposes of

discussing whether ADR would be appropriate, attendance does not

require a party to agree to the use of any dispute resolution proposal.

Second, because a proposal to use ADR must be supported by all

participants, it is not unreasonable to require the participants to

attend or consider non-attendance as consent to the process.

The Commission proposes an exception for proposals to use binding

arbitration under proposed new Rule 605. In those cases, it is proposed

in Rule 605(a)(5) to require the express consent of all interested

parties to such an agreement. Thus, a party's absence from a conference

under Rule 601 would not waive the party's rights to object to use

binding arbitration under Rule 605.

ADRA further amended Section 556(c) of the APA to require ALJs to

inform the parties as to the availability of ADR methods and to

encourage the use of such methods. The Commission expects all of its

staff, including its ALJs, to use the conference procedures, among

others, to facilitate the use of ADR in appropriate proceedings.

B. Mechanism for Using ADR in a Commission Proceeding

Rule 603 provides procedures for the parties or the Commission to

incorporate the use of settlement negotiations in Commission

proceedings. Rule 602 establishes procedures for the submission and

review of written offers of settlement. The Commission proposes to

provide in new Rule 604 similar procedures that participants can use to

incorporate in a proceeding the use of any ADR method, apart from

settlement negotiations which are covered in Rule 603. The mechanism

would consist of procedures for the filing and review of a proposal to

use a particular ADR method. Rule 604 proposes to adopt the standards

set out in the ADRA for the Commission to determine whether the use of

ADR in a proposal would be appropriate in that proceeding. Proposed

Rule 604 also adopts most of the definitions in the ADRA to facilitate

the use of ADR methods.

The written approval mechanism is intended to allow for the orderly

processing of the Commission's business. The Commission does not intend

the new written mechanism to replace the current practice of parties

using informal means to reach settlements. As a general rule, the

Commission allows parties flexibility in resolving their disputes.

1. Applicability

Proposed new Rule 604(a)(1) provides that participants may, subject

to the limitations of subparagraph (a)(2) of that section, use ADR to

resolve any issue in a pending matter, so long as all of the

participants agree to using the procedures.

The ADRA lists six factors for an agency to consider when

identifying cases in which the use of ADR would not be appropriate. The

Commission proposes to adopt these factors in subparagraph (a)(2) of

Rule 604 and to require that they be considered whenever a proposal to

use ADR is made. Thus, the new rule would provide that the appropriate

decisional authority will consider not using ADR if: (1) a definitive

resolution is required for precedential value; (2) the matter involves

significant questions of policy requiring additional procedures before

final resolution; (3) maintaining established policy is of special

importance; (4) the matter significantly affects persons or

organizations who are not parties to the proceeding; (5) a full public

record of the proceeding is important and the record cannot be provided

by dispute resolution; or (6) the Commission must maintain continuing

jurisdiction of the matter and dispute resolution would interfere with

the Commission's authority to alter the disposition of the matter if

circumstances change.

The use of alternative means of dispute resolution when any of

these factors is present is not absolutely prohibited under the

proposed rule. As proposed, Rule 604(a)(3) provides that ADR may be

used if the dispute resolution proceeding can be structured to avoid

the identified problem or if other concerns significantly outweigh one

or more of the factors.

Rule 604(a)(4) incorporates the ADRA's provision that the agency's

decision to use or not to use an ADR proceeding is not subject to

judicial review. Proposed Rule 604(a)(5) provides that settlement

agreements reached through the use of ADR will be subject to the

Commission's existing Rule 602, notice and comment procedures, unless

the decisional authority, upon motion or otherwise, orders a different

procedure.

2. Definitions

The Commission believes that certain of the definitions found in

the ADRA are helpful and proposes to incorporate these in Rule 604(b).

In the proposed rules, the Commission will use ``party'' and

``participant'' as defined in Rule 102.\38\ While staff is not included

in the definition of ``party,'' it is a ``participant.'' As discussed

below, the proposed rules provide for the full participation of parties

and staff in the ADR process to the same extent as in the settlement

process.

---------------------------------------------------------------------------

\38\18 CFR 385.102(b) and (c).

---------------------------------------------------------------------------

The definition of participant in Rule 102 does not expressly

identify the additional entities that are permitted to participate in

the application procedures in the Commission's rules for a license or

exemption to construct, operate, and maintain a hydroelectric project.

To ensure that all participants in such hydroelectric proceedings also

may participate in any matters concerning ADR under Subpart F of the

Commission's regulations, the Commission proposes to adopt a definition

of ``participant'' in Proposed Rule 604(b)(8) that includes these

entities, which may be state and federal agencies and Indian tribes

having statutory roles or a direct interest in the hydroelectric

proceedings, as participants in ADR proceedings.

3. Submission of a Proposal to Use ADR

The ADRA does not address the process for participants to follow in

implementing ADR. As indicated, the Commission believes that it would

be helpful to have in place a process for approving the use of certain

ADR methods in Commission proceedings. This would give the participants

a framework within which to use ADR. The proposal should be written to

avoid procedural disagreements during the ADR proceeding. A written

proposal also is needed by the decisional authority to determine the

appropriateness of using ADR in the proceeding and whether to suspend

action on a matter to give participants the opportunity to resolve

their disputes by means of an ADR process.

a. The Filing. Existing Rule 602 permits participants to file an

offer of settlement at any time during a proceeding. Because ADR is

meant to supplement existing settlement procedures, the Commission

proposes that the same opportunities be available for filing ADR

proposals. Consequently, Proposed Rule 604(e)(1) permits the

participants to submit a written proposal at any time during a

proceeding to use ADR to resolve all or part of any matter in

controversy or anticipated to be in controversy in the proceeding.

Except for the binding arbitration process identified in the ADRA

and incorporated in proposed Rule 605, the Commission does not propose

to identify the specific ADR methods available to the parties nor to

mandate specific procedures for each type of ADR, but leaves the

selection and procedures to the discretion of the participants. The

ADRA does not limit the ADR procedures available to the participants,

and the Commission does not propose to do so independently. The

proposed rules are intended to allow participants the flexibility to

create their own ADR procedures. ADR may be appropriate in particular

proceedings, but the Commission will not try to identify in advance the

various types of cases in which ADR would be appropriate. The

participants should feel free to propose any type of ADR in any

proceeding.

Proposed Rule 604(e)(2) provides that, if a proceeding is pending

before an ALJ, the proposal must be filed with the ALJ. Proposed Rule

604(e)(3) provides that, if a proposal involves binding arbitration, it

must be filed with the Secretary for consideration by the Commission.

For all other matters, proposed Rule 604(e)(4) provides that a proposal

to use ADR may be filed with the Secretary, who would transmit the

proposal to the appropriate decisional authority. If authority to act

on a matter has already been delegated to the staff, the staff member

would also consider a related ADR proposal. For matters not delegated

to the staff, the Commission would be the appropriate authority to

review an ADR proposal.

Proposed Rule 604(e)(6) allows the participants to modify the ADR

proposal once it has been approved and provides that requests to modify

must follow the same procedure as proposals for ADR.

b. Contents of the Proposal to Use ADR. Proposed Rule 604(f)

identifies the information that the proposal should contain. The

proposal should be written. It should be signed by all participants to

demonstrate that all participants support the use of ADR, or include

other evidence to indicate unanimous support.\39\

---------------------------------------------------------------------------

\39\This evidence could include attendance at a conference where

the proposal is adopted, or waiver of the right to consent by

documented failings to attend.

---------------------------------------------------------------------------

Under the ADRA, any use of ADR proceedings must be voluntary on the

part of the participants. The Commission is not willing to create

different levels of participants for purposes of determining whether

the participants support using an ADR proceeding. The Commission does

not propose to require less than the unanimous consent contemplated by

the ADRA. Nonetheless, the Commission requests further comment on

whether some limitation, based upon directness of interest or

otherwise, should be considered.

It should be restated, however, that under Rule 601(b)(3), any

party who fails to attend a conference convened for the purpose of

determining whether to use ADR waives any objection to decisions made

about an ADR proposal at that conference. Thus, the unanimous consent

is by those participants who choose to attend a conference convened for

the purpose of determining whether to use ADR. As indicated, there

would be an exception for binding arbitration proposals under proposed

Rule 605(a)(5), which proposes to require express consent of all

parties in such a proposal.

A proposal to use ADR should also include a general description of

the matters to be pursued so that the ALJ or other decisional authority

can assess the proposal under the criteria set forth in proposed Rules

604(a) (2) and (3). An ADR proposal could also provide a description of

the ADR process to be used. If the participants desire a neutral, the

proposal could indicate the neutral that is chosen by the participants,

or the mechanism by which a neutral would be chosen. (The neutral is

further discussed below.) Because the agreement will govern the

process, the participants should carefully consider and define issues

in advance. Points to be covered could include the option of having a

neutral, the neutral's role, issues to be considered, and procedural

matters such as the order and schedule of proceeding.

c. Determination by the Decisional Authority. Proposed Rule

604(e)(5) provides for the issuance of an order by the decisional

authority approving or denying a proposal filed under Rule 604 or Rule

605. The decisional authority would determine whether ADR would be

appropriate for a particular proceeding on a case-by-case basis, using

the guidelines set forth in proposed Rules 604(a) (2)and (3). If the

decisional authority approves a proposal to use ADR, an order to that

effect would be issued. If the proposal is disapproved, an order would

be issued setting forth the reasons. Further, a proposal to use ADR

would be deemed approved unless the decisional authority issues an

order denying approval within 30 days after the proposal is filed.

d. Monitoring ADR Proceedings. The Commission proposes to provide

for monitoring an ADR proceeding. Proposed Rule 604(f) allows the

decisional authority to require status reports on the proceeding at any

time. The Commission is concerned about the possibility of delay. This

provision is designed to prevent parties from using ADR as a stalling

tactic.

e. Terminating an ADR Proceeding. In proposed Rule 604(g), the

Commission would give the decisional authority, upon motion or

otherwise, the authority to terminate an ADR proceeding under Rule 604

or 605 if it appears that ADR is no longer appropriate. The decision to

terminate would be in the form of an order. Proposed Rule 604(g)(2)

provides that a decision to terminate an ADR proceeding is not subject

to judicial review because the decision is interlocutory in nature.

This is consistent with our existing settlement negotiation procedures

in Rules 603 (h) and (i). Parties may seek Commission review of such a

decision under Rule 715 in cases pending before an ALJ or, in all other

cases, under Rule 212 as a motion for reconsideration.

4. Selection and Use of Neutrals

The ADRA contains a full section concerning the selection and use

of neutrals in ADR proceedings. The Commission proposes to adopt the

definition of neutral in the ADRA and to incorporate most of the

provisions in the ADRA regarding neutrals.

Rule 604(c) proposes that a neutral may be a permanent or temporary

officer or employee of the Federal Government, (including an ALJ), or

any other individual who is acceptable to the participants in an ADR

proceeding. A neutral may not have any official, financial, or personal

conflict of interest with respect to the issues in controversy. While

the Commission proposes to adopt the proviso in the ADRA that such a

neutral may nevertheless serve if such interest is fully disclosed in

writing to all participants and if the participants agree that the

neutral may serve, the Commission proposes to exclude such a neutral

who is a Government employee. This qualification as to Government

employees is necessary because of the prohibition of conflicts of

interest found in other statutes for Federal employees.

Although the ADRA recognizes the right of the participants to

choose outsiders as neutrals, ALJs or other staff members may also be

neutrals in the ADR process. This provides an alternative for

participants who want to forgo the expense of using an outside neutral.

Another reason for using ALJs might be if participants require a

neutral familiar with the Commission's decisions, policies, and

programs.

ALJs are the most likely class of the Commission's staff to be

chosen as neutrals to decide disputes, but other staff members may be

chosen for their expertise as facilitators/mediators. However, if a

staff member served as a neutral in no event could that person

thereafter serve in any other capacity in the proceeding.\40\

---------------------------------------------------------------------------

\40\This is consistent with the Commission's current settlement

procedures. Under Rule 603, the settlement judge serves a single

function as a mediator or facilitator and cannot be a decisionmaker

or advisor in that proceeding.

---------------------------------------------------------------------------

The Commission also proposes in Rule 604(c)(3) to provide that

neutrals may be selected from rosters kept by the Federal Mediation and

Conciliation Service, ACUS, and the American Arbitration Association,

as well as any other source. Pursuant to proposed Rule 604(c)(2),

neutrals would be selected by the participants and would serve at the

will of the participants, unless the ADR agreement provides otherwise.

When it is the desire of the participants to select an ALJ to act as

the neutral, upon a request made to the Chief ALJ, that individual, if

available, would be designated as the neutral in the particular

proceeding. If the requested ALJ is not available, the participants

would be informed and they could select another ALJ if they desired.

C. Arbitration

The ADRA establishes procedures for binding arbitration

proceedings. Proposed Rule 605 incorporates the arbitration provisions

as they appear in the ADRA, with a few modifications as discussed

below. To the extent participants wish to use a different arbitration

procedure, they are free to propose one, rather than using the

procedure set forth in Rule 605.

1. Applicability to Commission Proceedings

The Commission recognizes that arbitration may not be appropriate

for many types of Commission proceedings given the number of parties

typically involved and the nature of the issues. However, arbitration

should be one of the dispute resolution tools that is available to

parties and trial staff when considering ADR.

2. Authorization

Proposed Rule 605(a) provides that the participants may at any time

submit a proposal to use the binding arbitration provisions of Rule 605

to resolve all or part of any matter in controversy before the

Commission. Proposed Rule 605(a)(2) would require that a proposal to

use binding arbitration follow the procedures outlined in Rule 604(d).

Proposed Rule 605(a)(3) would require that the proposal be submitted in

writing and contain the information listed in Rule 604(e). Under

proposed Rule 605(a)(4), the arbitration process could be monitored and

terminated just as other ADR methods under Rules 604 (f) and (g). To

ensure that arbitration is truly voluntary on all sides, proposed Rule

605(a)(5) provides that the Commission will not require any person to

consent to an arbitration proposal as a condition of receiving a

contract or benefit. Similarly, no company regulated by the Commission

may impose such a condition. Proposed Rule 605(a)(5) further proposes

to require that an arbitration proposal under Rule 605 have the express

written consent of all parties to the dispute.

3. Arbitrator

Under new Rule 605(b), participants in an arbitration proceeding

would be entitled to select the arbitrator. The particular procedure to

be used in selecting an arbitrator is not provided; however, the

arbitrator is required to meet the requirements of the neutral as

described in new Rule 604(d). Rule 605(c) sets forth the arbitrator's

duties, including conducting hearings, administering oaths, issuing

subpoenas to compel attendance of witnesses and production of evidence

at hearing. The arbitrator would be expressly authorized to make

awards, i.e., issue decisions.\41\ As the Senate Report explains:

\41\The power to issue awards does not include the authority to

issue licenses and certificates.

---------------------------------------------------------------------------

This section is intended to provide arbitrators with the

appropriate authority and flexibility to conduct arbitral

proceedings in an informal and efficient manner and to keep the

arbitral proceedings from becoming, in essence, full-blown

litigation proceedings. An arbitrator should not use the authority

granted in this section to indulge in or permit excessive discovery.

Instead, the arbitrator should make appropriate use of the authority

provided in this section to gather the necessary materials and

information to conduct a fair, effective and expeditious inquiry.

The section also limits arbitrators to the subpoena authority

granted by the Arbitration Act and to the agency sponsoring the

arbitral proceeding. This language is intended to ensure that the

same practices and body of law apply to all arbitrations of disputes

with federal agencies, whether initiated under the ADR subchapter in

Title 5 or the Arbitration Act in Title 9. It is also intended to

ensure that federal agencies do not gain, as a consequence of this

Act, any subpoena powers that they do not already possess.\42\

---------------------------------------------------------------------------

\42\S. Rep. No. 543, 101st Cong., 2d Sess. at 13 (1990).

---------------------------------------------------------------------------

4. Rules of Conduct for Conducting Arbitration

Proposed Rule 605(d) incorporates the provisions in Section 579 of

the ADRA that establish basic rules for the conduct of binding

arbitration proceedings, including hearings. Rule 605(d)(1) provides

that the arbitrator will set the time and place for the hearing and

notify the participants. Proposed Rules 605(d) (2) and (3) provide for

preparation of a record, if desired, and for presenting evidence. The

rule would require the hearing to be conducted expeditiously and

informally and would establish basic rights of the participants. Under

proposed Rule 605(d)(3)(iv), the arbitrator may exclude evidence that

is irrelevant, immaterial, unduly repetitious or privileged. According

to the Senate Report, this common arbitral standard ensures informal

and expeditious proceedings.\43\ Proposed Rule 605(d)(4) would prohibit

ex parte communications with the arbitrator, allowing the arbitrator to

impose sanctions for a violation of this prohibition. Proposed Rule

605(d)(5) would require the arbitrator to issue an award within 30 days

of the close of the hearing, unless the participants and arbitrator

agree to a different schedule.

---------------------------------------------------------------------------

\43\Id.

---------------------------------------------------------------------------

5. Arbitration Awards

The ADRA provides standards for issuing and appealing arbitral

awards. The Commission proposes to incorporate those standards in new

Rule 605(e). The award would be in writing and include a brief,

informal discussion of the factual and legal basis for the award. The

prevailing participants would file the award with the Commission and

any other relevant agencies and serve all participants. The award would

become final 30 days after it is served on all participants. However,

the Commission, upon motion or otherwise, could extend this period for

one additional 30-day period upon notice of the extension to all

participants.

Proposed Rule 605(e)(3) provides that a final award will be binding

on the participants.

6. Vacating an Award

As provided in the ADRA, the Commission proposes Rule 605(f) to

provide procedures for the Commission to vacate an award. Proposed Rule

605(f)(1) permits any person to request, within 10 days of the filing

of an award under Rule 605(e), that the Commission vacate the award and

requires that person to provide notice of the request to all

participants. Responses to such a request must be filed within 10 days

after the request is filed. Under proposed Rule 605(f)(2), the

Commission, upon request or otherwise, may vacate an arbitration award

before the award becomes final, and, to do so, must issue a written

order to that effect. The Commission's review of an arbitration award

would be based on the statutory standard that applies to the issues

resolved, and depends, therefore, on whether the issues involve rate,

certificate, or other matters in the Commission's jurisdiction. In

proposed Rule 605(e), the Commission would adopt the ADRA's provision

that the award need only discuss informally the factual and legal bases

for the award. If the participants wish to require that an award

include formal findings of fact and conclusions of law, they may do so

by adopting a different standard.

Proposed Rule 605(f)(4) adopts the ADRA's provision for monetary

relief. Thus, if the Commission vacates an arbitration award, a party

to the arbitration proceeding may petition the Commission for an award

of the attorney fees and expenses incurred in connection with the

arbitration proceeding. The Commission must award the petitioning party

those fees and expenses that would not have been incurred in the

absence of the arbitration proceeding, unless the Commission finds that

special circumstances make the award unjust.

As provided by the ADRA, proposed Rule 605(f)(6) establishes that a

decision by the Commission to vacate an arbitration award is not

subject to judicial review.

D. Confidentiality

The ADRA contains extensive confidentiality provisions.\44\ The

Commission proposes to establish new Rule 606 regarding confidentiality

in ADR proceedings. The confidentiality provisions set forth in Rule

606 would apply only to ADR proceedings established under proposed new

Rules 604 and 605, and are necessary for the neutral in dispute

resolution proceedings to remain effective. The participants should

feel free to be forthcoming and frank without fear that their

statements may later be used against them. As well, a neutral should be

protected from being required to divulge such information.

---------------------------------------------------------------------------

\44\5 U.S.C. 574.

---------------------------------------------------------------------------

The Commission's proposed Rule 606 incorporates most of the

confidentiality provisions for neutrals and participants that are found

in the ADRA. Under proposed Rule 606(a), confidentiality must be

maintained by a neutral unless: (1) All participants in the ADR

proceeding and the neutral consent in writing to the disclosure; (2)

the communication has already been made public; (3) the communication

is required by statute to be made public; or (4) a court determines,

after a balancing of considerations, that disclosure is necessary to

prevent a manifest injustice, to help establish a violation of law, or

to prevent harm to the public health or safety.

Under proposed Rule 606(b), a participant in the ADR proceeding

must not disclose information concerning any dispute resolution

communication unless, pursuant to five of the seven exceptions set out

in the ADRA: (1) All participants consent in writing; (2) the

communication has already been made public; (3) the communication is

required by statute to be made public; (4) a court determines, after

balancing considerations, that disclosure is necessary to prevent

manifest injustice, establish a violation of law, or prevent harm to

the public health or safety; or (5) the communication is relevant to

determining the existence or meaning or the enforcement of an agreement

or award resulting from the proceeding. The Commission does not propose

to include the remaining two exceptions, which permit a participant to

disclose a communication that was prepared by the party seeking

disclosure or that was available to all parties to the ADR proceeding,

because the exceptions could lead to the disclosure of material that

may need protection.

Under proposed Rule 606(c), any communication disclosed in

violation of this section would not be admissible in any proceeding

relating to the issues in controversy. Proposed Rule 606(d) provides

that the participants may agree to alternative confidentiality

procedures for disclosure by a neutral, but should inform the neutral

of any modifications prior to the commencement of the ADR procedure. If

the neutral is not so informed, the provisions of proposed Rule 606(a)

would apply. Under proposed Rule 606(e), the participants must be

notified of a demand for disclosure, whether by discovery or other

legal process. Proposed Rule 606 (f) through (i) adopt the remaining

provisions of the ADRA, including the provision that nothing in the

section would prevent discovery or admissibility of evidence that is

otherwise discoverable, merely because the evidence was presented in

the course of a dispute resolution proceeding.

E. Representation of Parties

The ADRA requires each agency to consider whether to allow non-

attorney representation in ADR proceedings, and, if non-attorneys are

allowed, to develop a policy on the disqualification of non-attorney

representatives when warranted.

The Commission has already incorporated such policies in its rules

and those existing rules would apply to ADR proceedings as well.

Existing Rule 2101 permits a participant to appear in a proceeding in

person or by an attorney or other qualified representative, and

existing Rule 2102 provides for suspension or disqualification

(temporary or permanent) of representatives when necessary.

V. Settlement Rules

The settlement procedures in Rules 601 through 603 generally work

well and, under the framework established by the rules, various ADR

methods are now used to great advantage to bring Commission proceedings

to more efficient and effective outcomes. Nevertheless, the NOI invited

comments on whether the settlement regulations in general should be

revised and, if so, in what manner. Specific comments were requested on

whether changes are necessary to accommodate the filing and processing

of omnibus settlements. Also, comments were requested on whether to

permit an ALJ to certify a contested settlement on less than unanimous

concurrence of the parties in a motion to omit an initial decision.

As discussed previously in this notice, the commenters responding

to the NOI uniformly support in general the current settlement

procedures as a successful method for resolving countless controversies

in numerous and varied proceedings. They support the use of the ADR

methods promoted by the ADRA as an additional tool to complement the

tools already available under the rules providing for settlement

conferences, settlement judge proceedings, and the submission and

review of settlements.

Although the commenters request that any changes that may be

proposed in this notice to existing rules or policy not in any way

diminish the effectiveness of the settlement process, they urge that

the Commission should consider a number of changes that would improve

and expedite that process. For the most part, they propose changes to

certain procedures in Rule 602 that govern the submission and review of

settlements and, specifically, to the certification process in subparts

(g) and (h) for the transmission from the ALJ to the Commission of

uncontested or contested settlements.

Based on the comments and a reexamination of the settlement rules,

the Commission proposes to adopt certain of the changes requested by

the commenters and not to adopt other requested changes, as more fully

discussed below. The Commission invites comments on its proposals and

any information that would be useful and appropriate in assisting in

the formulation of rules to improve the settlement process.

A. Omnibus Settlements

Rules 602 (a) and (b) now provide that any participant in a

proceeding may submit a written offer of settlement in any proceeding

pending before the Commission or set for hearing. The Secretary

transmits the offer either to the ALJ, if the offer is filed after a

proceeding is set for hearing and before the ALJ has certified the

record to the Commission, or to the Commission, as appropriate.

Omnibus settlements may cover multiple proceedings, as well as

multiple parties, involving pipelines, electric utilities, or other

regulated entities. These settlements have grown in importance in

recent years, in particular for pipelines, as parties attempt to

resolve the numerous issues that arise in the many proceedings

generated by the company's shift to a more competitive environment. The

many and diverse parties recognize that the resolution of an issue will

be affected by the resolution of other issues and, as a result, they

seek to settle the interrelated proceedings in a single settlement.

As the commenters acknowledge, parties to multiple proceedings that

wish to resolve overlapping issues through the filing of a single,

omnibus settlement are able to do so under the existing regulations.

Parties are free to include any number of proceedings and issues in an

offer of settlement submitted under Rules 602 (a) and (b). Settlement

discussions to develop omnibus settlements involving multiple

proceedings may be readily established by the Commission, the ALJs, or

upon motion by any participant under Rule 601 (which provides for

informal conferences) or under the more structured settlement judge

procedures of Rule 603. The discussions may involve multiple

proceedings pending before ALJs, the Commission, or both. Under the

rules, the Commission, the ALJs, or the participants in any underlying

proceeding may seek the appropriate procedural relief to facilitate

discussion, including stay of any of the proceedings during the course

of the discussion. The Commission believes that, as modified earlier in

this NOPR to include discussions for purposes of the use of ADR

techniques, these rules are sufficiently flexible to accommodate and

facilitate settlement discussions in any situation, including the

discussion of possible omnibus settlements involving proceedings before

the Commission and the ALJs.

However, the Commission agrees in part with the commenters that

amendments to the regulations would be useful and appropriate

specifically to provide participants the opportunity to consolidate

proceedings in settlements filed at the Commission. Rule 503(a)

provides the Chief ALJ with the authority, on motion or otherwise, to

order multiple proceedings pending before ALJs consolidated for

hearing. Under this authority, the Chief ALJ also has been able to

consolidate multiple proceedings if they are included in a settlement

and to assign the settlement to a single ALJ for the efficient and

effective treatment of the settlement.

The Commission proposes to codify current practice and amend Rule

503(a) by adding that the Chief ALJ may order multiple proceedings that

are pending before ALJs to be consolidated for settlement, as well as

hearing, on any or all matters in issue. By specifically designating

settlements as a basis for consolidation of multiple proceedings

pending before ALJs, the proposed amendment to Rule 503 recognizes the

importance of omnibus settlements as an alternative to hearings and may

encourage the participants or the ALJs to pursue alternatives.

There is no provision in the regulations for the consolidation of

multiple proceedings that are pending in part before ALJs and in part

before the Commission for disposition of an offer of settlement. Unless

otherwise delegated in its rules, the Commission has the authority, on

its own or upon the filing of a motion with the Commission, to take

appropriate action to waive its rules, consolidate proceedings, or any

other action permitted by law.45 If a settlement is filed that

includes multiple proceedings pending in part before one or more ALJs

or that involves issues in common with other settlements pending before

one or more ALJs, it is the Commission's current practice to consider

any motion to waive its rules as necessary to permit consolidation of

all the proceedings for the Commission to evaluate the

settlement.46

---------------------------------------------------------------------------

\4\518 CFR 385.101(e) and 385.212.

\4\6El Paso Natural Gas Co., 53 FERC  61,014; clarified, 53

FERC  61,187 (1990); Transcontinental Gas Pipe Line Corp., 53 FERC

 61,301 (1990), order on reh'g, 54 FERC  61,072 (1991).

---------------------------------------------------------------------------

The Commission proposes to codify its current practice by amending

the procedures in Rule 602(b) for the submission of offers of

settlement to provide specifically for requests to be filed with the

Commission for consolidation or other appropriate procedural relief to

enable proceedings pending before ALJs to be transmitted to the

Commission for consideration in an omnibus settlement together with

proceedings pending before the Commission. The amendment would add new

paragraph (b)(3) to permit any participant in a proceeding covered by

an offer of settlement submitted under (b)(1) to file a consolidation

request when the settlement covers multiple proceedings pending in part

before the Commission and in part before one or more ALJs. As

indicated, the authority of the ALJ and the Commission to consolidate

multiple proceedings exclusively under their respective jurisdictions

for review in an omnibus settlement is established, respectively, in

Rules 503(a), 101(e), and 212.

In keeping with current practice, under the proposed rule the

Commission would determine whether to have all the related proceedings

brought together, regardless of where they are pending, to consider an

omnibus settlement. To consolidate multiple proceedings in such

situations in the past, the Commission has waived Rule 602's

certification requirements and ordered certification. The Commission

has found that its evaluation of the settlement at that time was

necessary to ensure consistent treatment of the underlying proceedings

and to prevent the limitations on an ALJ's ability to certify

settlements from frustrating the Commission's consideration of

interrelated proceedings, including interrelated settlements, that are

pending before the ALJs.47 The proposed rule gives the Commission

the discretion to deny the request to consolidate and waive the

certification requirements. If necessary, the Commission can order a

hearing in any underlying docket, including a docket that is pending

before an ALJ. Any expediency to be gained by this consolidation

procedure may not outweigh the need for adherence to the procedural

rules or the development of a record on the merits.

---------------------------------------------------------------------------

\4\7El Paso Natural Gas Co., 53 FERC  61,014, at 61,055 (1990);

Transcontinental Gas Pipe Line Corp., 53 FERC  61,301, at 62,123

(1990).

---------------------------------------------------------------------------

The Commission believes that codification of its current practice

is necessary and appropriate to clarify these procedures and establish

their availability. Participants may be encouraged to seek settlements

of interrelated issues that are involved in proceedings both before

ALJs and the Commission without concern for the different

jurisdictions.

B. Rule 602(g): Uncontested Offers of Settlement and Adequacy of the

Record

Rule 602(g) provides for the certification to the Commission of

uncontested settlements filed with an ALJ. If an offer is uncontested,

the ALJ is required under Rule 602(g)(1) to certify to the Commission

the offer of settlement with the hearing record and any related

pleadings. Under the standard set out in Rule 602(g)(3), the Commission

may approve an uncontested offer ``upon a finding that the settlement

appears to be fair and reasonable and in the public interest.''

It is well established that the agreement of the parties alone is

not necessarily a sufficient basis upon which the Commission may

approve an uncontested settlement. Whether disregarding or relying on

the settlement, the Commission must fully consider and justify its

action. The court in Tejas Power Co. v. FERC, (Tejas) held that the

Commission is required to make an independent determination that the

settlement is in the public interest.48 On some issues, an

exercise of the Commission's independent review may be required even

though the parties may not want to develop a record. In these

circumstances, the Commission is entitled to require the development of

an adequate record before it can determine whether an uncontested

settlement is in the public interest.

---------------------------------------------------------------------------

\4\8Tejas Power Co. v. FERC, 908 F.2d 998 (D.C. Cir. 1990).

Specifically, the court found that the issues in that rate

proceeding required the Commission to examine the impact of the

settlement and collect evidence that the consumers' interest would

be served by the agreement, that the parties had adequate bargaining

power to produce an equitable agreement, and that the agreement's

terms are acceptable under the Commission's requirements.

---------------------------------------------------------------------------

As a general proposition, the Commission has in the past and

expects in the future to approve most uncontested settlements as they

are presented by the parties and the trial staff. It is the

Commission's practice to review uncontested settlements as a whole in

determining whether they are in the public interest and to approve them

as presented where important objectives are to be achieved. There are

circumstances, however, when the Commission may be seeking to implement

specific policies in particular types of cases. In these circumstances,

the Commission may direct the parties to make a showing beyond what

would normally accompany an uncontested settlement. If changes in the

terms of the settlement are ordered when the Commission approves the

settlement, it is to conform the settlement to Commission policy to

ensure that the settlement is fair, reasonable, and in the public

interest.

C. Rule 602(h): Contested Settlements

Rule 602(h) provides for processing settlements that are contested

in whole or in part by any participant. Rule 602(h)(1) governs the

Commission's evaluation and decision of contested settlements. Rule

602(h)(2) sets out the standards that govern the ALJ's evaluation of

contested settlements in proceedings before the ALJ and provides for

the certification of the settlement to the Commission for a decision on

the merits of the contested issues.

Under Rule 602(h)(1), the Commission may decide the merits of the

issues in a contested settlement if the record contains substantial

evidence upon which to base a reasoned decision or the Commission

determines there is no genuine issue of material fact. Under Rule

602(h)(2), a settlement that is contested by a party and that is before

an ALJ may be certified to the Commission for a merits decision if,

under Rule 602(h)(2)(ii), no genuine issue of material fact exists. If

genuine issues of material fact exist, the ALJ may still certify the

contested settlement but only if the following three conditions

specified in Rule 602(h)(2)(iii) are met: (1) the parties concur on a

motion for omission of the initial decision, (2) the presiding officer

determines that the record contains substantial evidence from which the

Commission may reach a reasoned decision on the merits of the contested

issues, and (3) the parties have an opportunity to avail themselves of

their rights with respect to the presentation of evidence and cross-

examination of opposing witnesses.

1. Severance of Parties or Issues

The rules permit either the Commission or the ALJ, as appropriate,

to sever contested issues from a settlement and resolve them

separately.49 The uncontested issues may be considered under the

expedited procedures for Commission review of uncontested settlements,

while the contested issues proceed with further review on the merits.

In establishing the settlement rules in 1979, the Commission encouraged

the parties to a settlement to indicate whether parts of the settlement

are severable and to advise the ALJ or the Commission to permit a

prompt decision on the uncontested parts of the settlement.50

Although the rules speak of severing issues, the Commission has also

construed the rules to permit contesting parties to be severed and

given a separate hearing, while approving the settlement for consenting

parties.51

---------------------------------------------------------------------------

\4\9Rule 602(h)(1)(iii) and Rule 602(h)(2)(iv). See, e.g.,

Tennessee Gas Pipeline Co., 31 FERC  61,308 (1985), in which the

Commission approved a settlement in the public interest on issues

where the record was sufficient, but severed an issue for later

decision where the record was insufficient.

\5\0FERC Stats. & Regs. Preambles, 1977-1981  30,061, at

30,433.

\5\1United Gas Pipeline Co., 22 FERC  61,094; reh'g denied, 23

FERC  61,101 (1983); approved sub nom., United Municipal

Distributors Group v. FERC, 732 F.2d 202 (D.C. Cir. 1984); reaff'd,

Arctic Slope Regional Corp. v. FERC, 832 F.2d 158 (D.C. Cir. 1987).

---------------------------------------------------------------------------

The determination whether to sever a party under the regulations is

made, as are other decisions under the regulations, on a case-by-case

basis. The practice of severing contesting parties from settlements has

been adopted when such action preserved the benefits of the settlement

for the consenting parties while affording contesting parties the

opportunity to establish a record upon which their rates could be

based. When certain essential services, such as transportation or

storage, are at issue, the Commission has refused to sever parties.

This is based on the view that it is unduly discriminatory to provide

service to some on different terms, or to withhold service because some

parties choose to exercise their rights to present their positions to

the Commission for decision.52

---------------------------------------------------------------------------

\5\2Tennessee Gas Pipeline Co., 57 FERC  61,360 (1991), reh'g,

59 FERC  61,045 (1992).

---------------------------------------------------------------------------

When parties cannot be severed, the Commission has pointed out the

many options available under its rules and policies that might allow

certification of the contested settlement.53 In such

circumstances, the ALJ can examine the record under the guidelines

previously discussed in this NOPR to determine whether genuine issues

of material fact are contained in the settlement and, if so, whether

the written record was sufficient to resolve the issues. Another option

is to sever the disputed issues of material fact for a decision on the

merits if the parties would continue to support the settlement. Also,

the ALJ could hold a brief, limited hearing to develop enough of a

record on certain issues to permit certification.

---------------------------------------------------------------------------

\5\3Williams Natural Gas Co., 53 FERC 61,060 (1990), 53 FERC

61,231 (1990).

---------------------------------------------------------------------------

While some commenters have urged otherwise, the Commission believes

that codification in the rules of the cases in which it has approved,

or not approved, motions to sever parties would be unnecessary,

cumbersome, and unduly restrictive. The Commission's policy has been

established by case law in these areas. Because the situations tend to

be fact specific, this case-by-case approach is preferred.

Additionally, codification of the precise language to protect a

settlement from severance of any party or issue is unnecessary and

unduly restrictive. Parties may prevent severance of issues by

expressly making the settlement a non-severable package. If an issue is

contested in those settlements, the Commission may consider whether to

approve the settlement as to all parties that do not contest that issue

and to require a decision on the merits on that issue as to the

contesting parties.54 In some cases, settlements may provide that

the terms are to apply only to those parties electing to be

bound.55

---------------------------------------------------------------------------

\5\4United Municipal Distributors Group v. FERC, 732 F.2d 202,

208 (D.C. Cir. 1984).

\5\5However, the Commission has imposed limits on the ability of

a regulated company to coerce parties into waiving their statutory

rehearing and appeal rights in a settlement by denying them certain

services if they seek rehearing or judicial review of an order

accepting a settlement. Tennessee Gas Pipeline Co., 57 FERC 61,360,

at 62,167-68 (1991), order on reh'g, 59 FERC 61,045, at 61,172-74

(1992); ANR Pipeline Co., 59 FERC 61,347 (1992).

---------------------------------------------------------------------------

As indicated, the existing rules do not provide for the severance

of contesting parties, but only for the severance of contested issues.

Thus, the existing rules do not reflect existing practice. The

Commission proposes to modify those provisions to permit the ALJ or the

Commission to sever contesting parties as well. As provided in the

rules, the uncontested portions would be decided in accordance with the

procedures for uncontested settlements under Rule 602(g). Accordingly,

Rules 602(h)(1)(ii) and (iii) and Rule 602(h)(2)(iv) would be changed

by adding the phrase ``contesting parties or'' before the discussion

beginning with ``contested issues''.

2. Rule 602(h)(2): Certification of Contested Settlements

Rule 602(h)(2) sets out the procedures by which the ALJ may certify

a contested settlement to the Commission. The Commission does not

propose to change the general framework it has established in Rule

602(h)(2). As discussed below under the various certification

requirements, the ALJ fulfills an important function in transmitting to

the Commission a settlement that, if it raises material issues,

contains an adequate record on which the Commission can then base a

decision on the merits.

a. Genuine Issue of Material Fact. Under paragraph (ii) of Rule

602(h)(2), the ALJ determines whether a settlement that is contested by

any participant contains a genuine issue of material fact. If the

settlement does not, the ALJ may certify the settlement directly to the

Commission. If the settlement contains a genuine issue of material

fact, the ALJ may certify the settlement only if the three conditions

under paragraph (iii) are met.

The Commission has recognized the potential roadblocks to the

expedited resolution of settlements created by claims of materiality of

issues in a settlement before an ALJ. It has never been Commission

policy to provide a forum for litigation of each and every contested

issue at the expense of another reasonable resolution of disputed

issues. Not every fact is material, and the ALJ should let a settlement

promptly go to the Commission if no material facts are found. The

Commission has provided guidance for narrowing the scope of contested

issues and preventing a hearing from covering unnecessarily broad

issues by requiring objections raised to a settlement to be closely

scrutinized.56

---------------------------------------------------------------------------

\5\6Williams Natural Gas Co., 53 FERC 61,060, at 61,187 and 53

FERC 61,231, at 61,966-67 (1990).

---------------------------------------------------------------------------

However, the Commission believes that measures could be taken to

improve the ALJ's ability to scrutinize contested issues for their

materiality and factual content. In this regard, the Commission

proposes to modify Rule 602(f) by adding the requirement that

contesting parties submit affidavits with their initial comments

detailing any genuine issues of material fact that they contend exist.

Reply comments, including responding affadavits would also be allowed.

The ALJs and the Commission will thus have necessary information

concerning materiality at the outset of the settlement review process.

This may avoid the delays created later in the process when the ALJ or

the Commission may be required to have further proceedings to sort

through claims and determine materiality of those claims.

To ensure the completeness of the information to be provided by

contesting parties in the affidavits, the parties would include

specific references to documents, testimony, or other items included in

the offer of settlement as required under Rule 602(c)(iii) that are

related to and support the claims of the contesting party that there

are genuine issues of material fact in the settlement. This requirement

would also extend to documents, testimony, or other matters that may

not have been included in the settlement, but that are relevant to

support the claims of the contesting party.

This change in the regulations makes the consideration of a

contested settlement comparable to the practice in federal court for

ruling on motions for summary judgment. Under Rule 56(e) of the Federal

Rules of Civil Procedure, an affidavit must identify certain facts

showing that a genuine issue of material fact exists for trial.57

---------------------------------------------------------------------------

\5\7Fed. R. Civ. P. 56(e).

---------------------------------------------------------------------------

The Commission does not propose to modify subparagraph (ii) of Rule

602(h)(2) to narrow or limit by rule the definition of what constitutes

a genuine issue of material fact. The determination of what is a

material fact depends on what is at issue in the case. The definition

is sufficiently flexible to permit the ALJ to identify a material fact

based on the substantive issues in the case and to determine if the

record is adequate. The ALJ also has the ability to develop the record

further, if it is inadequate, and then to certify the settlement to the

Commission. Rather than amend the standard under which the ALJs

currently operate in determining the genuineness of any disputed facts

and the sufficiency of a record, the Commission believes that its

proposal to amend Rule 602(f) to require a strong showing by contesting

parties is a sufficient barrier to superficial claims of material fact

that can block certification of a settlement to the Commission.

Contrary to the request of some commenters, the Commission does not

propose to modify the rule to require the ALJ to issue an initial

decision in all settlements. This essentially would eliminate the

certification process and the Commission's procedures for ruling on all

settlements either under the public interest standard or, if contested,

on the merits. Under Section 557(b) of the Administrative Procedure Act

and Rule 708, an ALJ is only required to issue an initial decision in

those proceedings in which the ALJ presided over the taking of

evidence, and that may be waived under Rule 710 upon motion of the

parties. To delay the Commission's review of all settlements until the

parties seek review on exceptions of a mandatory initial decision not

only is inconsistent with the APA, it establishes an additional

roadblock to the Commission's ultimate review of settlements.

b. Rule 602(h)(2)(iii): Three Conditions for Certification if

Genuine Issues of Material Fact Exist. Under current Rule

602(h)(2)(iii), the ALJ may certify an offer of settlement or part of

any offer of settlement even if the settlement contains genuine issues

of material fact. In these circumstances, the ALJ is entitled to

certify an offer that is contested by a party if all of the following

conditions, contained in subparts (A), (B), and (C), are met:

(A) The parties concur on a motion for omission of the initial

decision as provided in Rule 710;

(B) The presiding officer determines that the record contains

substantial evidence from which the Commission may reach a reasoned

decision on the merits of the contested issues; and

(C) The parties have an opportunity to avail themselves of their

rights with respect to the presentation of evidence and cross-

examination of opposing witnesses.

If any one of these conditions is not present, the judge may direct

further procedures as deemed appropriate, including certification of

the settlement at a later time if the conditions are then met.

Modifications to conditions (A) and (C) are necessary and

appropriate. The barriers to certification by the ALJ under the rules

are at times formidable. The ALJs, under Rule 602(h)(2), have less

discretion than the Commission in reviewing offers of settlement. These

limitations on the ALJ's ability to certify settlements can frustrate

the Commission's ability to review the contested settlements on the

merits. As discussed previously, the Commission in particular cases has

waived the certification conditions to permit immediate transfer of a

settlement, or parts of a settlement, to the Commission.58 By

refusing to agree to a waiver request, a single party can delay a

settlement and prevent the Commission's review on the merits until an

initial decision issues, even though the settlement has broad-based

support and there exists a sufficient record on the disputed issues of

fact. Nevertheless, unless all parties agree or the Commission

otherwise waives the initial decision under Rule 710, the settlement

cannot be certified to the Commission without the initial

decision.59

---------------------------------------------------------------------------

\5\8Williams Natural Gas Co., 53 FERC 61231, at 61,967 (1990);

El Paso Natural Gas Co., 53 FERC 61,014, at 61,055 (1990).

\5\9Williams Natural Gas Co., 53 FERC 61,060, at 61,185, order

on reconsideration, 53 FERC 61,231, at 61,967 (1990).

---------------------------------------------------------------------------

Condition (C) allows a single party to insist on cross-examination

of all opposing witnesses or, simply, to present additional evidence.

Again, this could slow or stall the certification of the settlement,

even though the parties have presented evidence and the ALJ believes

the record is sufficient for the Commission to reach a decision.

Conditions (A), (B), and (C) in paragraph (iii) of Rule 602(h)(2)

were designed to ensure that, in providing the ALJ with the authority

to certify a contested settlement or a portion of a settlement, a

sufficiently developed record existed on which a reasoned decision

could be based.60 As long as there is substantial evidence in the

record for a decision by the Commission on the contested issues and

each of the participants has been afforded an opportunity to be heard,

no further proceedings before the ALJ are necessary and the ALJ is

permitted by the rules to certify the settlement to the

Commission.61

---------------------------------------------------------------------------

\6\0Order No. 32, FERC Stats. & Regs. Preambles 1977-1981

30,062, at 30,431-32.

\6\1Id. at 30,435-36.

---------------------------------------------------------------------------

In establishing these rules, the Commission intended to reduce the

length of time required for processing settlements to encourage

participants in proceedings to seek the benefits of the settlement

process for the expeditious resolution of contested issues.

Under condition (B), the ALJ may not certify a contested settlement

unless the ALJ determines that the record contains substantial evidence

from which the Commission may reach a reasoned decision on the merits

of the contested issues. The Commission believes that this condition

should be the core of the ALJ's decision to certify a contested

settlement. As noted, this is consistent with the Commission's

intention in establishing the certification requirements. Moreover, it

conforms to Rule 602(h)(1)(i), requiring that the Commission may decide

the merits of any contested issues in a settlement before it for

evaluation if the record contains substantial evidence or else there is

no genuine issue of material fact.

Thus, if there are genuine issues of material fact and the record

contains substantial evidence to allow for the decision on the merits,

certification of the settlement should be permitted at the ALJ's

discretion.

With this background in mind, the Commission proposes to make the

following changes to conditions (A) and (C). The Commission proposes to

modify the regulations to permit the ALJ to certify a settlement if

there is less than unanimous concurrence of the parties under condition

(A) to a motion filed under Rule 710 for omission of the initial

decision. To accomplish this, the Commission proposes to amend both

condition (A) and Rule 710 to delegate to the ALJ the authority to

determine that, if a motion filed under Rule 710 has less than

unanimous concurrence, omission of the initial decision is appropriate

to the same extent the Commission is able to make that determination

under Rule 710. The Commission believes that delegating authority to

the ALJ to dispose of the Rule 710 motion when omission of the initial

decision is requested pursuant to the certification requirement in

condition (A) of Rule 602(h)(2)(iii) will streamline the certification

process.

In reaching its determination, the Commission relies on a

functional test in which it examines the significance of the issues

raised by the settlement, the substantial record evidence, and the

importance of a prompt Commission decision.62 The Commission

proposes that the same requirements and considerations govern the ALJ.

---------------------------------------------------------------------------

\K\Id.

---------------------------------------------------------------------------

The Commission has concluded that condition (C) is subsumed by

condition (B) and proposes to eliminate condition (C) entirely. This is

consistent with authority delegated to the ALJ when the Commission

promulgated condition (C) and with Commission practice and policy

concerning the use of cross-examination. In Order No. 32-A, the

Commission denied that condition (C) requires each party to a

proceeding to have the opportunity to present evidence and cross-

examine opposing witnesses. Rather,

the rule assures only the opportunity for all parties to avail

themselves of such rights as they may have to present evidence and

to cross-examine opposing witnesses. The rule leaves to the

presiding officer, based on the nature of the contested issues and

the state of the record, to determine whether due process requires

the presentation of evidence and cross-examination prior to

certification for Commission resolution of a contested settlement.

The opportunity to present evidence and to cross-examine is not

always a matter of right. It is for the presiding officer to apply

the law in deciding whether certification is appropriate. This rule

does not provide any greater rights to those contesting a settlement

than they had previously.63

---------------------------------------------------------------------------

\6\38 FERC 61,160, at 61,603-04 (1979).

In considering the scope of an ALJ's authority to consider a cross-

examination request pursuant to condition (C), the Commission has

stated that its rules permit cross-examination only as necessary to

assure true and full disclosure of the facts.64 If the record is

developed, the ALJ may deny a request for cross-examination.65 As

the Commission stated, answering written testimony generally will be

sufficient to adequately ventilate the issues. If not, the ALJ could

ensure that the record is adequately developed by according the

participants the opportunity to put their views in the record. In these

circumstances, condition (C) serves no useful purpose in the

certification process. Rather, the due process considerations that it

covers are subsumed in condition (B), inasmuch as the ALJ, in

determining whether the record contains substantial evidence from which

the Commission may reach a reasoned decision on the merits of the

contested issues, must conclude that all participants have had the

opportunity to make their views known.

---------------------------------------------------------------------------

\6\4Williams Natural Gas Co., 53 FERC 61,231, at 61,966-67

(1990).

\6\518 CFR 385.505.

---------------------------------------------------------------------------

D. Deadlines

The Commission does not propose to adopt specific deadlines to

govern the determinations to be made either by the Commission or the

ALJ under Rules 602(g) and (h). Additional measures have been taken in

this order to streamline the process further by giving the ALJ the

discretion to remove certain roadblocks to certifying a contested

settlement to the Commission on the merits. Neither the ALJ nor the

Commission should be bound by the restrictions of deadlines, which may

impede the ability to ensure the adequacy of the record or the issuance

of an appropriate decision.

VI. Written Comment Procedure

The Commission invites all interested persons to submit written

data, views, and other information concerning the proposals in this

NOPR. All comments in response to this NOPR should be submitted to the

Secretary of the Federal Energy Regulatory Commission, 825 North

Capitol Street, N.E., Washington, D.C. 20426, and should refer to

Docket No. RM91-12-000. An original and fourteen copies should be filed

with the Commission February 2, 1995. Commenters are urged to double

space their comments and to provide a heading for each issue. Written

submissions will be placed in the Commission's public files and will be

available for inspection during regular business hours in the

Commission's Public Reference Room, Room 3308, 941 North Capitol

Street, N.E., Washington, D.C. 20426.

VII. Administrative Findings

A. Regulatory Flexibility Act

The Regulatory Flexibility Act (RFA)66 generally requires the

Commission to describe the impact that a proposed rule would have on

small entities or to certify that the rule will not have a significant

economic impact on a substantial number of small entities. The

Commission is not required to make an analysis if a proposed rule will

not have such an impact.67

---------------------------------------------------------------------------

\6\65 U.S.C. 601-612.

\6\75 U.S.C. 605(b).

---------------------------------------------------------------------------

Pursuant to section 605(b) of the RFA, the Commission certifies

that the proposed amendments, if promulgated, will not have a

significant economic impact on a substantial number of small entities.

B. Environmental Review

The Commission is not preparing an environmental assessment or

environmental impact statement in this proceeding because the proposed

amendments are procedural only, changing only the Commission's rules of

practice and procedure, and therefore have no significant effect on the

human environment.68

---------------------------------------------------------------------------

\6\8Section 380.4(a)(2)(ii) of the Commission's regulations

categorically exempts from environmental review Commission proposals

for promulgation of rules that are clarifying, corrective, or

procedural, or that do not substantially change the effect of the

regulations being amended. See 18 CFR 380.4(a)(2)(ii).

---------------------------------------------------------------------------

C. Information Collection Requirements

Office of Management and Budget (OMB) regulations require OMB to

approve certain information collection requirements imposed by agency

rules.69 However, this rule contains no new information collection

requirements in Part 385 and therefore is not subject to OMB approval.

---------------------------------------------------------------------------

\6\95 CFR 1320.13.

---------------------------------------------------------------------------

List of Subjects in 18 CFR Part 385

Administrative practice and procedure, Electric power, Penalties,

Pipelines, Reporting and recordkeeping requirements.

By direction of the Commission.

Lois D. Cashell,

Secretary.

In consideration of the foregoing, the Commission proposes to amend

Part 385, Chapter I, Title 18, Code of Federal Regulations, as set

forth below.

PART 385--RULES OF PRACTICE AND PROCEDURE

1. The authority citation for Part 385 is revised to read as

follows:

Authority: 5 U.S.C. 551-557; 15 U.S.C. 717-717z, 3301-3432; 16

U.S.C. 791a-825r, 2601-2645; 31 U.S.C. 9701; 42 U.S.C. 7101-7352; 49

U.S.C. 60502; 49 App. U.S.C. 1-85.

2. In Sec. 385.503, paragraph (a) is revised to read as follows:

Sec. 385.503 Consolidation, severance and extension of close-of-record

date by Chief Administrative Law Judge (Rule 503).

(a) The Chief Administrative Law Judge may, on motion or otherwise,

order proceedings pending under this subpart consolidated for hearing

on, or settlement of, any or all matters in issue in the proceedings,

or order the severance of proceedings or issues in a proceeding. The

order may be appealed to the Commission pursuant to Rule 715.

* * * * *

3. In Sec. 385.504, paragraph (b)(7) is revised to read as follows:

Sec. 385.504 Duties and powers of presiding officers (Rule 504).

* * * * *

(b) Powers. * * *

(7) Hold conferences of the participants, as provided in Subpart F

of this part, including for the purpose of considering the use of

alternative dispute resolution procedures;

* * * * *

4. In Sec. 385.601, paragraph (a) is revised to read as follows:

Sec. 385.601 Conferences (Rule 601).

(a) Convening. The Commission or other decisional authority, upon

motion or otherwise, may convene a conference of the participants in a

proceeding at any time for any purpose related to the conduct or

disposition of the proceeding, including submission and consideration

of offers of settlement or the use of alternative dispute resolution

procedures.

* * * * *

5. In Sec. 385.602, paragraphs (b)(3) and (f)(4) are added and

paragraphs (h)(1)(ii) introductory text, (h)(1)(iii), (h)(2)(iii),

(h)(2)(iv) are revised to read as follows:

Sec. 385.602 Submission of settlement offers (Rule 602).

* * * * *

(b) Submission of offer. * * *

(3) If an offer of settlement pertains to multiple proceedings that

are in part pending before the Commission and in part set for hearing,

any participant may by motion request the Commission to consolidate the

multiple proceedings and to provide any other appropriate procedural

relief for purposes of disposition of the settlement.

* * * * *

(f) Comments. * * *

(4) Any comment that contests an offer of settlement by alleging a

dispute as to a genuine issue of material fact must include an

affidavit detailing any genuine issue of material fact by specific

reference to documents, testimony, or other items included in the offer

of settlement, or items not included in the settlement, that are

relevant to support the claim. Reply comments may include responding

affidavits.

* * * * *

(h) Contested offers of settlement.

(1) * * *

(ii) If the Commission finds that the record lacks substantial

evidence or that the contesting parties or contested issues can not be

severed from the offer of settlement, the Commission will:

* * * * *

(iii) If contesting parties or contested issues are severable, the

contesting parties or uncontested portions may be severed. The

uncontested portions will be decided in accordance with paragraph (g)

of this section.

(2) * * *

(iii) Any offer of settlement or part of any offer of settlement

may be certified to the Commission, if:

(A) The parties concur on a motion for omission of the initial

decision as provided in Rule 710, or, if all parties do not concur in

the motion, the presiding officer determines that omission of the

initial decision is appropriate under Rule 710(d), and

(B) The presiding officer determines that the record contains

substantial evidence from which the Commission may reach a reasoned

decision on the merits of the contested issues.

(iv) If any contesting parties or contested issues are severable,

the uncontested portions of the settlement may be certified immediately

by the presiding officer to the Commission for decision, as provided in

paragraph (g) of this section.

* * * * *

6. In Subpart F, Secs. 385.604 through 385.606 are added to read as

follows:

Sec. 385.604 Alternative means of dispute resolution (Rule 604).

(a) Applicability. (1) Participants may, subject to the limitations

of paragraph (a)(2) of this section, use alternative means of dispute

resolution to resolve all or part of any pending matter if the

participants agree. The alternative means of dispute resolution

authorized under Subpart F of this part will be voluntary procedures

that supplement rather than limit other available dispute resolution

techniques.

(2) Except as provided in paragraph (a)(3) of this section, the

decisional authority will not consent to use of an alternative dispute

resolution proceeding if:

(i) A definitive or authoritative resolution of the matter is

required for precedential value;

(ii) The matter involves or may bear upon significant questions of

policy that require additional procedures before a final resolution may

be made, and the proceeding would not likely serve to develop a

recommended policy;

(iii) Maintaining established policies is of special importance;

(iv) The matter significantly affects persons or organizations who

are not parties to the proceeding;

(v) A full public record of the proceeding is important, and a

dispute resolution proceeding cannot provide a record; or

(vi) The Commission must maintain continuing jurisdiction over the

matter with authority to alter the disposition of the matter in the

light of changed circumstances, and a dispute resolution proceeding

would interfere with the Commission's fulfilling that requirement.

(3) If one or more of the factors outlined in paragraph (a)(2) of

this section is present, alternative dispute resolution may

nevertheless be used if the alternative dispute resolution proceeding

can be structured to avoid the identified factor or if other concerns

significantly outweigh the identified factor.

(4) A determination to use or not to use a dispute resolution

proceeding under Subpart F of this part is not subject to judicial

review.

(5) Settlement agreements reached through the use of alternative

dispute resolution pursuant to Subpart F of this part will be subject

to the provisions of Rule 602, unless the decisional authority, upon

motion or otherwise, orders a different procedure.

(b) Definitions. For the purposes of Subpart F of this part:

(1) Alternative means of dispute resolution means any procedure

that is used, in lieu of an adjudication, to resolve issues in

controversy, including but not limited to, settlement negotiations,

conciliation, facilitation, mediation, factfinding, minitrials, and

arbitration, or any combination thereof;

(2) Award means any decision by an arbitrator resolving the issues

in controversy;

(3) Dispute resolution communication means any oral or written

communication prepared for the purposes of a dispute resolution

proceeding, including any memoranda, notes or work product of the

neutral, parties or non-party participant. A written agreement to enter

into a dispute resolution proceeding, or a final written agreement or

arbitral award reached as a result of a dispute resolution proceeding,

is not a dispute resolution communication;

(4) Dispute resolution proceeding means any alternative means of

dispute resolution that is used to resolve an issue in controversy in

which a neutral may be appointed and specified parties participate;

(5) In confidence means information is provided:

(i) With the expressed intent of the source that it not be

disclosed, or

(ii) Under circumstances that create a reasonable expectation on

behalf of the source that the information will not be disclosed;

(6) Issue in controversy means an issue which is or is anticipated

to be material to a decision in a proceeding before the Commission and

which is the subject of disagreement between participants who would be

substantially affected by the decision or between the Commission and

any such participants;

(7) Neutral means an individual who, with respect to an issue in

controversy, functions specifically to aid the parties in resolving the

controversy;

(8) Participants in a dispute resolution proceeding that is used to

resolve an issue in controversy in a proceeding involving an

application for a license or exemption to construct, operate, and

maintain a hydroelectric project pursuant to the Federal Power Act or

the Public Utility Regulatory Policies Act shall include such state and

federal agencies and Indian tribes as have statutory roles or a direct

interest in such hydroelectric proceedings.

(c) Neutrals. (1) A neutral may be a permanent or temporary officer

or employee of the Federal Government (including an administrative law

judge), or any other individual who is acceptable to the participants

to a dispute resolution proceeding. A neutral must have no official,

financial, or personal conflict of interest with respect to the issues

in controversy, except that a neutral who is not a government employee

may serve if the interest is fully disclosed in writing to all

participants and all participants agree.

(2) A neutral serves at the will of the participants, unless

otherwise provided.

(3) Neutrals may be selected from among the Commission's

administrative law judges or other employees, from rosters kept by the

Federal Mediation and Conciliation Service, the Administrative

Conference of the United States, the American Arbitration Association,

or from any other source.

(d) Submission of proposal to use alternative means of dispute

resolution. (1) The participants may at any time submit a written

proposal to use alternative means of dispute resolution to resolve all

or part of any matter in controversy or anticipated to be in

controversy before the Commission.

(2) For matters set for hearing under Subpart E of this part, a

proposal to use alternative means of dispute resolution other than

binding arbitration must be filed with the presiding administrative law

judge.

(3) A proposal to use binding arbitration must be filed with the

Secretary for consideration by the Commission.

(4) For all other matters, a proposal to use alternative means of

dispute resolution may be filed with the Secretary for consideration by

the appropriate decisional authority.

(5) The appropriate decisional authority will issue an order,

approving or denying, under the guidelines in Rule 604(a)(2) and (3), a

proposal to use alternative means of dispute resolution. Denial of a

proposal to use alternative dispute resolution will be in the form of

an order and will identify the specific reasons for the denial. A

proposal to use alternative dispute resolution is deemed approved

unless an order denying approval is issued within 30 days after the

proposal is filed.

(6) Any request to modify a previously-approved ADR proposal must

follow the same procedure used for the initial approval.

(e) Contents of proposal. A proposal to use alternative means of

dispute resolution must be in writing and include:

(1) A general identification of the issues in controversy intended

to be resolved by the proposed alternative dispute resolution method,

(2) A description of the alternative dispute resolution method(s)

to be used,

(3) The signatures of all participants or evidence otherwise

indicating the consent of all participants; and

(4) A certificate of service pursuant to Rule 2010(h).

(f) Monitoring the alternative dispute resolution proceeding. The

decisional authority may order reports on the status of the alternative

dispute resolution proceeding at any time.

(g) Termination of alternative dispute resolution proceeding. (1)

The decisional authority, upon motion or otherwise, may terminate any

alternative dispute resolution proceeding under Rule 604 or 605 by

issuing an order to that effect.

(2) A decision to terminate an alternative dispute resolution

proceeding is not subject to judicial review.

Sec. 385.605 Arbitration (Rule 605).

(a) Authorization of arbitration. (1) The participants may at any

time submit a written proposal to use binding arbitration under the

provisions of Rule 605 to resolve all or part of any matter in

controversy, or anticipated to be in controversy, before the

Commission.

(2) The proposal must be submitted as provided in Rule 604(d).

(3) The proposal must be in writing and contain the information

required in Rule 604(e).

(4) An arbitration proceeding under this rule may be monitored and

terminated as provided in Rule 604(d) and (g).

(5) No person may be required to consent to arbitration as a

condition of entering into a contract or obtaining a benefit. All

interested parties must expressly consent before arbitration may be

used.

(b) Arbitrators. (1) The participants to an arbitration proceeding

are entitled to select the arbitrator.

(2) The arbitrator must be a neutral who meets the criteria of a

neutral under Rule 604(c).

(c) Authority of arbitrator. An arbitrator to whom a dispute is

referred under this section may:

(1) Regulate the course of and conduct arbitral hearings;

(2) Administer oaths and affirmations;

(3) Compel the attendance of witnesses and the production of

evidence to the extent the Commission is authorized by law to do so;

and

(4) Make awards.

(d) Arbitration proceedings. (1) The arbitrator will set a time and

place for the hearing on the dispute and must notify the participants

not less than 5 days before the hearing.

(2) Any participant wishing that there be a record of the hearing

must:

(i) Prepare the record;

(ii) Notify the other participants and the arbitrator of the

preparation of the record;

(iii) Furnish copies to all identified participants and the

arbitrator; and

(iv) Pay all costs for the record, unless the participants agree

otherwise or the arbitrator determines that the costs should be

apportioned.

(3) (i) Participants to the arbitration are entitled to be heard,

to present evidence material to the controversy, and to cross-examine

witnesses appearing at the hearing to the same extent as in a

proceeding under Subpart E of this part;

(ii) The arbitrator may, with the consent of the participants,

conduct all or part of the hearing by telephone, television, computer,

or other electronic means, if each participant has an opportunity to

participate.

(iii) The hearing must be conducted expeditiously and in an

informal manner.

(iv) The arbitrator may receive any oral or documentary evidence,

except that irrelevant, immaterial, unduly repetitious, or privileged

evidence may be excluded by the arbitrator.

(v) The arbitrator will interpret and apply relevant statutory and

regulatory requirements, legal precedents, and policy directives.

(4) No interested person will make or knowingly cause to be made to

the arbitrator an unauthorized ex parte communication relevant to the

merits of the proceeding, unless the participants agree otherwise. If a

communication is made in violation of this prohibition, the arbitrator

will ensure that a memorandum of the communication is prepared and made

a part of the record, and that an opportunity for rebuttal is allowed.

Upon receipt of such communication, the arbitrator may require the

offending participant to show cause why the claim of the participant

should not be resolved against the participant as a result of the

improper conduct.

(5) The arbitrator will make the award within 30 days after the

close of the hearing or the date of the filing of any briefs authorized

by the arbitrator, whichever date is later, unless the participants and

the arbitrator agree to some other time limit.

(e) Arbitration awards. (1)(i) The award in an arbitration

proceeding under Subpart F of this part will include a brief, informal

discussion of the factual and legal basis for the award.

(ii) The prevailing participants must file the award with the

Commission, along with proof of service on all participants.

(2) The award in an arbitration proceeding will become final 30

days after it is filed, unless the award is vacated. The Commission,

upon motion or otherwise, may extend the 30-day period for one

additional 30-day period by issuing a notice of the extension before

the end of the first 30-day period.

(3) A final award is binding on the participants to the arbitration

proceeding.

(4) An award may not serve as an estoppel in any other proceeding

for any issue that was resolved in the proceeding. The award also may

not be used as precedent or otherwise be considered in any factually

unrelated proceeding or in any other arbitration proceeding.

(f) Vacating an award. (1) Within 10 days after the award is filed,

any person may file a request with the Commission to vacate an

arbitration award and must serve the request to vacate on all

participants. Responses to such a request are due 10 days after the

request is filed.

(2) Upon request or otherwise, the Commission may vacate any award

issued under this rule before the award becomes final by issuing an

order to that effect, in which case the award will be null and void.

(3) Rule 2202 regarding separation of functions applies with

respect to a decision to vacate an arbitration award.

(4) If the Commission vacates an award under paragraph (f)(3) of

this section, a party to the arbitration may, within 30 days of the

action, petition the Commission for an award of attorney fees and

expenses incurred in connection with the arbitration proceeding. The

Commission will award the petitioning party those fees and expenses

that would not have been incurred in the absence of the arbitration

proceeding, unless the Commission finds that special circumstances make

the award unjust.

(5) An arbitration award vacated under this paragraph will not be

admissible in any proceeding relating to the issues in controversy with

respect to which the award was made.

(6) A decision by the Commission to vacate an arbitration award is

not subject to rehearing or judicial review.

Sec. 385.606 Confidentiality in dispute resolution proceedings (Rule

606).

(a) Except as provided in paragraphs (d) and (e) of this section, a

neutral in a dispute resolution proceeding shall not voluntarily

disclose, or through discovery or compulsory process be required to

disclose, any information concerning any dispute resolution

communication or any communication provided in confidence to the

neutral, unless:

(1) All participants in the dispute resolution proceeding and the

neutral consent in writing;

(2) The dispute resolution communication has already been made

public;

(3) The dispute resolution communication is required by statute to

be made public, but a neutral should make the communication public only

if no other person is reasonably available to disclose the

communication; or

(4) A court determines that the testimony or disclosure is

necessary to:

(i) Prevent a manifest injustice;

(ii) Help establish a violation of law; or

(iii) Prevent harm to the public health or safety of sufficient

magnitude in the particular case to outweigh the integrity of dispute

resolution proceedings in general by reducing the confidence of

participants in future cases that their communications will remain

confidential.

(b) A participant in a dispute resolution proceeding shall not

voluntarily disclose, or through discovery or compulsory process be

required to disclose, any information concerning any dispute resolution

communication, unless:

(1) All participants to the dispute resolution proceeding consent

in writing;

(2) The dispute resolution communication has already been made

public;

(3) The dispute resolution communication is required by statute to

be made public;

(4) A court determines that the testimony or disclosure is

necessary to:

(i) Prevent a manifest injustice;

(ii) Help establish a violation of law; or

(iii) Prevent harm to the public health and safety of sufficient

magnitude in the particular case to outweigh the integrity of dispute

resolution proceedings in general by reducing the confidence of

participants in future cases that their communications will remain

confidential; or

(5) The dispute resolution communication is relevant to determining

the existence or meaning of an agreement or award that resulted from

the dispute resolution proceeding or to the enforcement of the

agreement or award.

(c) Any dispute resolution communication that is disclosed in

violation of paragraphs (a) or (b) of this section shall not be

admissible in any proceeding relating to the issues in controversy with

respect to which the communication was made.

(d) The participants may agree to alternative confidential

procedures for disclosures by a neutral. The participants must inform

the neutral before the commencement of the dispute resolution

proceeding of any modifications to the provisions of paragraph (a) of

this section that will govern the confidentiality of the dispute

resolution proceeding. If the participants do not so inform the

neutral, paragraph (a) of this section shall apply.

(e) If a demand for disclosure, by way of discovery request or

other legal process, is made upon a neutral regarding a dispute

resolution communication, the neutral will make reasonable efforts to

notify the participants of the demand. Any participant who receives the

notice and within 15 calendar days does not offer to defend a refusal

of the neutral to disclose the requested information waives any

objection to the disclosure.

(f) Nothing in Rule 606 prevents the discovery or admissibility of

any evidence that is otherwise discoverable, merely because the

evidence was presented in the course of a dispute resolution

proceeding.

(g) Paragraphs (a) and (b) of this section do not preclude

disclosure of information and data that are necessary to document an

agreement reached or order issued pursuant to a dispute resolution

proceeding.

(h) Paragraphs (a) and (b) of this section do not prevent the

gathering of information for research and educational purposes, in

cooperation with other agencies, governmental entities, or dispute

resolution programs, so long as the participants and the specific

issues in controversy are not identifiable.

(i) Paragraphs (a) and (b) of this section do not prevent use of a

dispute resolution communication to resolve a dispute between the

neutral in a dispute resolution proceeding and a participant in the

proceeding, so long as the communication is disclosed only to the

extent necessary to resolve the dispute.

(j) Nothing in this section precludes parties from seeking

privileged treatment for documents under section 388.112 of this

chapter.

7. In Sec. 385.710, paragraph (d) is added to read as follows:

Sec. 385.710 Waiver of the initial decision (Rule 710).

* * * * *

(d) Waiver by presiding officer. A motion for waiver of the initial

decision, requested for the purpose of certification of a contested

settlement pursuant to Rule 602(h)(2)(iii)(A), may be filed with, and

decided by, the presiding officer. If all parties join in the motion,

the presiding officer will grant the motion. If all parties do not join

in the motion, the motion is denied unless the presiding officer grants

the motion within 30 days of filing the written motion or presenting an

oral motion. The contents of any motion filed under this paragraph must

comply with the requirements in paragraph (b) of this section. A motion

may be oral or written, and may be made whenever appropriate for the

consideration of the presiding officer.

Note: This appendix will not be published in the Code of Federal

Regulations.

Appendix

Alternative Dispute Resolution

Docket No. RM91-12-000

Commenters

American Gas Association

American Public Power Association

Associated Gas Distributors

Center for Dispute Settlement and Donelan, Cleary, Wood & Maser,

P.C.

Colorado Interstate Gas Company and ANR Pipeline Company

Colorado River Energy Distributors Association

Enron Interstate Pipelines

Federal Energy Bar Association

Indicated Producers

Interstate Natural Gas Association of America

Natural Gas Pipeline Company of America

Pacific Gas and Electric Company

The Process Gas Consumers Group,

The American Iron and Steel Institute,

The Chemical Manufacturers Association, and The Georgia

Industrial Group (The Industrials)

Southern California Gas Company and Pacific Interstate Company

Tennessee Gas Pipeline Company

Texas Eastern Transmission Corporation,

Panhandle Eastern Pipe Line Company,

Trunkline Gas Company and Algonquin Gas Transmission Company

(PEC Pipeline Group)

City of Willcox, Arizona

Williams Natural Gas Company

[FR Doc. 94-28447 Filed 11-17-94; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.